Title: Linear Collider Options for SLAC
1Linear Collider Options for SLAC
- Tor Raubenheimer
- SLUO Town Meeting
- November 25th, 2003
2LC Group Membership
- Jim Brau
- Marty Breidenbach
- John Galayda
- Tom Himel (ex-officio)
- Ewan Paterson (co-chair)
- Tor Raubenheimer (co-chair)
- Marc Ross
- Bob Siemann
- Andy Wolski
3Linear Collider Schedule
- 2004 Technology choice
- Formation of international design team and
US bid to host - Start of Project Engineering and Design
- Start of LC construction (6 year
construction) - 2014 Early physics at 250 350 GeV ??
- 2015 Construction project finished
- Energy upgrades start (Installation of 100
GeV during each 3 month shutdown) - 2023 Operation at 1 TeV
Optimistic schedule! LC is a twenty to thirty
year commitment.
4S3 LC Group Goals
- What role does SLAC want in the linear collider?
- How do we design, construct and operate a linear
collider while keeping a strong set of individual
laboratories? - What might the ownership pieces be for SLAC?
- What about other laboratories?
- How might one divide the LC project for
construction and operation? - How should SLAC organize itself to be most
effective? - Does site or the technology choice make a
difference? - Is GAN a viable path? If not, what?
- Do not focus on management models (although some
discussion is necessary) - USLCSG, ELCSC, ALCSC, ILCSC are all considering
models
5Discussions on Other Projects
- Howard Gordon LHC detectors
- Norbert Holtkamp SNS Accelerator
- Jim Strait LHC Accelerator
- Robert Brown ALMA
- Bob Goldston ITER
- David Burke NLC
- Mostly helped us understand management models,
their limitations, and the implications - Certainly possible to build a project
collaboratively but may be hard to maintain
relationships through operation
6Linear Collider Assumptions
- Construction of a high luminosity 500 GeV e/e-
linear collider upgradeable to 1 TeV or higher
with 2 detectors - NLC (normal conducting) cost details based on NLC
1999 Lehman cost model - Superconducting cost based on ratios of costs
given in TDR but with a total assumed to be equal
to NLC - Fermilab cost study for TESLA under US accounting
rules estimated a value slightly less than NLC
for a collider upgradeable to 800 GeV - Three project stages
- Design and engineering through 2008
- Construction from 2009 through 2015
- Operation after 2015 (not considered because of
timescale - Aggressive schedule
7Accelerator Funding Assumptions
- Funding model 25 US contribution 35 extra to
host - The 35 is a large fraction of the civil
construction and site work - Feel this is reasonable to ask the host country
to assume - The 25 is based on the ratio of national GPD for
the remaining 65 - America Asia Europe all contribute 20 to 25
of the remainder - Fractions are at the high end of the proposals
- ELCSG committed chaired by G. Kalmus proposed 25
host-premium yielding a total US contribution of
about 50 - http//committees.web.cern.ch/Committees/ECFA/Cern
03KalmusReport.pdf - Contributions mostly in-kind but also in cash
- Much of the project contingency would be held by
a central office - Operations support would require cash
contributions
8National GDP Percentages
- Many proposals assume base contributions are
proportional to GDP - Total GDP of three major regions is similar
- US is the single largest with 20 25
Europe35
Americas37
Asia 28
9LC Management Models (1)
- No detailed assumptions on management models
except to assume a central project office which - Manages construction on the site including the
conventional construction and technical system
installation - Must at least have control of a significant cash
balance to ensure project completion - Can redirect portions of project construction as
necessary - The central office might be a lead laboratory
which has dominant control and sub-contracts out
portions to other laboratories - Similar to the LHC or SNS construction
- Collaborator ownership of contributions end
(decrease) upon delivery - Alternately, the central office might be a
independent group which manages the collaboration - Collaborators are responsible for operations,
maintenance, and upgrades
10ELCSG Management Model
11ACFA Management Model
12LC Management Models (2)
- Concern that it may be hard to prevent a central
office (LCCO) taking a dominant position on the
accelerator - It would be hard to compete against LCCO for top
people - It would be hard to compete against LCCO for
funding - The collaborative model sounds like a better
working environment however - There is probably little difference to a foreign
collaborator - For example, the US LHC group has been working
well with CERN and CERN has been encouraging an
ongoing relationship - There is also probably little difference before
commissioning and operations which were at the
end of the timescale considered - The biggest impact might be in the US where
multiple laboratories have a common funding source
13Reasons for SLAC Participation in LC
- The LC will be the premier accelerator project in
the world and we will want to be involved - Largest knowledge base for a linear collider
exists at SLAC - Strengthen/upgrade SLACs core competencies
- Very exciting project will attract very good
people - Most of SLACs technical and theoretical
innovative ideas have originated from problems
tied to building/operating accelerators - Need to have a large flux of problems and need to
have sufficient funds to explore technical
options ? need operating accelerator - Tight coupling between accelerator and detector
groups - As a large project, the LC can also assist a
change in direction by providing a smooth
transition to employment at a new LC laboratory
14Central Project Office
- A Central Project Office is assumed to be formed
at the start of construction - Two versions considered
- Primary laboratory model
- Sub-contract major portions of construction to
participating labs - Collaboration with strong central management
- Collaborators with in-kind and cash contributions
- Believe that the later would be a better model
for SLAC participation however - Small differences in terms of the contributions
during construction - Commissioning responsibilities are likely smaller
in the primary laboratory model as the lab would
assume control earlier - Operating responsibility would be small in
primary lab model but quite possibly end up being
small in the other case as well
15Global Accelerator Network (GAN)
- Discussed frequently!
- Everybodys favorite acronym but what does this
really mean? - People like to focus on operational model of
distributed control rooms but is the important
aspect? - Remote control of accelerator is certainly
technically possible - How to give control for aspects of the
accelerator and maintain this during the
operation phase? - Special problem for the US where multiple
laboratories compete for limited HEP funding - Why should DOE maintain multiple LC centers?
- Need critical mass to attract excellent people
- How to prevent central project office from
assuming full control? - No answers, these questions still need to be
resolved
16Questions Regarding Participation during LC
Operations
- In either management model, it is likely that
many (good) people will move towards the LC site
after construction - Project office will strive to grow and capture
good people - Hard to attract new people
- Dont want become backwater laboratory with 2nd
rate people - Hard to see artificial boundaries limiting the
size of the project office - Greater impact in the US with multiple HEP
laboratories - In CA, the project office would likely have a
strong tie to SLAC - In IL, the project office would probably be at
FNAL - SLAC may have a larger operating role at an
offshore site than a US site - Is this a problem? No, but it implies a
different path for the lab. - Some development work for upgrades may continue
at collaborating institutions but this will be
technology dependent - SLACs participation during operations phase is
likely dependent on technology and site location
17Linear Collider Cost Model NC
- Used 1999 Lehman costs with update for EDIA
- Present cost and cost ratios differ but not
enormously - Total cost was 5.1 B without contingency or
escalation - Technical costs 2.2 B
- Global costs 2.9 B dominated by the civil
construction - Technical costs were divided by Area and
Technical system - Area (Injector, Main Linac, and BDS)
- Technical (LLRF, Modulators, Klystrons,
Structures, Distribution, Magnets, Vacuum,
Instrumentation, and Installation) - Technical system installation costs were assigned
to project office - RD costs were assigned to the respective Areas
- Global costs were divided as
- Civil 1.7 B
- OPC, Control System, Manufacturing, and
Management 300M each
18Linear Collider Cost Model SC
- Used TDR cost ratios but a total cost similar to
the NC case - FNAL report estimated the TDR cost using US
accounting ruleswith a resultsimilar to NLC - Cost fractionsare similar
- Big differencesin civil and Linac
Modulesversus Linacstructures - TESLA DR isslightly more but other parts of the
injector are less
19Central Project Office Portion
- In our models, the central project office might
manage - 80 of the civil construction
- 20 of the civil cost is assumed offset through
equipment contributions - Technical system installation
- Smaller amounts for installation setup and
oversight managed by Areas - 50 of the OPC covering 67 of the Startup and
Pre-Ops costs - The pre-construction RD and commissioning
portion of the OPC is assigned to the Areas - 40 of the management and support costs
- This totals to 40 of the total project cost w/o
contingency - The project office would also hold the project
contingency which would be a large fraction of
the total contingency
20What Role for SLAC?
- Assume that SLAC would want a major role in the
LC - Play a leadership role in the LC design effort
- Primary efforts in
- Accel. Phys. (beam line design, modeling, and
commissioning) - High power rf Polarized e- source
- Also want to develop technologies that might be
useful for SLAC - S-band rf sources and structures
- What should be the scale of a contribution?
- US project with 60 US contribution
- 40 to US Project office 10 SLAC 10 other
- Foreign LC with 25 US contribution
- 5 foreign project office 10 SLAC 10 other
- SLAC FNAL would have major US portions
- Other laboratories (LBNL, BNL, Cornell) might
work through them
21Cost Model Matrix
- Matrix the project assigning responsibility for
Area Subsystems and different Technical Systems
to different parties - Example Warm US LC
- Injector system ? SLAC Main linac ? KEK BDS?
UK - X-band structures ? SLAC KEK Magnets ? FNAL
DESY - Etc.
22Sites Technology Options
- SLAC can contribute 10 to LC independent of
site and technology however the details will
differ - Major design effort at SLAC (2 of TPC )
- Projects can be broken into numerous pieces that
would be interesting - Look for topics with large accelerator physics
contribution - Look for early contributions eases transition
from design stage - Look for early commissioning get established on
the project quickly - Injector system seems like a good match for
either technology - Represents roughly 3 of TPC
- BDS is a good match to LCD but is a smaller
contribution 1.5 TPC - Other 5 depends on technology
- The NC X- and S-band rf couple well with SLAC
future and expertise - The SC 1.3 MHz klystrons still need development
and might be interesting - Beam line instrumentation might be interesting
- Magnets or vacuum or 1.3 GHz waveguide
23Model for aCalifornia Normal Conducting LC(CA
NC LC ??)
- SLAC might assume responsibility for
- Major role in design effort (2 TPC)
- Injector subsystem (includes DR) (3 TPC)
- Complicated accelerator physics issues
- Early commissioning
- S-band power and structures (technical portion of
Injector) (2 TPC) - Possible use for SLAC linac upgrade
- 50 of the X-band klystrons and X-band structures
(3 TPC) - Continue development of high power rf
- This amounts to 10 of TPC
- FNAL might contribute remaining 10 of the US
contribution - Alternate options would include the BDS
responsibility - Good match to LCD but
- Late commissioning and small contribution in
matrix model 1.5
24Model for German SuperConducting LC
- SLAC might assume responsibility for
- Major role in design effort (2 TPC)
- Injector subsystem (includes DR) (2 TPC)
- Complicated accelerator physics issues
- Early commissioning
- 50 of 1.3 GHz klystrons (1 TPC)
- Further development using klystron dept.
- Beam line instrumentation (3 TPC)
- Important subsystems tied to knowledge from SLC
- This also amounts to 10 of TPC
- FNAL might contribute remaining 10 of the US
contribution
25Model for SLAC Effort on LC Accelerator
- Maximum of roughly 250 people on the project
- Requires rapid buildup which would be hard with
PEP-ii upgrades and LCLS at the same time - Mix of people is similar to other projects as
well as NLC group - Topics chosen for participation are personnel
intensive - NLC funding model is frugal with EDIA 22 of TPC
- SLAC portion of project is much higher in EDIA
40 of the laboratory contribution - Effort is maximum early in the project 2010-2011
- Design effort and Injector systems are all
required early - Tapers off to be similar to present NLC effort
assuming some continuing participation
26LC Detector Assumptions
- Much more straightforward than the accelerator
- SLAC would like to have major responsibility for
one of the two detectors - Detectors are expected to cost 350 M each
- Collaborative construction model is natural
- 50 contribution to 350 M detector
- 50 physicists and main engineering group at SLAC
- Some prototyping and possibly responsibility for
major assemblies - SLAC should strive to be US collaboration host
- Reasonable if CA site unlikely if IL site
possible if offshore site
27Summary
- Developed models for SLACs contribution to a LC
- SLAC should aspire to make a 10 contribution to
an LC independent of site and/or technology - Where should SLAC put it efforts
- Play a leadership role in the LC design effort
- Primary efforts in
- Accelerator Physics (beam line design, modeling,
and commissioning) High power rf technologies
Polarized e- source - Also want to develop technologies that might be
useful for SLAC (S-band undulators
instrumentation) - Injector systems of either an NC or SC is an
excellent match - The beam delivery system is a smaller piece but
also a good match - Technology and site choices do matter for the
long-term (20 years) involvement in the linear
collider - More likely to remain involved in operations with
a local site and involved in rf upgrades on a
normal conducting collider