Title: Achieving Predictable Projects
1Achieving Predictable Projects
In a World of Black Swan Risks
2SESSION 9
Achieving Predictable Projects
In a World of Black Swan Risks
Gary Berman, PE, FCMAAPresident / CEOGREYHAWK
3SESSION 9
Achieving Predictable Projects
In a World of Black Swan Risks
Paul McNuttManager, Project Risks
Reviews ConocoPhillips
4SESSION 9
Achieving Predictable Projects
In a World of Black Swan Risks
TBDTBDTBD
5Agenda
- What risks are you including?
- Risk Spectrum
- Discussion
- How do you assess and manage those risks?
- Levels of Analysis
- Risk Management Techniques
- Discussion
- How will you management risk in the future?
- Discussion
6How Deep is Your Risk Pond
7A Spectrum of Risk
Tactical Quantity accuracy Labor
rates Productivity Weather Margin of error Design
allowance
Black Swan Market crash War Extreme
weather Major scope change
Future Foreign exchange Hyper-inflation Changing
regulation
Strategic Basis of design unc. Partner
alignment Permitting
8Labor Availability
9Design Allowance
10Material Availability
11Weather Delay
12Scope Definition
13Governance Model
14Global Hyper-inflation
15Geopolitcal
16Considerations When Modeling Risk
- Definition of risk in dollars or days
- Frequency
- Probability Rating Scale
- Optimistic / Likely / Pessimistic
- Combinations
- Lone wolf or hunting in packs
- Iterative Analysis to determine ranges
- Determine cost effectiveness of risk mitigation
17Risk Translated into Real Impact
18Risk Spectrum
19The Four Levels of Risk Assessment
- Level 1 Sensitivity Analysis
- Use of plus/minus percents to test a projects
weaknesses - Generally uses symmetric ranges (e.g., 10 and
-10) - Level 2 Three Point Ranging
- Use of continuous distributions on cost estimate
line items - Generally ignores dependency between similar
items - Level 3 Three Point Ranging with Dependencies
- Use of continuous distributions with correlation
- Generally ignores risk events and schedule slips
- Level 4 Full Cause and Effect Modeling
- Use of three point ranges on cost estimate
variables coupled with dependencies and risk
events including a linked schedule risk
Ranges generated from Levels 1-3 are typically
narrow and unskewed Ranges generated from Level 4
are wider and skewed reflecting observed data
20Any more comments or questions
Achieving Predictable Projects
In a World of Black Swan Risks
- Gary Berman GREYHAWK
- Paul McNutt ConocoPhillips
- TBD TBD