USCMS EMU - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

USCMS EMU

Description:

No particular piece of tooling is used at 100%. Winding Machine: 1 panel/3 hours ... During stoppage many subassemblies can be done by the MP9 work-force. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 16
Provided by: giorgioap
Category:
Tags: emu | uscms | inspection

less

Transcript and Presenter's Notes

Title: USCMS EMU


1
US-CMS EMU Chamber Factory Production Readiness
Review December 16 1999
2
US CMS EMU Introduction
  • Fermilab has responsibility for the design and
    procurement of the components for all the CMS_EMU
    chambers
  • Fermilab has responsibility for the assembly of
    the ME234/2 Chambers
  • ME234/2 Subject of this Review
  • ME2/1 Assembled at PNPI (Russia)
  • ME3/1 Assembled at PNPI (Russia)
  • ME1/2 Assembled at IHEP (China)
  • ME1/3 Assembled at IHEP (China)
  • Fermilab has responsibility for the shipment of
    kits and critical tooling to PNPI and China IHEP.

3
US CMS EMU Introduction
4
US CMS EMU Introduction
  • Production Readiness Review
  • Committee
  • J. Kerby Chairperson
  • J. Carson
  • K. Kephart
  • D. Denisov
  • F. Nobrega
  • M. Lindgreen

5
US CMS EMU Factory Organization - Drawings
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
6
US CMS EMU - Factory Organization Procurement
Inspection
Project Management
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
7
US CMS EMU - Factory Organization Kit Processing
Project Management
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
8
US CMS EMU - Factory Organization QA/QC
Monitoring
Project Management
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
9
US CMS EMU Introduction
  • US CMS and CMS-EMU Organization Structure

L1 Managers D.Green E.Temple
L2 Manager G.Mitselmakher
L3 Electronics T.Ling
L3 Chamber A.Korytov
L3 Infrastructure D. Loveless
FNAL G.Apollinari N.Chester
10
PNPI Site
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
UC Site
large CSCs
large CSCsElectronics, tested installation/commis
sioning
Fermilab Site - panel production - large CSC
assembly
CERN
large CSCsElectronics, tested installation/commis
sioning
large CSCs
UF Site
Procurement
etc.
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
frames
guard strips
gap bars
IHEP Site
wire fix bars
wire
panels
11
US CMS EMU Tooling Readiness
  • Majority of the tooling in place and operated on
    many prototypes
  • Missing Tooling
  • Cleaning Machine
  • High Pressure (100 psi) dry air line for the
    Ionized Air Cleaning
  • Vacuum lifting device to transfer panels to/from
    the gluing machine
  • Mechanical stands for final chamber HV testing
  • Box for anode panel electrical testing

12
US CMS EMU Manpower
  • Analysis of Manpower
  • L2-L3 Managers
  • 8 technicians needed on production floor
  • Spit-ball 2 of the technicians are IHEP/PNPI
    visitors for training purposes (lower efficiency)
  • Production Engineer
  • 8 high-efficiency technicians needed on
    production floor.
  • MP9 Floor Manager (G.Smith)
  • As high as 12, with reasonable approach ( i.e.
    add people as necessary)

13
US CMS EMU Manpower
  • Tooling Utilization/Contingency
  • Goal 1 chamber/week _at_ full speed production
  • No particular piece of tooling is used at 100
  • Winding Machine 1 panel/3 hours
  • Soldering Machine 1 panel/4 hours
  • Hand Soldering 1 panel/5 hours
  • Major bottlenecks are expected to be
    hand-operations
  • Soldering
  • Chamber Sealing Testing
  • Chamber Repair
  • Contingency Plan
  • Increase manpower
  • Second Shift

14
US CMS EMU Cost/Schedule Risk
  • Chamber Integration
  • Although the chamber design is complete, some
    electronic-chamber integration issues are still
    pending. None of these issues is a FNAL
    responsibility, but some of them may affect the
    chamber assembly at FNAL
  • HV Cable/Electronics-Chamber grounding
  • external mounting
  • Frame Finalization/Chamber Faraday Cage
  • Chamber dis-assembly
  • The goal of the CMS-EMU Collaboration is the
    completion of integration by the end of FY 99
    (?).

15
US CMS EMU Cost/Schedule Risk
  • Risk
  • stop production for chamber reworking
  • Schedule
  • Worst case scenario stoppage 3-4 months
  • 1 month design change
  • 3 months procurement
  • schedule may be recovered going to contingency
    plan
  • second shift
  • extra man-power
  • Manpower
  • During stoppage many subassemblies can be done by
    the MP9 work-force.
  • Chamber rework is expected to be 20-30 of a
    typical chamber assembly time.
Write a Comment
User Comments (0)
About PowerShow.com