D0 Trigger Status - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

D0 Trigger Status

Description:

Loss of senior engineer, Steve Gross. Loss of engineer, Kirsten Moore. Replacement uncertain ... 5 days to stuff & check. Installation/Commissioning ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 19
Provided by: GeraldC1
Category:
Tags: gross | status | stuff | trigger

less

Transcript and Presenter's Notes

Title: D0 Trigger Status


1
D0 Trigger Status
7 MHz input rate
Data
Framework
Data Log
L2 100ms
L1 4.2 ms
L3 48 ms
50 Hz
7 kHz
1000 Hz
48 nodes
128 terms
128 terms
  • Excellent progress all systems
  • Manpower Shortages
  • L1 Central Tracking
  • L1 Muon
  • L2 Integration
  • L3 Filtering/Database
  • Delivery Delays
  • L2 Alphas
  • L2 CIC/SFO
  • L3 DAQ

2
Framework Status
  • Components(MSU)
  • Operational
  • Installation/Commissioning
  • Support detector commissioning
  • Completing readout to L3
  • Integrating with L2
  • Firmware
  • Completion of pseudo-terms
  • Commissioning run-control
  • Personnel
  • Loss of senior engineer, Steve Gross
  • Loss of engineer, Kirsten Moore
  • Replacement uncertain
  • Schedule
  • Complete Readout to L3 1/11
  • L2 trigger mask and pseudo-terms deferred?

Good progress, on time
3
Detector/L1/L2 Components
L1 LUM
LUM
L2Cal
CAL
L1 FPS
L2PS
FPS
Global L2
CFT/ CPS
L1 CTPT
L2CFT
L2STT
SMT
L2 Muon
L1 Muon
Muon
L2FWCombined objects (e, m, j)
L1FPD
FPD
L1FW towers, tracks, correlations
4
Luminosity Monitor Status
  • Components(Brown)
  • Scintillator(48) Complete
  • Electronics
  • CAFÉ boards(175) on hand
  • Completing ADC(12) board layout, ordering parts
  • Vertex board, FPGA 75 complete, layout
    commencing.
  • Procuring signal cables(60) soon
  • Crate/PS on hand
  • Installation/Commissioning
  • Installed Scintillator 4/00
  • Cabling awaits FPS.
  • Commissioning thereafter
  • Software
  • Working on embedded software
  • Download currently underway.
  • Database under development
  • Schedule
  • February 1, Electronics Installed
  • March 1, Luminosity Monitoring

Good progress, on time
5
L1CTPT/FPS
6
L1 CTPT/FPS Status
  • Components
  • Analog(Fermilab-D0)
  • AFE-8MCM (primarily CFTax) At vendor, full order
    complete 1/01
  • AFE-12MCM (primarily FPS)
  • motherboard prototype this month
  • daughter prototype board order 1/01
  • Crates/Cables on hand
  • Power supplies delayed until new year (partial).
  • Mixer(Fermilab-CD)
  • Super-sector (1/5th) 11/15
  • Full Mixer 1/01
  • Digital(Fermilab-D0)
  • Motherboard here
  • Transition module 1/11
  • CTPT daughter boards 11/15
  • FPS daughter board order out, parts on order
  • Crates/Cables/PS here
  • Installation/Commissioning
  • Assembling test stands for digital/VHDL testing

7
L1 CTPT/FPS Status
  • Firmware
  • AFE Mixer complete
  • DFE 50
  • Collector/Broadcaster 50
  • No diagnostics
  • Personnel
  • Recently lost Kin Yip (FNAL postdoc) Juan
    Lizarazo (FNAL Co-op) both on VHDL
  • A position has been available but not yet filled
    a new student arrived.
  • Reduced engineering (John Anderson) has delayed
    AFE12.
  • Have redirected Jamieson Olsen to assist with
    VHDL, but need technical help to assist with
    reorganization and installation.
  • Schedule
  • Analog
  • 10 AFE8 installed, operating 12/00
  • Balance by 2/01
  • AFE12 unknown (in prototype)
  • Supplies as arrive
  • Digital
  • Sufficient hardware for commissioning
  • Balance Installed by 12/00

Good progress on all fronts AFE12, VHDL concerns

8
L1 CAL Status
  • Components
  • Analog pick-offs (320) to accommodate changed BW
    prototyped. 1FTE month to production
  • Quadrant hardware (40) circuit/firmware designed
  • L2/L3 Readout complete
  • Installation/Commissioning
  • Inactive until framework complete 11/00
  • Firmware
  • All exists, not all tested
  • Personnel
  • Same as framework
  • Schedule
  • Within a month progress should resume
  • Start w/ analog pick-offs
  • L2 L3 readout 11/00

Late but well before 3/01
9
L1 MUON Status
  • Components
  • L1MuTrigger (4 crates) Prod Beginning(UAz)
  • Motherboard starting production/fabrication
  • Scintillator daughter board preproduction in
    assembly
  • Wire daughter board production board in design
  • Crate Manager testing production card, balance to
    be assembled
  • Trigger Manager daughter-board starting prod/fab
    now
  • Serial Link Transmitters complete
  • Serial Link Receivers production testing
  • MCEN (5 crates) in Preprod Testing(BU)
  • MCEN preproduction testing underway
  • Centroid Daughter Board preprod testing underway
  • Crate manager preprod layout.
  • Crates/Backplanes complete
  • Power Supplies on order.
  • Installation/Commissioning
  • One trigger, one manager crate in operation and
    readout.
  • Next providing L1CTPT Manager Crate.
  • Two Octants triggering by 11/00

10
L1 Muon Status
  • Software
  • Download Infrastructure in place
  • Preproduction versions of all firmware exist.
  • No alarms, monitoring
  • Personnel
  • Arizona down to zero from two postdocs.
    Advertising for one replacement
  • Boston post doc hired, visa difficulties
  • Discussing Ken Johns buy-out.
  • Need help w/ assembly/test of PSupplies
  • Schedule
  • L1 Muon full crate commissioned 1/01
  • MCEN full crate commissioned 3/01

L1Muon before 3/01 Some concern MCEN, manpower
11
L2 Component Status
  • Alpha serial processors (MSU,UM,UIC)
  • Production Status
  • preproduction worked out-of-the-box
  • ADCO, same vendor that produced CDF TDCs
  • About 30 stuffed or nearly stuffed
  • Parts for another 15 in reserve
  • Many key components obsolete
  • Diagnostics _at_ UM
  • Four boards
  • To our knowledge none work
  • Diagnostics _at_ UIC
  • 10 boards
  • 2 incorrectly mounted components
  • 5 have partial functionality (1 close, others
    unknown)
  • Considering a range of options
  • Repair sufficient boards for March 1, 2001
  • Build new boards with larger vias and reserve
    parts
  • Build new boards with larger vias. Recover
    components and build full complement.
  • Re-layout board and/or find new vendor

12
L2 Components Cont.
  • MBT I/O Cards(U-Maryland)
  • 6 production cards received. 3 pass specs. 3
    under test now
  • Firmware functionality 90 done.
  • Remaining 25 boards built, parts on hand
  • Balance after Oct. tests.
  • FIC L1/L2 Interface(SACLAY)
  • Boards complete
  • Final firmware adjustments October 16-20.
  • SLIC Parallel Proc.(NIU,Columbia)
  • Boards complete
  • First results from DSP Central algorithm meet
    speed/efficiency requirements
  • CIC, SFO Muon/L2 Interface (U-Neb)
  • Prototypes pass battery of tests but not up to
    standard design practices (two layers,
    unconventional shielding planes, unequal traces
    on differential signals...)
  • Have solicited advice from Fermilab engineers but
    process delayed by illness. Restarting now.
  • Delivery unknown

13
L2 Status Cont.
  • Software
  • C Framework exists
  • Preprocessor algorithms well developed, global
    needs attention.
  • Installation/Commissioning
  • MCH and test stand racks and crates 85 done.
    Cabling 65 done
  • Commissioning sequence under discussion.
  • Personnel
  • Recently lost one key postdoc from UIC and one
    from Maryland, will lose another UIC postdoc at
    the end of the year
  • One UIC postdoc has been replaced and new ones
    added from MSU and Columbia
  • Lack of on-site coordinator has slowed progress.
    Discussing Nikos Varelas buy-out.
  • Lack of project engineer has slowed progress.
    However, Rich Kwarciany (CD Electronics System
    Engineer) has been a great help as an on-call
    consultant.
  • Schedule
  • Essentially on hold until alpha, CIC, SFO issues
    resolved.
  • Once alphas MBTs are on hand the L2CAL, L2CTT,
    L2PS can be assembled lt1 month.

MBT, SLIC, FIC ready before 3/01 Alpha, CIC/SFO,
manpower concerns
14
DAQ/L3
  • Evolved to a single multipurpose card used in
    VRC, SB, processor nodes (100)
  • VHDL code specific to VRC, SB, Node complete
  • ETG is one of a kind.

15
L3/DAQ Status
  • Components(Brown)
  • Layout done for 6 wks, parts procurement
    difficult.
  • 25 board order placed with vendor
  • Layout _at_ board houses. Bids received. Production
    complete lt 2 weeks.
  • Procuring parts now
  • 5 days to stuff check
  • Installation/Commissioning
  • Maintaining emulators for commissioning, no
    schedule delay for other systems.
  • Cable plant is minimal - reuses infrastructure,
    MCH 50 done, remainder under discussion.
  • Software(Brown,Washington)
  • Framework up and running
  • Nodes also operational
  • Schedule (full chain by Jan 1)
  • After receipt of board 1-2 week at Brown, then
    install 4 VRCs _at_ DAB
  • 2 wks install 1 SB, fiber between VRC-SB
  • 2 wks install multiple node adapters, fiber
    between SB-node.
  • ETG January

Software in good shape Watching delivery closely
16
Filtering/Database
  • Components(Various Institutions)
  • Operational version of ScriptRunner
  • Unpacking code for cal, smt and muon
  • electron, muon, jet, missing et, and tau tools
  • Database and interface in design.
  • Installation/Commissioning
  • Participating in online tests of PDTs, CFT.
  • Participating in 10 SiDet Test
  • Personnel
  • Impending departure of Charles Leggett (LBL)
    infra-structure (unpack,tool template,offline
    verification)
  • Carmem Silva (LAFEX) database, currently only
    1FTE on database
  • Insufficient support for NT release porting.
  • Schedule
  • 11/00 standard running including ScriptRunner in
    Mark Pass mode
  • 1/01 monitor displays available
  • 3/01 operational versions of all physics tools
    ported and available

Filtering operable, needs manpower
17
Reportable Milestones
Priorities (1) FWK, L1mu, L1CAL, L3 (2)
L2Global, L2CAL (3) L1L2 CTPT, FPS
18
Manpower Needs
  • To free engineers for VHDL preparation a senior
    technician to assist CTPT construction. Could
    also help with L1Muon, L2 installation.
  • An engineer to assist L2 debugging integration.
    This could be considered an escalation of the
    already valuable on-call arrangement.
  • Arrange full-time contributions for
  • Ken Johns L1Muon
  • Nikos Varelas L2
  • Two programmers for
  • L3 infrastructure/release
  • Database
Write a Comment
User Comments (0)
About PowerShow.com