Title: D0 Trigger Status
1D0 Trigger Status
7 MHz input rate
Data
Framework
Data Log
L2 100ms
L1 4.2 ms
L3 48 ms
50 Hz
7 kHz
1000 Hz
48 nodes
128 terms
128 terms
- Excellent progress all systems
- Manpower Shortages
- L1 Central Tracking
- L1 Muon
- L2 Integration
- L3 Filtering/Database
- Delivery Delays
- L2 Alphas
- L2 CIC/SFO
- L3 DAQ
2Framework Status
- Components(MSU)
- Operational
- Installation/Commissioning
- Support detector commissioning
- Completing readout to L3
- Integrating with L2
- Firmware
- Completion of pseudo-terms
- Commissioning run-control
- Personnel
- Loss of senior engineer, Steve Gross
- Loss of engineer, Kirsten Moore
- Replacement uncertain
- Schedule
- Complete Readout to L3 1/11
- L2 trigger mask and pseudo-terms deferred?
Good progress, on time
3Detector/L1/L2 Components
L1 LUM
LUM
L2Cal
CAL
L1 FPS
L2PS
FPS
Global L2
CFT/ CPS
L1 CTPT
L2CFT
L2STT
SMT
L2 Muon
L1 Muon
Muon
L2FWCombined objects (e, m, j)
L1FPD
FPD
L1FW towers, tracks, correlations
4Luminosity Monitor Status
- Components(Brown)
- Scintillator(48) Complete
- Electronics
- CAFÉ boards(175) on hand
- Completing ADC(12) board layout, ordering parts
- Vertex board, FPGA 75 complete, layout
commencing. - Procuring signal cables(60) soon
- Crate/PS on hand
- Installation/Commissioning
- Installed Scintillator 4/00
- Cabling awaits FPS.
- Commissioning thereafter
- Software
- Working on embedded software
- Download currently underway.
- Database under development
- Schedule
- February 1, Electronics Installed
- March 1, Luminosity Monitoring
Good progress, on time
5L1CTPT/FPS
6L1 CTPT/FPS Status
- Components
- Analog(Fermilab-D0)
- AFE-8MCM (primarily CFTax) At vendor, full order
complete 1/01 - AFE-12MCM (primarily FPS)
- motherboard prototype this month
- daughter prototype board order 1/01
- Crates/Cables on hand
- Power supplies delayed until new year (partial).
- Mixer(Fermilab-CD)
- Super-sector (1/5th) 11/15
- Full Mixer 1/01
- Digital(Fermilab-D0)
- Motherboard here
- Transition module 1/11
- CTPT daughter boards 11/15
- FPS daughter board order out, parts on order
- Crates/Cables/PS here
- Installation/Commissioning
- Assembling test stands for digital/VHDL testing
7L1 CTPT/FPS Status
- Firmware
- AFE Mixer complete
- DFE 50
- Collector/Broadcaster 50
- No diagnostics
- Personnel
- Recently lost Kin Yip (FNAL postdoc) Juan
Lizarazo (FNAL Co-op) both on VHDL - A position has been available but not yet filled
a new student arrived. - Reduced engineering (John Anderson) has delayed
AFE12. - Have redirected Jamieson Olsen to assist with
VHDL, but need technical help to assist with
reorganization and installation. - Schedule
- Analog
- 10 AFE8 installed, operating 12/00
- Balance by 2/01
- AFE12 unknown (in prototype)
- Supplies as arrive
- Digital
- Sufficient hardware for commissioning
- Balance Installed by 12/00
Good progress on all fronts AFE12, VHDL concerns
8L1 CAL Status
- Components
- Analog pick-offs (320) to accommodate changed BW
prototyped. 1FTE month to production - Quadrant hardware (40) circuit/firmware designed
- L2/L3 Readout complete
- Installation/Commissioning
- Inactive until framework complete 11/00
- Firmware
- All exists, not all tested
- Personnel
- Same as framework
- Schedule
- Within a month progress should resume
- Start w/ analog pick-offs
- L2 L3 readout 11/00
Late but well before 3/01
9L1 MUON Status
- Components
- L1MuTrigger (4 crates) Prod Beginning(UAz)
- Motherboard starting production/fabrication
- Scintillator daughter board preproduction in
assembly - Wire daughter board production board in design
- Crate Manager testing production card, balance to
be assembled - Trigger Manager daughter-board starting prod/fab
now - Serial Link Transmitters complete
- Serial Link Receivers production testing
- MCEN (5 crates) in Preprod Testing(BU)
- MCEN preproduction testing underway
- Centroid Daughter Board preprod testing underway
- Crate manager preprod layout.
- Crates/Backplanes complete
- Power Supplies on order.
- Installation/Commissioning
- One trigger, one manager crate in operation and
readout. - Next providing L1CTPT Manager Crate.
- Two Octants triggering by 11/00
10L1 Muon Status
- Software
- Download Infrastructure in place
- Preproduction versions of all firmware exist.
- No alarms, monitoring
- Personnel
- Arizona down to zero from two postdocs.
Advertising for one replacement - Boston post doc hired, visa difficulties
- Discussing Ken Johns buy-out.
- Need help w/ assembly/test of PSupplies
- Schedule
- L1 Muon full crate commissioned 1/01
- MCEN full crate commissioned 3/01
L1Muon before 3/01 Some concern MCEN, manpower
11L2 Component Status
- Alpha serial processors (MSU,UM,UIC)
- Production Status
- preproduction worked out-of-the-box
- ADCO, same vendor that produced CDF TDCs
- About 30 stuffed or nearly stuffed
- Parts for another 15 in reserve
- Many key components obsolete
- Diagnostics _at_ UM
- Four boards
- To our knowledge none work
- Diagnostics _at_ UIC
- 10 boards
- 2 incorrectly mounted components
- 5 have partial functionality (1 close, others
unknown) - Considering a range of options
- Repair sufficient boards for March 1, 2001
- Build new boards with larger vias and reserve
parts - Build new boards with larger vias. Recover
components and build full complement. - Re-layout board and/or find new vendor
12L2 Components Cont.
- MBT I/O Cards(U-Maryland)
- 6 production cards received. 3 pass specs. 3
under test now - Firmware functionality 90 done.
- Remaining 25 boards built, parts on hand
- Balance after Oct. tests.
- FIC L1/L2 Interface(SACLAY)
- Boards complete
- Final firmware adjustments October 16-20.
- SLIC Parallel Proc.(NIU,Columbia)
- Boards complete
- First results from DSP Central algorithm meet
speed/efficiency requirements - CIC, SFO Muon/L2 Interface (U-Neb)
- Prototypes pass battery of tests but not up to
standard design practices (two layers,
unconventional shielding planes, unequal traces
on differential signals...) - Have solicited advice from Fermilab engineers but
process delayed by illness. Restarting now. - Delivery unknown
13L2 Status Cont.
- Software
- C Framework exists
- Preprocessor algorithms well developed, global
needs attention. - Installation/Commissioning
- MCH and test stand racks and crates 85 done.
Cabling 65 done - Commissioning sequence under discussion.
- Personnel
- Recently lost one key postdoc from UIC and one
from Maryland, will lose another UIC postdoc at
the end of the year - One UIC postdoc has been replaced and new ones
added from MSU and Columbia - Lack of on-site coordinator has slowed progress.
Discussing Nikos Varelas buy-out. - Lack of project engineer has slowed progress.
However, Rich Kwarciany (CD Electronics System
Engineer) has been a great help as an on-call
consultant. - Schedule
- Essentially on hold until alpha, CIC, SFO issues
resolved. - Once alphas MBTs are on hand the L2CAL, L2CTT,
L2PS can be assembled lt1 month.
MBT, SLIC, FIC ready before 3/01 Alpha, CIC/SFO,
manpower concerns
14DAQ/L3
- Evolved to a single multipurpose card used in
VRC, SB, processor nodes (100) - VHDL code specific to VRC, SB, Node complete
- ETG is one of a kind.
15L3/DAQ Status
- Components(Brown)
- Layout done for 6 wks, parts procurement
difficult. - 25 board order placed with vendor
- Layout _at_ board houses. Bids received. Production
complete lt 2 weeks. - Procuring parts now
- 5 days to stuff check
- Installation/Commissioning
- Maintaining emulators for commissioning, no
schedule delay for other systems. - Cable plant is minimal - reuses infrastructure,
MCH 50 done, remainder under discussion. - Software(Brown,Washington)
- Framework up and running
- Nodes also operational
- Schedule (full chain by Jan 1)
- After receipt of board 1-2 week at Brown, then
install 4 VRCs _at_ DAB - 2 wks install 1 SB, fiber between VRC-SB
- 2 wks install multiple node adapters, fiber
between SB-node. - ETG January
Software in good shape Watching delivery closely
16 Filtering/Database
- Components(Various Institutions)
- Operational version of ScriptRunner
- Unpacking code for cal, smt and muon
- electron, muon, jet, missing et, and tau tools
- Database and interface in design.
- Installation/Commissioning
- Participating in online tests of PDTs, CFT.
- Participating in 10 SiDet Test
- Personnel
- Impending departure of Charles Leggett (LBL)
infra-structure (unpack,tool template,offline
verification) - Carmem Silva (LAFEX) database, currently only
1FTE on database - Insufficient support for NT release porting.
- Schedule
- 11/00 standard running including ScriptRunner in
Mark Pass mode - 1/01 monitor displays available
- 3/01 operational versions of all physics tools
ported and available
Filtering operable, needs manpower
17Reportable Milestones
Priorities (1) FWK, L1mu, L1CAL, L3 (2)
L2Global, L2CAL (3) L1L2 CTPT, FPS
18Manpower Needs
- To free engineers for VHDL preparation a senior
technician to assist CTPT construction. Could
also help with L1Muon, L2 installation. - An engineer to assist L2 debugging integration.
This could be considered an escalation of the
already valuable on-call arrangement. - Arrange full-time contributions for
- Ken Johns L1Muon
- Nikos Varelas L2
- Two programmers for
- L3 infrastructure/release
- Database