Title: TOF Project Construction Project Plan


1
TOF ProjectConstruction Project Plan
  • Technical, Cost, Schedule, Management Review
  • Ralph Brown, 8/22/05

2
Project Management Controls
  • WBS Structure.
  • ESHQ Design Standards and Guidelines.
  • Engineering Drawing Controls.
  • Change Control Procedures.
  • Contingency Analysis.
  • Resource Loaded Project Plan.

3
Work Breakdown Structure
4
Design Standards and Guidelines
  • Design must comply with BNL/C-A/STAR
    institutional standards (SBMS) for ESHQ
    requirements in engineering design, electrical
    safety, work planning and control of experiments,
    experimental safety review, STAR design review
    and C-A OPM.
  • Bill Christie STAR/C-A Safety Liaison.
  • Local institutional standards used for
    fabrication, assembly, and test.
  • Q/A, managed by TOF project office with
    institutional MOUs, compliance with local
    institutional procurement policies. Large
    procurements require a Statement of Work and
    Product Specification.

5
Engineering Drawing Control
6
Change Control Procedures
7
Contingency Analysis
  • Risk is a function of the following factors 
    The sophistication of the technology, the
    maturity of the design effort, the accuracy of
    the cost sources and the impact of delays in the
    schedule.  Risk analysis shall be performed for
    each WBS element at the lowest level estimated. 
    Results of this analysis will be related to a
    contingency which shall be listed for each WBS
    element.  The goal is to make the method of
    contingency determination uniform amongst all
    project WBS elements.

8
Contingency Analysis
9
Contingency Analysis
10
Contingency Analysis
11
TOF Project Resource Loaded Plan
12
TOF Project Resource Loaded Plan (cont.)
13
TOF Project Resource Loaded Plan (cont.)
14
TOF Project Resource Loaded Plan (cont.)
15
TOF Project Resource Loaded Schedule
  • All costs are in FY05 dollars, and institutional
    labor rates and procurements are fully burdened
  • STAR Operations labor and Scientific labor are
    contributed cost.
  • TOF project calendar assumes 220 days or 1760 hrs
    per yr.
  • MSTC (travel misc. cost) for subsystems
    included.
  • Project milestones are included.
  • Procurements deliverables have been phased into
    FYs.
  • Subsystem tasks have been linked constrained to
    develop critical path.
  • Monthly subsystem reporting on task complete to
    project office.
  • Quarterly reporting of project performance and
    milestone completion to BNL Project Manager.

16
TOF Project Critical Path
17
TOF Project Resource Usage