Title: LEED


1
LEED-NC Commissioning
Presented by MBO Inc.
2
Your Speakers for Today
  • Jorge Torres Coto, LEED AP
  • Building Systems Commissioning Engineer
  • MBO, Inc.
  • jorge_at_mbo1.com
  • Brought to you by
  • MBO, Inc.

3
Outline
  • What is commissioning?
  • Benefits and cost of Cx
  • LEED Requirements and tips
  • EAp1
  • EAc3
  • Examples and experience on LEED Cx
  • Who can be the Cx Provider?
  • Going beyond the LEED requirements and
    expectations

4
What is Commissioning (Cx)?
  • Technical systematic process of verifying and
    testing Building Systems
  • TOTAL QUALITY ASSURANCE!
  • It applies to the Building Design
  • It applies to the Construction of the Building
  • It applies to the turnover of the building

5
What Cx is NOT
  • Peer Review
  • Contractors Q A program
  • Paper only process
  • Testing, Adjusting Balancing
  • System Troubleshooting process
  • Inspection Process only

6
Cx Process
7
What are the Benefits of Cx
  • Systems perform as intended
  • Lower energy use and cost
  • Early detection of potential problems
  • Better building documentation (Systems Manual)
  • Trained building operators
  • Lower Operations Maintenance (OM) cost
  • Enhanced Indoor Environmental Quality (IEQ)
  • Reduced construction costs (ltChange Orders)

8
What can and will be Commissioned
  • Whole Building Commissioning NIBS
  • Guideline 0 - ASHRAE/NIBS The Cx Process
  • Guideline 1 - ASHRAE, HVACR System
  • Guideline 2 - ASCE, Structural System
  • Guideline 3 - BETEC, Exterior Envelope System
  • Guideline 4 - NRCA, Roofing System
  • Guideline 5 - AWCI, Interior System
  • Guideline 6 - NEII, Elevator System
  • Guideline 7 - ASPE, Plumbing System
  • Guideline 8 - IES, Lighting System
  • Guideline 9 - IEEE, Electrical System
  • Guideline 10 - NFPA, Fire Protection System
  • Guideline 11 - TIA, Telecommunications System

9
Economics of Cx
  • The operating costs of a commissioned building
    are 8 20 lower than a comparable
    non-commissioned building
  • (GSA Building Commissioning Guideline)

10
Other benefits of Cx
  • Reduced change orders.
  • 0.5 - 10 of total MEP change orders
  • Reduce RFIs
  • RFIs turn into change orders
  • Improved occupant comfort Productivity
  • 0.10/ft2/year

11
Cost associated with Cx
  • Commissioning cost (/Gft2)

Gft2 0.50 1.00 1.50
300,000
200,000
100,000
50,000
15,000
  • Commissioning cost can vary considerably from
    project to project.
  • Actual cost depend on
  • Project size
  • Project complexity
  • Rigor of Cx effort
  • The question is not whether you can afford to Cx?
    But, can you afford not to?

Simple Complex
12
Cx The Bottom Line
  • Cx adds value.
  • Helps maintain and prove the Green excitement
  • Ensures IEQ benefits
  • ROI

13
ASHRAE Cx Process
  • The 4 phases of the Cx Process

14
LEED Rating System
  • Sustainable Sites
  • Water Efficiency
  • Energy Atmosphere
  • Pre-1 Fundamental Systems Cx
  • Cre-3 Enhanced Cx
  • Materials Resources
  • Indoor Environmental Quality
  • Innovation Design Process

15
Energy Atmosphere EAp1
  • Pre-1 Fundamental Systems Cx
  • Designate a Cx Authority
  • Document OPR and develop BOD
  • Incorporate Cx requirements into CD
  • Develop and implement Cx plan
  • Verify the installation and performance of the
    Commissioned systems
  • Complete a summary of the Cx Report

16
1.Designate the Cx Authority
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Part of the owners team (ideally)
  • Third party in preferred but can be part of the
    design team
  • CxA shall be independent of the projects design
    and construction management, though they may be
    employees of the firms providing those services.

17
2.Document OPR BOD
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • OPR
  • Completed by Owner, CxA and Project Team
  • Owner and user requirements
  • Environmental and sustainable goals
  • Energy efficiency goals
  • IEQ requirements
  • Equipment and System expectations
  • Building occupant and OM personnel requirements
  • BOD
  • Completed by the design team
  • Primary design assumptions
  • Standards
  • Narrative descriptions

18
3.Incorporate Cx into CDs
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Project Specifications
  • Typically the Cx requirements are in the specs.
  • US DOE / PECI Guide
  • http//peci.org/library/mcpgs.htm
  • Whole Building Design Guide
  • http//www.wbdg.org/ccb/browse_org.php?o70

19
5.Develop Implement Cx Plan
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Start early
  • Preferably during DD
  • It is not a rigid document
  • changes with planning, scheduling, etc.

20
7.Verify the installation performance of the
systems
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Installation inspection
  • System performance testing
  • Evaluation of results compared to OPR/BOD

21
10.Complete Cx Report
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Executive summary on the process results
  • Deficiency list with resolutions
  • Performance test results

22
Certification Submittals
  • LEED Letter template
  • Completed OPR and BOD
  • Incorporated Cx into specifications
  • Cx plan
  • Verified installation and performance of systems
  • Completed Cx Report

23
Energy Atmosphere EAc3
  • Cre-3 Enhanced Commissioning
  • Designate a Cx Authority
  • Document OPR and develop BOD
  • Incorporate Cx requirements into CD
  • Conduct Cx design review prior to CD
  • Develop and implement Cx plan
  • Review contractor submittals applicable to Cx
    scope
  • Verify the installation and performance of the
    commissioned systems
  • Develop Systems Manual
  • Verify requirements for training are complete
  • Complete a summary of the Cx Report
  • Review building operation within 10 months after
    substantial completion

24
Cre-3 Enhanced Cx
  • Cx Authority must be an independent party
  • The CxA shall perform at least
  • Design review prior to CDs
  • Review contractor submittals
  • Review building operation (post-occupancy)

25
4.Design Review
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Minimum one Cx design review of
  • OPR
  • BOD
  • Design documents prior to mid-CD phase
  • Back check review comments in subsequent
    submission

26
6.Review Contractor Submittals
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Only review submittals applicable to systems
    being commissioned for compliance with OPR and
    BOD.
  • Do they meet OPR and BOD
  • O M requirements
  • Facilitating performance testing

27
8.Develop Systems Manual
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • In addition to the OM manual that is provided to
    the staff by the contractor.
  • Focuses on operations rather than maintenance.
  • Specifics of interactions between equipment
  • Final version of BOD
  • Single line diagrams
  • As-built sequences of operation
  • Operating instruction for integrated systems
  • Recommended maintenance schedules
  • Recommended retesting schedules with blank test
    forms
  • Recommended recalibration schedules for sensors
    and actuators

28
9.Verify Requirements for Training
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • Document training expectations and needs with the
    owner
  • Ensure staff and occupants receive training and
    orientation
  • Special attention should target new or uncommon
    design features that have a potential of being
    over-ridden or removed due to lack of
    understanding.

29
11.Review Building Operations
  • 1.Designate a Cx Authority
  • 2.Document OPR and develop BOD
  • 3.Incorporate Cx requirements into CD
  • 4.Conduct Design phase Cx Review
  • 5.Develop and implement Cx plan
  • 6.Review Contractors Approved Submittals
  • 7.Verify the installation and performance of the
    Commissioned systems
  • 8.Develop Systems Manual for the Cx Systems
  • 9.Verify the requirements for Training are
    completed.
  • 10.Complete a summary of the Cx Report
  • 11.Review building operation within 10 months
    after substantial completion
  • After handover ( 6 10 months) review
    performance of building/facility with owner and
    OM staff.
  • Create a deficiencies list (prior to manufacturer
    / contractors warranty expiration)
  • Any items listed on the deficiencies list that
    will not be corrected shall be documented in the
    Systems Manual

30
Certification Submittals
  • LEED Letter template
  • CxA conducted design review
  • CxA reviewed submittals
  • Systems Manual
  • OM staff and occupants have been trained
  • CxA review of building operation post-occupancy

31
USGBCs CxA inerpretations
  • CxA for Cre-3 has to be independent, cannot be
    hired by design or construction team
  • Late in the game.
  • If owner commits to LEED late it is acceptable to
    provide two reviews during and after CDs in lieu
    of reviews at SD and CD
  • For prototype buildings
  • Reviews are acceptable after SD
  • 2 reviews are to be performed on latter stages of
    design.

32
Open Forum
  • Questions?Comments?Complaints?Praises?

33
Cx References
  • www.peci.org
  • http//www.wbdg.org/ccb/NIBS/nibs_gl3.pdf
  • www.ashrae.org
  • www.bcxa.org
  • www.cacx.org/library