Linear Collider Options for SLAC - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Linear Collider Options for SLAC

Description:

Contributions mostly in-kind but also in cash ... Injector system SLAC; Main linac KEK; BDS UK. X-band structures SLAC & KEK; Magnets FNAL & DESY ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 28
Provided by: Star109
Category:
Tags: slac | cash | chair | collider | fund | linear | options | tied | uk

less

Transcript and Presenter's Notes

Title: Linear Collider Options for SLAC


1
Linear Collider Options for SLAC
  • Tor Raubenheimer
  • SLUO Town Meeting
  • November 25th, 2003

2
LC Group Membership
  • Jim Brau
  • Marty Breidenbach
  • John Galayda
  • Tom Himel (ex-officio)
  • Ewan Paterson (co-chair)
  • Tor Raubenheimer (co-chair)
  • Marc Ross
  • Bob Siemann
  • Andy Wolski

3
Linear Collider Schedule
  • 2004 Technology choice
  • Formation of international design team and
    US bid to host
  • Start of Project Engineering and Design
  • Start of LC construction (6 year
    construction)
  • 2014 Early physics at 250 350 GeV ??
  • 2015 Construction project finished
  • Energy upgrades start (Installation of 100
    GeV during each 3 month shutdown)
  • 2023 Operation at 1 TeV

Optimistic schedule! LC is a twenty to thirty
year commitment.
4
S3 LC Group Goals
  • What role does SLAC want in the linear collider?
  • How do we design, construct and operate a linear
    collider while keeping a strong set of individual
    laboratories?
  • What might the ownership pieces be for SLAC?
  • What about other laboratories?
  • How might one divide the LC project for
    construction and operation?
  • How should SLAC organize itself to be most
    effective?
  • Does site or the technology choice make a
    difference?
  • Is GAN a viable path? If not, what?
  • Do not focus on management models (although some
    discussion is necessary)
  • USLCSG, ELCSC, ALCSC, ILCSC are all considering
    models

5
Discussions on Other Projects
  • Howard Gordon LHC detectors
  • Norbert Holtkamp SNS Accelerator
  • Jim Strait LHC Accelerator
  • Robert Brown ALMA
  • Bob Goldston ITER
  • David Burke NLC
  • Mostly helped us understand management models,
    their limitations, and the implications
  • Certainly possible to build a project
    collaboratively but may be hard to maintain
    relationships through operation

6
Linear Collider Assumptions
  • Construction of a high luminosity 500 GeV e/e-
    linear collider upgradeable to 1 TeV or higher
    with 2 detectors
  • NLC (normal conducting) cost details based on NLC
    1999 Lehman cost model
  • Superconducting cost based on ratios of costs
    given in TDR but with a total assumed to be equal
    to NLC
  • Fermilab cost study for TESLA under US accounting
    rules estimated a value slightly less than NLC
    for a collider upgradeable to 800 GeV
  • Three project stages
  • Design and engineering through 2008
  • Construction from 2009 through 2015
  • Operation after 2015 (not considered because of
    timescale
  • Aggressive schedule

7
Accelerator Funding Assumptions
  • Funding model 25 US contribution 35 extra to
    host
  • The 35 is a large fraction of the civil
    construction and site work
  • Feel this is reasonable to ask the host country
    to assume
  • The 25 is based on the ratio of national GPD for
    the remaining 65
  • America Asia Europe all contribute 20 to 25
    of the remainder
  • Fractions are at the high end of the proposals
  • ELCSG committed chaired by G. Kalmus proposed 25
    host-premium yielding a total US contribution of
    about 50
  • http//committees.web.cern.ch/Committees/ECFA/Cern
    03KalmusReport.pdf
  • Contributions mostly in-kind but also in cash
  • Much of the project contingency would be held by
    a central office
  • Operations support would require cash
    contributions

8
National GDP Percentages
  • Many proposals assume base contributions are
    proportional to GDP
  • Total GDP of three major regions is similar
  • US is the single largest with 20 25

Europe35
Americas37
Asia 28
9
LC Management Models (1)
  • No detailed assumptions on management models
    except to assume a central project office which
  • Manages construction on the site including the
    conventional construction and technical system
    installation
  • Must at least have control of a significant cash
    balance to ensure project completion
  • Can redirect portions of project construction as
    necessary
  • The central office might be a lead laboratory
    which has dominant control and sub-contracts out
    portions to other laboratories
  • Similar to the LHC or SNS construction
  • Collaborator ownership of contributions end
    (decrease) upon delivery
  • Alternately, the central office might be a
    independent group which manages the collaboration
  • Collaborators are responsible for operations,
    maintenance, and upgrades

10
ELCSG Management Model
11
ACFA Management Model
12
LC Management Models (2)
  • Concern that it may be hard to prevent a central
    office (LCCO) taking a dominant position on the
    accelerator
  • It would be hard to compete against LCCO for top
    people
  • It would be hard to compete against LCCO for
    funding
  • The collaborative model sounds like a better
    working environment however
  • There is probably little difference to a foreign
    collaborator
  • For example, the US LHC group has been working
    well with CERN and CERN has been encouraging an
    ongoing relationship
  • There is also probably little difference before
    commissioning and operations which were at the
    end of the timescale considered
  • The biggest impact might be in the US where
    multiple laboratories have a common funding source

13
Reasons for SLAC Participation in LC
  • The LC will be the premier accelerator project in
    the world and we will want to be involved
  • Largest knowledge base for a linear collider
    exists at SLAC
  • Strengthen/upgrade SLACs core competencies
  • Very exciting project will attract very good
    people
  • Most of SLACs technical and theoretical
    innovative ideas have originated from problems
    tied to building/operating accelerators
  • Need to have a large flux of problems and need to
    have sufficient funds to explore technical
    options ? need operating accelerator
  • Tight coupling between accelerator and detector
    groups
  • As a large project, the LC can also assist a
    change in direction by providing a smooth
    transition to employment at a new LC laboratory

14
Central Project Office
  • A Central Project Office is assumed to be formed
    at the start of construction
  • Two versions considered
  • Primary laboratory model
  • Sub-contract major portions of construction to
    participating labs
  • Collaboration with strong central management
  • Collaborators with in-kind and cash contributions
  • Believe that the later would be a better model
    for SLAC participation however
  • Small differences in terms of the contributions
    during construction
  • Commissioning responsibilities are likely smaller
    in the primary laboratory model as the lab would
    assume control earlier
  • Operating responsibility would be small in
    primary lab model but quite possibly end up being
    small in the other case as well

15
Global Accelerator Network (GAN)
  • Discussed frequently!
  • Everybodys favorite acronym but what does this
    really mean?
  • People like to focus on operational model of
    distributed control rooms but is the important
    aspect?
  • Remote control of accelerator is certainly
    technically possible
  • How to give control for aspects of the
    accelerator and maintain this during the
    operation phase?
  • Special problem for the US where multiple
    laboratories compete for limited HEP funding
  • Why should DOE maintain multiple LC centers?
  • Need critical mass to attract excellent people
  • How to prevent central project office from
    assuming full control?
  • No answers, these questions still need to be
    resolved

16
Questions Regarding Participation during LC
Operations
  • In either management model, it is likely that
    many (good) people will move towards the LC site
    after construction
  • Project office will strive to grow and capture
    good people
  • Hard to attract new people
  • Dont want become backwater laboratory with 2nd
    rate people
  • Hard to see artificial boundaries limiting the
    size of the project office
  • Greater impact in the US with multiple HEP
    laboratories
  • In CA, the project office would likely have a
    strong tie to SLAC
  • In IL, the project office would probably be at
    FNAL
  • SLAC may have a larger operating role at an
    offshore site than a US site
  • Is this a problem? No, but it implies a
    different path for the lab.
  • Some development work for upgrades may continue
    at collaborating institutions but this will be
    technology dependent
  • SLACs participation during operations phase is
    likely dependent on technology and site location

17
Linear Collider Cost Model NC
  • Used 1999 Lehman costs with update for EDIA
  • Present cost and cost ratios differ but not
    enormously
  • Total cost was 5.1 B without contingency or
    escalation
  • Technical costs 2.2 B
  • Global costs 2.9 B dominated by the civil
    construction
  • Technical costs were divided by Area and
    Technical system
  • Area (Injector, Main Linac, and BDS)
  • Technical (LLRF, Modulators, Klystrons,
    Structures, Distribution, Magnets, Vacuum,
    Instrumentation, and Installation)
  • Technical system installation costs were assigned
    to project office
  • RD costs were assigned to the respective Areas
  • Global costs were divided as
  • Civil 1.7 B
  • OPC, Control System, Manufacturing, and
    Management 300M each

18
Linear Collider Cost Model SC
  • Used TDR cost ratios but a total cost similar to
    the NC case
  • FNAL report estimated the TDR cost using US
    accounting ruleswith a resultsimilar to NLC
  • Cost fractionsare similar
  • Big differencesin civil and Linac
    Modulesversus Linacstructures
  • TESLA DR isslightly more but other parts of the
    injector are less

19
Central Project Office Portion
  • In our models, the central project office might
    manage
  • 80 of the civil construction
  • 20 of the civil cost is assumed offset through
    equipment contributions
  • Technical system installation
  • Smaller amounts for installation setup and
    oversight managed by Areas
  • 50 of the OPC covering 67 of the Startup and
    Pre-Ops costs
  • The pre-construction RD and commissioning
    portion of the OPC is assigned to the Areas
  • 40 of the management and support costs
  • This totals to 40 of the total project cost w/o
    contingency
  • The project office would also hold the project
    contingency which would be a large fraction of
    the total contingency

20
What Role for SLAC?
  • Assume that SLAC would want a major role in the
    LC
  • Play a leadership role in the LC design effort
  • Primary efforts in
  • Accel. Phys. (beam line design, modeling, and
    commissioning)
  • High power rf Polarized e- source
  • Also want to develop technologies that might be
    useful for SLAC
  • S-band rf sources and structures
  • What should be the scale of a contribution?
  • US project with 60 US contribution
  • 40 to US Project office 10 SLAC 10 other
  • Foreign LC with 25 US contribution
  • 5 foreign project office 10 SLAC 10 other
  • SLAC FNAL would have major US portions
  • Other laboratories (LBNL, BNL, Cornell) might
    work through them

21
Cost Model Matrix
  • Matrix the project assigning responsibility for
    Area Subsystems and different Technical Systems
    to different parties
  • Example Warm US LC
  • Injector system ? SLAC Main linac ? KEK BDS?
    UK
  • X-band structures ? SLAC KEK Magnets ? FNAL
    DESY
  • Etc.

22
Sites Technology Options
  • SLAC can contribute 10 to LC independent of
    site and technology however the details will
    differ
  • Major design effort at SLAC (2 of TPC )
  • Projects can be broken into numerous pieces that
    would be interesting
  • Look for topics with large accelerator physics
    contribution
  • Look for early contributions eases transition
    from design stage
  • Look for early commissioning get established on
    the project quickly
  • Injector system seems like a good match for
    either technology
  • Represents roughly 3 of TPC
  • BDS is a good match to LCD but is a smaller
    contribution 1.5 TPC
  • Other 5 depends on technology
  • The NC X- and S-band rf couple well with SLAC
    future and expertise
  • The SC 1.3 MHz klystrons still need development
    and might be interesting
  • Beam line instrumentation might be interesting
  • Magnets or vacuum or 1.3 GHz waveguide

23
Model for aCalifornia Normal Conducting LC(CA
NC LC ??)
  • SLAC might assume responsibility for
  • Major role in design effort (2 TPC)
  • Injector subsystem (includes DR) (3 TPC)
  • Complicated accelerator physics issues
  • Early commissioning
  • S-band power and structures (technical portion of
    Injector) (2 TPC)
  • Possible use for SLAC linac upgrade
  • 50 of the X-band klystrons and X-band structures
    (3 TPC)
  • Continue development of high power rf
  • This amounts to 10 of TPC
  • FNAL might contribute remaining 10 of the US
    contribution
  • Alternate options would include the BDS
    responsibility
  • Good match to LCD but
  • Late commissioning and small contribution in
    matrix model 1.5

24
Model for German SuperConducting LC
  • SLAC might assume responsibility for
  • Major role in design effort (2 TPC)
  • Injector subsystem (includes DR) (2 TPC)
  • Complicated accelerator physics issues
  • Early commissioning
  • 50 of 1.3 GHz klystrons (1 TPC)
  • Further development using klystron dept.
  • Beam line instrumentation (3 TPC)
  • Important subsystems tied to knowledge from SLC
  • This also amounts to 10 of TPC
  • FNAL might contribute remaining 10 of the US
    contribution

25
Model for SLAC Effort on LC Accelerator
  • Maximum of roughly 250 people on the project
  • Requires rapid buildup which would be hard with
    PEP-ii upgrades and LCLS at the same time
  • Mix of people is similar to other projects as
    well as NLC group
  • Topics chosen for participation are personnel
    intensive
  • NLC funding model is frugal with EDIA 22 of TPC
  • SLAC portion of project is much higher in EDIA
    40 of the laboratory contribution
  • Effort is maximum early in the project 2010-2011
  • Design effort and Injector systems are all
    required early
  • Tapers off to be similar to present NLC effort
    assuming some continuing participation

26
LC Detector Assumptions
  • Much more straightforward than the accelerator
  • SLAC would like to have major responsibility for
    one of the two detectors
  • Detectors are expected to cost 350 M each
  • Collaborative construction model is natural
  • 50 contribution to 350 M detector
  • 50 physicists and main engineering group at SLAC
  • Some prototyping and possibly responsibility for
    major assemblies
  • SLAC should strive to be US collaboration host
  • Reasonable if CA site unlikely if IL site
    possible if offshore site

27
Summary
  • Developed models for SLACs contribution to a LC
  • SLAC should aspire to make a 10 contribution to
    an LC independent of site and/or technology
  • Where should SLAC put it efforts
  • Play a leadership role in the LC design effort
  • Primary efforts in
  • Accelerator Physics (beam line design, modeling,
    and commissioning) High power rf technologies
    Polarized e- source
  • Also want to develop technologies that might be
    useful for SLAC (S-band undulators
    instrumentation)
  • Injector systems of either an NC or SC is an
    excellent match
  • The beam delivery system is a smaller piece but
    also a good match
  • Technology and site choices do matter for the
    long-term (20 years) involvement in the linear
    collider
  • More likely to remain involved in operations with
    a local site and involved in rf upgrades on a
    normal conducting collider
Write a Comment
User Comments (0)
About PowerShow.com