Title: INTRODUCTION TO OUR PPT TEMPLATE
1(No Transcript)
2.
- Standard Contract Forum 3 November
200513.30Customer Suite, BT Centre, London
3Standard Contract Forum Thursday 3 November
2005
- AGENDA
- Introduction and Notes of Previous Meeting
- Consult 21
- Lead Times
- Review of New and Amended Schedules
- Geographic VOIP Ranges
- TMP Update
- Any Other Business
-
4Consult21New Working Groups
- The Groups
- The People
- The Objectives
- 28th October 2005
Nigel Scott Consult21
4
5Update Commentary
- The scope and interactions of the WGs have been
modified based on feedback and internal Buddy
war gaming, in particular - The work of the Legacy Working Group is subsumed
into the appropriate Product Working Group - A new WG Management group is formed
- The WG scopes have been fleshed out
6Consult21 Working Group Structure
WG Managemenet Co-Chair Co-ordination
Steering Board To be a co-ordination and
escalation point
Communications To keep end users informed
- Implementation Migration
- To make tomorrow happen
- Operational Planning
- Implementation
Architecture Framework Groups Providing the
underpinning Systems Processes Network
Structure, Network Hooks
7Top Level Themes
Product Groups
What do we do with what we've got
What (new) do we want and when
Legacy
21CN New
Contract Commercial
How we do business
The Product WGs address both legacy transition
and 21CN products
8Consult21 Themes Contacts Industry Co-Chair Consult21 Buddy Key Player/s
Commercial Group tba Chris Evans tba
Contract tba n/a Keith Mitchinson
Communications Claire Wallace (Energis) Andy Rudman Joe Kelly
Implementation Migration Chris Danzelman (CW) Liz Walsh Mike Cook
Broadband Gavin Young (Bulldog) Tom Saville Â
- LLU Â Â Paul Barratt (O)
- Datastream / FAS Â Â Bill Jones
- IPStream   Andy Jugg
Line Access Justin Orde (Spitfire) Tom Saville Â
- WLR (legacy migration) Â Â "Colin Reith" (O)
- MSAN Voice Access product(s) Â Â Mike Ward
Interconnect Portfolio Paul Griffin (Energis) Chris Evans Mike Ward
Point to Point John Lee (Energis) Tom Saville Â
- PCs PPCs   Rob Thomas
- Ethernet (WES) Â Â Peter Newton (O)
- Backhaul (BES) Â Â tba
 Systems Processes Nancy Saunders (Kingston)  Tim Short Graham Crane Mark Gray
Network Structure Paul Rosbotham (CW) Chris Evans Tim Wright
Network Hooks Antony Millington (Energis) Tim Short Andy Fielden
WG Management  Bill Du Cann Guy Bradshaw
   tba (O)
8
Key Players C0-Chairs to be re-confirmed
9Consult 21
Working Groups Proposed Scopes (Updated)
9
10WG Management Group Scope
- Objective / Purpose
- To own and manage the obligatory products
transformation plan (with clear understandings of
what constitutes no change, transfer engineering
and equivalent 21CN products and where these will
apply and impact migration plans) - To manage the cross-WG Issues and Requirements
register(s) to facilitate the WGs to achieve
their objectives - To monitor and report on the critical delivery
path for the Plan, instigating appropriate
actions to resolve any problems. - To monitor the Consult21 process, proposing
improvements where necessary
11Product Working Group ScopesBroadband, Point to
Point, Interconnect Portfolio and Line Access
- Objective / Purpose
- To provide the detailed trajectory and critical
path plans for those products contained within
the obligatory products transformation plan, in
particular addressing withdrawal and
transformation issues. - To agree the
- outline requirements / product descriptions for
- new products/services
- transformation products e.g. VIECs
- commercial and service wrap for the above
products - introduction timeframes for the new products
- Scope
- Obligatory products during the transformation
phase to BTs 21CN
12Architecture Framework Scope Systems
Processes, Network Hooks and Network Structure
(e.g. MSAN) Working Groups
- Objective / Purpose
- To adopt interface standards, rules,
functionality, principles, frameworks etc that
govern the development and implementation of
networks and systems. - To ensure that as far as is practicable
individual product needs are catered for in a
consistent way with a minimum of re-invention - Application of standards, inherent resilience,
impairment standards, planning rules, firewalls
etc - Scope
- Builds on UK standards from NICC etc.
13Implementation Migration Scope
- Objective / Purpose
- To create an assured environment that enables the
migration of voice and non-voice products off
affected BT switches and platforms - To minimise any potential negative impact of
migration on end users - To capture learning from the migration processes
for application to BAU. - To introduce new products as defined by the
Product WGs. -
- Scope
- All obligatory products and those non-obligatory
products within the remit of Consult21 to achieve
the above objectives
14Legacy vs New Products
Legacy
21CN New
Working Group
M
Interconnect Portfolio
C
M
C
Broadband
M
Line Access
C
M
C
Point to Point
Point to Point includes all TDM and Ethernet type
services All Product Working Groups have both
legacy new product opportunities. Many of the
same people will be involved in Legacy New
discussions Legacy work will conclude before New
concludes, but they will overlap
15- Thank you
- This is an evolving Consultation
- Your feedback on the structure and operation is
very much appreciated
16MIGRATION PROPOSALCONSULTATION FRAMEWORK
- Nigel Scott
- This presentation provides an overview of the
National Migration Proposal and its associated
Consultation
17PRE- CONSULTATION FEEDBACKSUMMARY
- 8 responses were received
- Feedback fell into 3 categories
- The data set
- Additional information relating to DLE closure or
clarifications has been incorporated into the
revised proposal - Clear methodology around document control
included - Consultation Framework
- Feedback received is consistent with Consultation
Framework - Adjudication process defined for Consultation
Phase only - Additional Information required to enable
planning - Voice Migration Methodology Strawman confirmed
to facilitate Bi-lateral discussion - Development of a Roadmap identifying when
additional information will be available
18MIGRATION PROPOSAL DATASETISSUE 2
- Audience
- Communications Providers with whom BT has direct
interconnect or LLU relationship - Objectives
- Provides details of the 21CN locations and
high-level site-based details of how the existing
infrastructure will be mapped on to the 21CN
infrastructure enabling these Communications
Providers to understand the implications for
their existing network infrastructure - To be viewed as a statement of BTs current
likely sequencing of migration activity, subject
to successful resolution of a series of complex
commercial and technical issues - Reflects regional workforce constraints in
scheduling work - Smoother ramp up of migration activities to
reflect training and realistic productivity
performance improvements - Outlines the consultation process which will
operate from issue to 16 Dec 2005 - Dataset disclosure
- Through NIPP or other appropriate closed user
portal - Subset of locational information available
through NISCC only
19MIGRATION PROPOSALCONSULTATION SCOPE
- Aim is
- Production of a Plan of Record for business
planning purposes (Jan 06) - BT seeks views on the most appropriate and timely
approach to - reach acceptable solution to all parties
recognising the schedule will be fine tuned to
reflect operational needs as migration proceeds - effective change control management
- minimising anticipating the impact on customers
20MIGRATION PROPOSALCONSULTATION FRAMEWORK
TIMETABLE
CONSULTATION (22/10 16/12)
- 05/12 16/12
- BT/Industry Board reviews/agrees Migration
Proposal Change Requests - Expert Groups on Migration methodology
- Communicate outcome of Change Requests to CPs
- IMWG 16/12/05
- 02/11-02/12
- Bi-laterals
- Interconnect CPs
- Service Provider CPs
- Multi-lateral consultation through IMWG expert
groups
- (21/10 02/11)
- CP Impact Analysis
21MIGRATION PROPOSALBI-LATERAL TOPICS
- Technical Operations focus on three broad
areas - Implementation Considerations and Impacts
- sequencing, timing, freeze periods, sensitive
customer impacts - asset and operational optimisation, NGN business
plan considerations - Migration Plan Change Requests
- recording of Changes Required
- recording of impacts rationale
- Migration Methodology
- transfer engineering methodologies to be used to
support Migration - minimising end user negative impact and
operational resource optimisation
22CONSULTATION PHASECHANGE CONTROL ADJUDICATION
- Change Requests documented at Bi-laterals
- Change Requests circulated to industry
- anonymous basis excluding rationale
- other CPs identify impacts if such a change were
to be accepted by BT - enables the acceptance or rejection to be done in
light of impacts across industry - BT Impact Analysis undertaken
- W/C 12/12/05, BT and Industry convene a pre
agreed Adjudication Board - Accepts or rejects each Change Request
- Membership is 3 from BT and 3 Industry nominees,
under BT chairmanship - Chair has casting vote
23Â STANDARD CONTRACTS FORUM3 November
2005Geoff Wills Interconnect Links Lead Times
24 Standard Contract Forum Thursday 3rd November
2005
Order Original timescale New or proposed timescale Comments
Traffic route through new point of connection 6 months 6 months No Change
New traffic route through an existing POC 65 days 45 days New orders from date to be briefed
New traffic route through an existing POC with IEC 75 days 65 days Agreed at General Contact Review
Route augmentation 25 days 25 days No change
Route augmentation with IEC 35 days 25 days Agreed at General Contract Review
25 Standard Lead Time Reduction from 65 to 45
working days
-
- Annex A
- 11.1.3 New Traffic Routes between Switch
Connections through an established Point of
Connection using the same technology, including
the provision of new Traffic Routes by way of
additional Customer Sited Interconnect from a
particular Operator site - 11.1.5 New Traffic Routes over IECs at a Switch
Connection using the same technology - 11.1.7 Capacity Re-arrangements involving the
provision of new Traffic Routes using the same
technology or a new technology already in service
at the relevant Switch Connection - 11.1.9 Capacity Re-arrangements involving the
provision of new Traffic Routes requiring IECs
using the same technology or a new technology
already in service at the relevant Switch
Connection - .
26Standard Contract Forum Thursday 3 November
2005
Keith Mitchinson 3 November 05
27Standard Contract Forum Thursday 3 November 2005
REVISED SCHEDULE Schedule 143 Carrier Pre
Selection WITHDRAWN SCHEDULE Schedule
153/153A Supply of Operator Branded
Telephone
Directories
28Standard Contract ReviewBriefing onBT and
Operator Geographic NVS (New Voice Service
Calls)3rd November 2005Les Stevens Product
Manager BT Core Network Services - Interconnect
29Contents
- Product overview BT / Operator NVS Services
- Ofcom Description summary
- Current position Operator BT NVS
- BT Service update.
- Applicable Contact Schedules BT Proposal
- Customer Feedback?
- Next Steps?
30Schematic Diagram of Operator NVS Geo Call
Termination
- Diagram below shows a typical application (may
also be VOiP Originated?)
Customer Originates a Call to Operator Geo NVS
number.
TDM Interconnect
Operator PSTN
(TDM to IP conversion)
BT TDM Network
IP Cloud
Delivery of IP Geo NVS call
31Schematic Diagram of BT Geo NVS Call Termination
- Diagram below shows a typical application (May
also be VOiP originated).
CP Customer Originates a Call to BT Geo NVS
number.
TDM Interconnect
(TDM to IP conversion)
CP TDM Network
BT PSTN
IP Cloud
Delivery of IP Geo NVS call
32Ofcom Description - Extract from Ofcom statement
of the 6/9/04 Numbering Arrangements for New
Voice Services
- Location Independent Electronic Communications
Services (LIECS) Calls. - The Ofcom description of the characteristic of a
Location Independent Electronic Communications
Services as defined in their statement of the
6/9/04 Numbering Arrangements for New Voice
Services can be summarised as follows- - The numbering plan of the Communications Provider
offering the service has no geographic
significance. - The location of the customers apparatus
identified by a given telephone number at the
time of use is not permanently associated with a
particular network termination point. - No revenue sharing with end users is allowed.
- Number translation to a geographic number is not
involved and the service is not a mobile service. - Service does not have to offer PATS.
33Current position Operator BT NVS.
- Increase in Operator Geo code builds believed
to be NVS driven. - BT Issued Interconnect Notification 05073
(12/08/05) - BT Notification of opening on Geo ranges
associated with NVS (19/08/05). - Draft Geo NVS schedule offered for discussion.
- Debate unfortunately deferred to Nov Meeting.
34Update on BT Launch Of Geo NVS.
- Originally notified on 19th August.
- Original service ready date 4th October 2005.
- Some 10K allocations but mainly at Ofcom request
sub allocations _at_ 1K. - Problems encountered building _at_ 1K using
automated systems. - Manual build progressing.
- Upgrade to automated required funding now
agreed. - New target completion by end April 2006.
- BT NVS Platform connected to 10 Trunk Switches
(as per notification) - Interconnection at these POI Single Tandem
rates. - BT to issue revised timescale notice.
35Contract Schedule for Geographic NVS ?
- Are Operators trading Geo NVS with BT under
existing Geo Schedules? - If so is this a sustainable position?
- Feedback to BT Proposed Schedule?
- Next steps to regularise this anomaly?
36(No Transcript)
37Standard Contract ForumBriefing
onTechnical Master Plan3rd November
2005Kevin Young BT Interconnect Numbering
Services
38Contents
- The Definition
- BTs view of the TMP content
- TMP Information ownership retention
39The Definition
- Contract (Annex D) Definition
- Current
- Technical Master Plan a document recording
details of the Points of Connection and the plans
for development of further Points of Connection - Proposed
- Technical Master Plan a document, retained and
owned by both Parties, recording details of the
Points of Connection and the plans for
development of further Points of Connection
40BTs view of the TMP content
- There are three aspects of information that
should be recorded within the TMP, these are - The details of the interconnect between the
Parties Systems and the plans for future
developments relating to interconnect. Typically,
but not solely, exchanged through the Capacity
Profile/ACO process. - The physical arrangements and Number Ranges, or
part thereof, for each of the Traffic Routes on
an Interconnect Link. Information shall be
provided in accordance with the Provisioning
Manual. Typically, but not solely, exchanged
through the Routing Plan process. - The allocation of Interconnect Capacity to
transmission capacity by means of Tributary
allocation charts as set out in the Provisioning
Manual. - The information relating to these three areas
are, in the main, exchanged within documentation
set out within the Provisioning Manual.
41TMP Information ownership retention
- The information that forms the TMP should be held
by both BT and the CP in order for both to manage
the interconnection between the two networks.
Therefore, both BT and the CP are responsible for
ownership and retention of this information. - Whilst the information between BT and the CP is
for the most part exchanged within documentation
set out within the Provisioning Manual, it is for
each to identify the means with which such
information is recorded within their own systems. - It is recognised by both BT and the CP that, from
time to time, information may be lost or its
accuracy be questioned. Therefore, it is accepted
by both BT and the CP that requests for
information exchange over and above the normal
flow may occur. These requests are on an
occasional basis and the scope is kept to a
minimum in order to ensure that any such requests
are reasonable. In such circumstances both BT and
the CP would generally comply with requests of
this nature.
42Â AOB3 November 2005