Title: USCMS EMU
1 US-CMS EMU Chamber Factory Production Readiness
Review December 16 1999
2US CMS EMU Introduction
- Fermilab has responsibility for the design and
procurement of the components for all the CMS_EMU
chambers - Fermilab has responsibility for the assembly of
the ME234/2 Chambers - ME234/2 Subject of this Review
- ME2/1 Assembled at PNPI (Russia)
- ME3/1 Assembled at PNPI (Russia)
- ME1/2 Assembled at IHEP (China)
- ME1/3 Assembled at IHEP (China)
- Fermilab has responsibility for the shipment of
kits and critical tooling to PNPI and China IHEP.
3US CMS EMU Introduction
4US CMS EMU Introduction
- Production Readiness Review
- Committee
- J. Kerby Chairperson
- J. Carson
- K. Kephart
- D. Denisov
- F. Nobrega
- M. Lindgreen
5US CMS EMU Factory Organization - Drawings
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
6US CMS EMU - Factory Organization Procurement
Inspection
Project Management
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
7US CMS EMU - Factory Organization Kit Processing
Project Management
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
8US CMS EMU - Factory Organization QA/QC
Monitoring
Project Management
Engineering
MP9
Pro-Eng
Procurement Inspection
Technological Physicists
9US CMS EMU Introduction
- US CMS and CMS-EMU Organization Structure
L1 Managers D.Green E.Temple
L2 Manager G.Mitselmakher
L3 Electronics T.Ling
L3 Chamber A.Korytov
L3 Infrastructure D. Loveless
FNAL G.Apollinari N.Chester
10PNPI Site
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
UC Site
large CSCs
large CSCsElectronics, tested installation/commis
sioning
Fermilab Site - panel production - large CSC
assembly
CERN
large CSCsElectronics, tested installation/commis
sioning
large CSCs
UF Site
Procurement
etc.
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
frames
guard strips
gap bars
IHEP Site
wire fix bars
wire
panels
11US CMS EMU Tooling Readiness
- Majority of the tooling in place and operated on
many prototypes - Missing Tooling
- Cleaning Machine
- High Pressure (100 psi) dry air line for the
Ionized Air Cleaning - Vacuum lifting device to transfer panels to/from
the gluing machine - Mechanical stands for final chamber HV testing
- Box for anode panel electrical testing
12US CMS EMU Manpower
- Analysis of Manpower
- L2-L3 Managers
- 8 technicians needed on production floor
- Spit-ball 2 of the technicians are IHEP/PNPI
visitors for training purposes (lower efficiency) - Production Engineer
- 8 high-efficiency technicians needed on
production floor. - MP9 Floor Manager (G.Smith)
- As high as 12, with reasonable approach ( i.e.
add people as necessary)
13US CMS EMU Manpower
- Tooling Utilization/Contingency
- Goal 1 chamber/week _at_ full speed production
- No particular piece of tooling is used at 100
- Winding Machine 1 panel/3 hours
- Soldering Machine 1 panel/4 hours
- Hand Soldering 1 panel/5 hours
- Major bottlenecks are expected to be
hand-operations - Soldering
- Chamber Sealing Testing
- Chamber Repair
- Contingency Plan
- Increase manpower
- Second Shift
14US CMS EMU Cost/Schedule Risk
- Chamber Integration
- Although the chamber design is complete, some
electronic-chamber integration issues are still
pending. None of these issues is a FNAL
responsibility, but some of them may affect the
chamber assembly at FNAL - HV Cable/Electronics-Chamber grounding
- external mounting
- Frame Finalization/Chamber Faraday Cage
- Chamber dis-assembly
- The goal of the CMS-EMU Collaboration is the
completion of integration by the end of FY 99
(?).
15US CMS EMU Cost/Schedule Risk
- Risk
- stop production for chamber reworking
- Schedule
- Worst case scenario stoppage 3-4 months
- 1 month design change
- 3 months procurement
- schedule may be recovered going to contingency
plan - second shift
- extra man-power
- Manpower
- During stoppage many subassemblies can be done by
the MP9 work-force. - Chamber rework is expected to be 20-30 of a
typical chamber assembly time.