Title: Welcome to SNS The Next Large EPICS Project
1Welcome to SNSThe Next Large EPICS Project
- A Partnership between Six National Laboratories
- Argonne National Lab
- Brookhaven National Lab
- Lawrence Berkeley National Lab
- Los Alamos National Lab
- Oak Ridge National Lab
- Thomas Jefferson National Lab
2Your local hosts
- The SNS Controls Team at ORNL
- John Cleaves
- Richard Epps
- Bill DeVan
- John Munro
- Delphy Nypaver
- Ron Battle
Coles Sibley Bill Stone Herb Strong Ernest
Williams Paul Wright Pam Gurd
3Spallation Neutron Source Aerial/Site Plan
4Spallation Neutron Source Aerial/Site Plan
5Schedule Overview
Activity
FY99
FY00
FY01
FY02
FY03
FY04
FY05
FY06
1.1.9 RD
Turnover to operations
BOD MCR
MCR Operational
1.9.2 Global
Systems
BOD
Start Commissioning
1.9.
3 Front End
Controls
Start Commissioning
BOD
1.9.4 Linac
Controls
Start Commissioning
BOD
1.9.5 Ring
Controls
Start Commissioning
BOD
1.9.6 7 Target
Instrument
Controls
Complete Target
Commissioning
BOD
Start Cooldown
Complete Cooldown
1.9.8 1.9.10
CF CHL
Controls
Turnover to operations
BOD MCR
1.9.9 PPS
Legend
RD
Design, Procure, Fabricate
Integrated Controls Systems Master Schedule
Installation Testing
Test Support
Software development
6Status of the Project
- Good News
- Funding of 1.4B approved (incl 60M for
Controls) - FY01 Funding of 278M approved (incl 9.5M for
Controls) - 1.4 million yard of dirt moved, first concrete
poured - Unresolved Issues
- Pre-operations funding
- Some controls staffing problems at BNL and LANL
- Who is the President (and is he from
Tennessee)???
7An aside
8We plan a system fullyintegrated under EPICS,
including
- Accelerator Systems
- Front End, Linac, Compressor Ring, Beamlines
- 50,000 channels, 160 IOCs
- Front End already running under EPICS (at
Berkeley) - Target System
- Large and complex liquid Mercury Target
- 1000 channels, 6 PLCs
- Test facility already running prototypical EPICS
system - Conventional Facilities
- 2500 channels, 10 PLCs, 150 screens
- To be done in EPICS by Sverdrup in Tullahoma
- Training in January
9Control System Construction is distributed among
all Collaborating Laboratories
ICWG include JLAB
1.3
1.4
1.5
1.6
1.7
1.8
1.9
Cryo
Front End
Linac
Ring
Target
Instruments
Facilities
Controls
(JLAB, ORNL)
(LBNL)
(LANL)
(BNL)
(ORNL)
(ORNL, ANL)
(ORNL, CM)
1.9.3
1.9.4
1.9.5
1.9.6
1.9.7
1.9.8
1.9.10
1.9.9
Front End
Linac
Ring
Target
Instrument
Facilities
Personnel
Cryo
Controls
Controls
Controls
Controls
Controls
Controls
Controls
Safety
1.9.2 Global Controls (Network, Timing,
Protection, Control Room, Labs, Applications,
System Software)
1.9.1 Integration Management
10Total Controls ManpowerConstruction and
Operations
11Where we are now
- Controls Group Staff of 10 here at ORNL
- EPICS Systems running Target Test Facility here
and Front End Systems at Berkeley - Application Development Environment here at ORNL
- Distributed CVS accessible by all the partners
- Prototypical Environment running in lab here
- MVME 2100 PPC, EPICS 3.13.3, Tornado II, DM2K
- ControlLogix PLC
- ControlNet over EtherNet Driver
12The SNS Control Room
13Some things we have agreed upon
- Site-wide Device and Signal Naming Convention
- ControlLogix PLCs (Allen-Bradley)
- ControlNet over EtherNet Driver
- Standard Cabinets
- PowerPC IOCs (MVME 2100)
- VME64x (Bid on the street)
- Including Utility Board
- Linux Environment where appropriate
- Oracle, but
14 and some we have not.
- Display Manager
- DM2K (The current official standard) vs EDM
- Database creation
- Will use Oracle, but the process is uncertain
- Capfast??
- Templates?
- We hope this meeting will help with these
decisions
15Some EPICS Developments are needed
- Large Array Support
- Needed for Diagnostics
- Long PV Names
- We could bump up against the current limit
- Variable String Size
- Multipriority Channel Access
- Needed for Diagnostics and Machine Protect
- SNS will fund some of these Core developments,
but we will need help from the community
16Summary
- Jobs available
- Many issues the EPICS Community can help us with.
- Jobs available
- We hope to contribute to EPICS
- Jobs available
- We look for help and advice from this meeting
- Jobs available
17Front End A Highly Complex System with Several
Major Subsystems and Critical Functions
The Front End has relationships with all
systems rf, high voltage, diagnostics,
alignment, controls, magnets, power supplies,
pulsed power, physics, vacuum, Cesium,
radiation.
Create 65-mA H- ion beam Ion
Source/LEBT Accelerate beam to 2.5 MeV
RFQ Chop beam into mini-pulses LEBT/MEBT Match
52-mA beam into DTL MEBT
18Layout of Linac RF with NC and SRF Modules
DTL
RFQ
CCL
(4)
(6)
(1)
86.8 MeV
2.5 MeV
972 MeV
SRF, ß0.81
SRF, ß0.61
186 MeV
379 MeV
HEBT
(33)
(59)
(2)
from
CCL
1
59 (92 total)
1
33
19Ring Lattice
2000P-03550/jhb
20WBS 1.9 Scope includes control of all major
subsystems as well as Personnel Safety and
Global Systems.
SNS Integrated Control System
OPIs
IOCs
(1.8.3.4)
ROUTER
FILE SERVERS (EPICS FILE SERVER, ARCHIVERS,
ETC.) (1.9.2.4)
(1.9.2.4)
(1.9.2.4)
(1.9.2.4)
(1.9.2.4)
MAIN CTRL. RM. EQUIP.
FRONT END CTRL. RM. EQUIP.
RING CTRL. RM. EQUIP.
OTHER LOCAL CNTL STNS
TIMING SYSTEM MASTER (1.9.2.2)
BEAM PERMIT SYSTEM (1.9.2.3)
CABLES (1.9.2.2) RACEWAYS (1.8.X)
1.9.2.1 CONTROL SYSTEM NETWORK (EQUIPMENT AND
NODE CABLING) 1.8.4 POWER AND COMMUNICATIONS
SYSTEMS (BACKBONE CABLING)
CABLES (1.9.2.3) RACEWAYS (1.8.X)
CONVENTIONAL FACILITIES IOCS (1.9.8).
PPS IOC (1.9.9)
FAST PROTECT OUTPUT HARDWARE (1.9.2.3)
FRONT END CONTROL SYSTEMS (1.9.3)
RING CONTROL SYSTEMS (1.9.5)
EXPERIMENT CONTROL SYSTEMS (1.7)
TARGET IOCS (1.9.6)
LINAC CONTROL SYSTEMS (1.9.4,10)
PPS PLCs (1.9.9)
C.F. PLCs (1.8.x)
RACEWAY SYSTEM (1.8.x), TYPICAL
CABLE SYS. (1.7.x)
CABLE SYS. (1.3.x)
CABLE SYS. (1.5.x)
CABLE SYS. (1.6.8)
PLCs
CABLE SYS. (1.4.x)
CABLE S (1.8.x)
CABLE S (1.8.x)
(1.9.6)
FRONT END SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.3)
LINAC SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.4)
RING SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.5)
TARGET SENSORS, CONTROL ELEMENTS, CONTROLLERS,
ETC. (1.6)
EXPERIMENT SENSORS, CONTROL ELEMENTS, CONTROLLERS
, ETC. (1.7)
CONVENTIONAL FACILITIES SENSORS CONTROL
ELEMENTS, CONTROLLERS, ETC.(1.8)
PERSONNEL PROTECTION SYSTEM SENSORS CONTROL
ELEMENTS, ETC. (1.9)
EQUIPMENT PROTECTION SYSTEM HARDWARE (1.9.2.3)
TIMING SYSTEM SLAVE HARDWARE (1.9.2.2)
21Subsystem interfaces arevaried and complex
Ethernet TCP/IP Channel Access Protocol
VXI IOC
PC IOC
VME IOC
VME IOC
PC IOC
Negotiated Exception Examples Cryoplant
Conven. Facilities
Default Interface Examples Injector
Default Interface Examples Beamlines Vac.
Sys.
PLC
Default Interface Example HPRF
Negotiated Exception Examples LLRF
Diagnostics
PLC
PLC
Packaged PLC System
Embedded PLC System
Equipment
Equipment
Equipment
Equipment
PLC
Equipment
IOC Input.Output Controller PLC Programmable
Logic Controller PC Personal Computer
22Proposed Baseline for full operations (26)
2
Management GL Secretary
8
4
12
Hardware Design Eng Tech Pool (7)
Safety Eng (2) Techs (2)
Software EPICS System Programmers (3) Application
Engineers (7) Network, Sysadmin, Database (2)
Total is 26
APS is 29 for same scope
23The exact number of IOCsdepends upon Title II
design.
Ethernet - TCP/IP
RF System
Cavity System
Control System
HPRF IOC
ControlNet
PLC
KA
KA
KB
HPRF System
KA
KB
LLRF IOCs
LLRF IOCs
KA
KB
Power Supply
KA
KB
(50 Channels)
KA
KB
PLC
PLC
X 5
X 6
Transmitter
Transmitter
(125 Channels)
(125 Channels)
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
Klystron
11 Cavities
24Baseline Staffing Plan for Controls
25Ring Straight Section Functions
- Separate functions in each straight
- Four straights 12.5 m 2 x 6.85 m
- Injection modules
- Two-stage collimation
- 3 (h1)1 (h2) interchangeable RF cavities
- Beam-in-gap kicker
- Empty section for future use
26Spallation Neutron Source Aerial/Site Plan
27Control System Systems and Functions
- Data Acquisition and Control
- 160 distributed Input Output Controllers with
50,000 signals - Timing and Synchronization
- Synchronizes choppers, kickers, rf systems and
beam diagnostics - Time stamps all acquired data to microsecond
accuracy - Machine Protection
- Turns off beam in lt20usecs for beam loss) or
equipment failure - Control System Network
- Isolated Control system network includes gt20
switches - System and Application Software
- Communications, databases, EPICS core software,
engineering applications and the human
interface - Control Room
- Operator Consoles, Personnel Access control,
network hub, computer servers, timing
distribution etc