Title: Noncompliance Letter Response


1
Noncompliance Letter Response
  • David Smicherko

2
Noncompliance Letter
  • Noncompliance Letters (NCLs) are the one type of
    letter generated from a compliance inspection.
  • Sent via mail or email. (operator is usually
    copied)
  • Deficiencies noted during the inspection are
    enumerated in the NCL.
  • The inspection report may list other deficiencies
    noted during the inspection.
  • Only the deficiencies in the NCL must be
    responded to.

3
Noncompliance Letter
  • The response to a Noncompliance Letter
    should include
  • The corrective action.
  • The date the corrective action was completed
    or will be completed.
  • If appropriate how the noncompliance
  • issue can be avoided in the future.

4
Common Problems in NCL Responses
  • No response received.
  • NCL gives permittee or responsible authority 14
    days to respond. In some cases a time extension
    will be granted.
  • A second NCL will be issued, sent via certified
    mail with a 7 day response time given.
  • Inadequate response received.
  • All items in NCL are not responded to.
  • Items in NCL are not responded to completely.

5
Examples of Complete Responses
  • Deficiency
  • Documentation of the calibration of the elapsed
    time meters was not on site.
  • Response
  • The elapsed time meters were calibrated on March
    7, 2007. A copy of the calibration sheet is
    attached and a has been placed on site.

6
Examples of Complete Responses
  • Deficiency
  • The reduced pressure zone backflow preventer was
    leaking excessively indicating the need for
    testing and/or repair.
  • Response
  • The RPZ was repaired and re-certified on April
    4, 2007. A copy of the certification is enclosed.

7
Examples of Complete Responses
  • Deficiency
  • Advisory signs must be posted around the
    percolation ponds to designate the nature of the
    project area.
  • Response
  • Advisory signs have been posted. See enclosed
    photos.

8
Examples of Incomplete Responses
  • Deficiencies
  • The percolation pond had a freeboard of less than
    one foot.
  • Erosion of the percolation pond berm was noted.
  • An unauthorized discharge was observed from the
    percolation ponds.
  • Response (Operations)
  • (Operations Company name) can not comment on the
    condition of the pond, therefore, the owner will
    address items 1, 2 and 3.
  • Response (Owner)
  • As you are aware we are working with (Operations
    Company name) to resolve issues 1, 2 and 3.

9
Examples of Incomplete Responses
  • Deficiency
  • The Department has not received a response to the
    Noncompliance Letter numbered OCD-C-WW-07 which
    is enclosed.
  • Responses
  • (Operations Company name) did not receive copy of
    this letter.
  • A response was mailed to the noncompliance
    letter.

10
Examples of Incomplete Responses
  • Deficiency
  • A copy of the permit was not onsite.
  • Response
  • A copy of the permit should have been in the
    office.
  • Deficiency
  • The operations logbook and copy of operators
    license were not onsite.
  • Response
  • I had the logbook with me copy of license in
    logbook.

11