Title: Status of SNS


1
Status of SNS
  • Carl Lionberger

2
Spallation Neutron Source
  • The SNS will begin operation in 2006
  • At 1.4 MW it will be 8x ISIS, the worlds
    leading pulsed spallation source
  • The peak neutron flux will be 20-100x ILL
  • SNS will be the worlds leading facility for
    neutron scattering.

3
SNS Construction Progress
4
Project Status
  • The FY 2003 request was 225M, fully funded minus
    3M due to rescission
  • Impact being evaluated
  • The FY 2004 request is 143M as expected
  • Overall project design is 87 complete
  • Overall the project is 58 complete (through
    January 2003) and within budget and schedule
    constraints
  • 1.4B and June 2006 completion
  • Contingency is adequate at 19
  • ESH performance outstanding
  • gt1.9 million construction site work hours without
    lost workday injury

.. BCWS ___ BCWP ___ ACWP
5
Multi-Lab project
6
SNS Project Staffing
  • FY 2003 Project Average Staffing Through Jan.
    2003
  • 2 FTEs above the FY 2003 plan average - 670
  • 672 FTEs, a decrease of 4 FTEs from December
  • Staffing Actuals for Jan. 2003
  • 655 FTEs, a decrease of 38 FTEs from 693 FTEs in
    December

7
Multiple Labs Advantages
  • Many teams working concurrently
  • Labs working on parts that are their specialties

8
Multiple Labs Problems
  • All using EPICS, but often differently
  • Naming conventions and other standardizations are
    more important than they seem
  • Last minute integration (at least from ORNL point
    of view)
  • Developers dont come with the system

9
How far along are controls?
  • Much is still at other labs but ready for
    installation task of local staff largely
    integration.
  • CF, Front end and 2 DTLS as well as overall
    patterns of timing, MPS, PPS and vacuum controls
    done.
  • 25 iocs out of 150 online
  • Also 250 NADS

10
EPICS components
  • Operator screens
  • We have lots, often eng level
  • Alarm Handler previously not used- next run will
    indicate current success.
  • Archiver archiving lots of channels, needs some
    refinement
  • Lots of physics apps that use JCA are well along.
  • Matlab also useable tool with MCA
  • BURT not in use previously we have developed
    jburt - again, next run will tell.

11
EPICS components 2
  • Striptool heavily used in operations
  • Bumpless reboot widely used
  • Elog developed and used
  • IOC logging using EPICS logserver

12
Conclusions
  • We couldnt do things this way without EPICS
  • Need fewer people
  • Equipment shows up with a compatible control
    system
  • Even with EPICS there are still ownership and
    local practices issues
  • We have a lot of work left to do.