Welcome to SNS The Next Large EPICS Project - PowerPoint PPT Presentation

About This Presentation
Title:

Welcome to SNS The Next Large EPICS Project

Description:

SNS Integrated Control System. Welcome to SNS. The Next Large EPICS Project ... Design, Procure, Fabricate. Installation & Testing. Test Support. Software development ... – PowerPoint PPT presentation

Number of Views:66
Avg rating:3.0/5.0
Slides: 28
Provided by: david446
Learn more at: https://epics.anl.gov
Category:

less

Transcript and Presenter's Notes

Title: Welcome to SNS The Next Large EPICS Project


1
Welcome to SNSThe Next Large EPICS Project
  • A Partnership between Six National Laboratories
  • Argonne National Lab
  • Brookhaven National Lab
  • Lawrence Berkeley National Lab
  • Los Alamos National Lab
  • Oak Ridge National Lab
  • Thomas Jefferson National Lab

2
Your local hosts
  • The SNS Controls Team at ORNL
  • John Cleaves
  • Richard Epps
  • Bill DeVan
  • John Munro
  • Delphy Nypaver
  • Ron Battle

Coles Sibley Bill Stone Herb Strong Ernest
Williams Paul Wright Pam Gurd
3
Spallation Neutron Source Aerial/Site Plan
4
Spallation Neutron Source Aerial/Site Plan
5
Schedule Overview
Activity

FY99

FY00

FY01

FY02

FY03

FY04

FY05

FY06


1.1.9 RD




Turnover to operations

BOD MCR

MCR Operational

1.9.2 Global




Systems



BOD

Start Commissioning




1.9.
3 Front End

Controls


Start Commissioning

BOD


1.9.4 Linac


Controls



Start Commissioning


BOD


1.9.5 Ring



Controls



Start Commissioning

BOD

1.9.6 7 Target



Instrument

Controls

Complete Target
Commissioning


BOD
Start Cooldown


Complete Cooldown


1.9.8 1.9.10





CF CHL
Controls


Turnover to operations

BOD MCR





1.9.9 PPS



Legend


RD


Design, Procure, Fabricate

Integrated Controls Systems Master Schedule


Installation Testing

Test Support

Software development

6
Status of the Project
  • Good News
  • Funding of 1.4B approved (incl 60M for
    Controls)
  • FY01 Funding of 278M approved (incl 9.5M for
    Controls)
  • 1.4 million yard of dirt moved, first concrete
    poured
  • Unresolved Issues
  • Pre-operations funding
  • Some controls staffing problems at BNL and LANL
  • Who is the President (and is he from
    Tennessee)???

7
An aside
8
We plan a system fullyintegrated under EPICS,
including
  • Accelerator Systems
  • Front End, Linac, Compressor Ring, Beamlines
  • 50,000 channels, 160 IOCs
  • Front End already running under EPICS (at
    Berkeley)
  • Target System
  • Large and complex liquid Mercury Target
  • 1000 channels, 6 PLCs
  • Test facility already running prototypical EPICS
    system
  • Conventional Facilities
  • 2500 channels, 10 PLCs, 150 screens
  • To be done in EPICS by Sverdrup in Tullahoma
  • Training in January

9
Control System Construction is distributed among
all Collaborating Laboratories
ICWG include JLAB
1.3
1.4
1.5
1.6
1.7
1.8
1.9
Cryo
Front End
Linac
Ring
Target
Instruments
Facilities
Controls
(JLAB, ORNL)
(LBNL)
(LANL)
(BNL)
(ORNL)
(ORNL, ANL)
(ORNL, CM)
1.9.3
1.9.4
1.9.5
1.9.6
1.9.7
1.9.8
1.9.10
1.9.9
Front End
Linac
Ring
Target
Instrument
Facilities
Personnel
Cryo
Controls
Controls
Controls
Controls
Controls
Controls
Controls
Safety
1.9.2 Global Controls (Network, Timing,
Protection, Control Room, Labs, Applications,
System Software)
1.9.1 Integration Management
10
Total Controls ManpowerConstruction and
Operations
11
Where we are now
  • Controls Group Staff of 10 here at ORNL
  • EPICS Systems running Target Test Facility here
    and Front End Systems at Berkeley
  • Application Development Environment here at ORNL
  • Distributed CVS accessible by all the partners
  • Prototypical Environment running in lab here
  • MVME 2100 PPC, EPICS 3.13.3, Tornado II, DM2K
  • ControlLogix PLC
  • ControlNet over EtherNet Driver

12
The SNS Control Room
13
Some things we have agreed upon
  • Site-wide Device and Signal Naming Convention
  • ControlLogix PLCs (Allen-Bradley)
  • ControlNet over EtherNet Driver
  • Standard Cabinets
  • PowerPC IOCs (MVME 2100)
  • VME64x (Bid on the street)
  • Including Utility Board
  • Linux Environment where appropriate
  • Oracle, but

14
and some we have not.
  • Display Manager
  • DM2K (The current official standard) vs EDM
  • Database creation
  • Will use Oracle, but the process is uncertain
  • Capfast??
  • Templates?
  • We hope this meeting will help with these
    decisions

15
Some EPICS Developments are needed
  • Large Array Support
  • Needed for Diagnostics
  • Long PV Names
  • We could bump up against the current limit
  • Variable String Size
  • Multipriority Channel Access
  • Needed for Diagnostics and Machine Protect
  • SNS will fund some of these Core developments,
    but we will need help from the community

16
Summary
  • Jobs available
  • Many issues the EPICS Community can help us with.
  • Jobs available
  • We hope to contribute to EPICS
  • Jobs available
  • We look for help and advice from this meeting
  • Jobs available

17
Front End A Highly Complex System with Several
Major Subsystems and Critical Functions
The Front End has relationships with all
systems rf, high voltage, diagnostics,
alignment, controls, magnets, power supplies,
pulsed power, physics, vacuum, Cesium,
radiation.
Create 65-mA H- ion beam Ion
Source/LEBT Accelerate beam to 2.5 MeV
RFQ Chop beam into mini-pulses LEBT/MEBT Match
52-mA beam into DTL MEBT
18
Layout of Linac RF with NC and SRF Modules
DTL
RFQ
CCL
(4)
(6)
(1)
86.8 MeV
2.5 MeV
972 MeV
SRF, ß0.81
SRF, ß0.61
186 MeV
379 MeV
HEBT
(33)
(59)
(2)
from
CCL
1
59 (92 total)
1
33
19
Ring Lattice
2000P-03550/jhb
20
WBS 1.9 Scope includes control of all major
subsystems as well as Personnel Safety and
Global Systems.
SNS Integrated Control System
OPIs
IOCs
(1.8.3.4)
ROUTER
FILE SERVERS (EPICS FILE SERVER, ARCHIVERS,
ETC.) (1.9.2.4)
(1.9.2.4)
(1.9.2.4)
(1.9.2.4)
(1.9.2.4)
MAIN CTRL. RM. EQUIP.
FRONT END CTRL. RM. EQUIP.
RING CTRL. RM. EQUIP.
OTHER LOCAL CNTL STNS
TIMING SYSTEM MASTER (1.9.2.2)
BEAM PERMIT SYSTEM (1.9.2.3)
CABLES (1.9.2.2) RACEWAYS (1.8.X)
1.9.2.1 CONTROL SYSTEM NETWORK (EQUIPMENT AND
NODE CABLING) 1.8.4 POWER AND COMMUNICATIONS
SYSTEMS (BACKBONE CABLING)
CABLES (1.9.2.3) RACEWAYS (1.8.X)
CONVENTIONAL FACILITIES IOCS (1.9.8).
PPS IOC (1.9.9)
FAST PROTECT OUTPUT HARDWARE (1.9.2.3)
FRONT END CONTROL SYSTEMS (1.9.3)
RING CONTROL SYSTEMS (1.9.5)
EXPERIMENT CONTROL SYSTEMS (1.7)
TARGET IOCS (1.9.6)
LINAC CONTROL SYSTEMS (1.9.4,10)
PPS PLCs (1.9.9)
C.F. PLCs (1.8.x)
RACEWAY SYSTEM (1.8.x), TYPICAL
CABLE SYS. (1.7.x)
CABLE SYS. (1.3.x)
CABLE SYS. (1.5.x)
CABLE SYS. (1.6.8)
PLCs
CABLE SYS. (1.4.x)
CABLE S (1.8.x)
CABLE S (1.8.x)
(1.9.6)
FRONT END SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.3)
LINAC SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.4)
RING SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.5)
TARGET SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.6)
EXPERIMENT SENSORS, CONTROL ELEMENTS, CONTROLLERS
, ETC. (1.7)
CONVENTIONAL FACILITIES SENSORS CONTROL
ELEMENTS, CONTROLLERS, ETC.(1.8)
PERSONNEL PROTECTION SYSTEM SENSORS CONTROL
ELEMENTS, ETC. (1.9)
EQUIPMENT PROTECTION SYSTEM HARDWARE (1.9.2.3)
TIMING SYSTEM SLAVE HARDWARE (1.9.2.2)
21
Subsystem interfaces arevaried and complex
Ethernet TCP/IP Channel Access Protocol
VXI IOC
PC IOC
VME IOC
VME IOC
PC IOC
Negotiated Exception Examples Cryoplant
Conven. Facilities
Default Interface Examples Injector
Default Interface Examples Beamlines Vac.
Sys.
PLC
Default Interface Example HPRF
Negotiated Exception Examples LLRF
Diagnostics
PLC
PLC
Packaged PLC System
Embedded PLC System
Equipment
Equipment
Equipment
Equipment
PLC
Equipment
IOC Input.Output Controller PLC Programmable
Logic Controller PC Personal Computer
22
Proposed Baseline for full operations (26)
2
Management GL Secretary
8
4
12
Hardware Design Eng Tech Pool (7)
Safety Eng (2) Techs (2)
Software EPICS System Programmers (3) Application
Engineers (7) Network, Sysadmin, Database (2)
Total is 26
APS is 29 for same scope
23
The exact number of IOCsdepends upon Title II
design.
Ethernet - TCP/IP
RF System
Cavity System
Control System
HPRF IOC
ControlNet
PLC
KA
KA
KB
HPRF System
KA
KB
LLRF IOCs
LLRF IOCs
KA
KB
Power Supply
KA
KB
(50 Channels)
KA
KB
PLC
PLC
X 5
X 6
Transmitter
Transmitter
(125 Channels)
(125 Channels)
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
11 Cavities
24
Baseline Staffing Plan for Controls
25
Ring Straight Section Functions
  • Separate functions in each straight
  • Four straights 12.5 m 2 x 6.85 m
  • Injection modules
  • Two-stage collimation
  • 3 (h1)1 (h2) interchangeable RF cavities
  • Beam-in-gap kicker
  • Empty section for future use

26
Spallation Neutron Source Aerial/Site Plan
27
Control System Systems and Functions
  • Data Acquisition and Control
  • 160 distributed Input Output Controllers with
    50,000 signals
  • Timing and Synchronization
  • Synchronizes choppers, kickers, rf systems and
    beam diagnostics
  • Time stamps all acquired data to microsecond
    accuracy
  • Machine Protection
  • Turns off beam in lt20usecs for beam loss) or
    equipment failure
  • Control System Network
  • Isolated Control system network includes gt20
    switches
  • System and Application Software
  • Communications, databases, EPICS core software,
    engineering applications and the human
    interface
  • Control Room
  • Operator Consoles, Personnel Access control,
    network hub, computer servers, timing
    distribution etc
Write a Comment
User Comments (0)
About PowerShow.com