Title: NSLS-II Project Update


1
NSLS-II Project Update
Steve Dierker Associate Laboratory Director for
Light Sources, NSLS-II Project Director Experiment
al Facilities Advisory Committee April 23, 2009
2
CD-3 Approval
  • Independent Project Review - Sep 30-Oct 2, 2008
  • 3 recommendations
  • Include all three bypass corridors where long
    beamlines may be sited
  • Implement a Lessons Learned program
  • Approve CD-3
  • External Independent Review (OECM) - Oct 20-24,
    2008
  • 7 major findings
  • Implement an alternative tailored approach to
    CD-3 for technical baseline
  • Rest are clean-ups of details in cost and
    schedule
  • All have been closed
  • ESAAB meeting held Tuesday, Nov 18
  • CD-3 Approved on January 9 by DOE Deputy
    Secretary
  • Approval to start construction

3
Key Project Milestones
Aug 2005 CD-0, Approve Mission
Need (Complete) Jul 2007 CD-1, Approve
Alternative Selection and Cost Range (Complete) J
an 2008 CD-2, Approve Performance
Baseline (Complete) Jan 2009 CD-3, Approve Start
of Construction (Complete) Feb 2009 Contract
Award for Ring Building (Complete) Aug
2009 Contract Award for Storage Ring
Magnets Mar 2010 Contract Award for Booster
System Feb 2011 1st Pentant Ring Building
Beneficial Occupancy Begin Accelerator
Installation Feb 2012 Beneficial Occupancy of
Experimental Floor Oct 2013 Start Accelerator
Commissioning Jun 2014 Early Project
Completion Ring Available to Beamlines Jun
2015 CD-4, Approve Start of Operations
4
Project Funding
  • FY09 Omnibus Bill passed on March 12 included
    103M funding for NSLS-II
  • Stimulus bill provided 150M additional funding
    allocation for NSLS-II project TPC remains same
    (912M) but profile changed
  • Accelerates Ring Building, Chilled Water,
    Electrical Substation, Unit Substations, LOBs
  • Front loaded profile exactly what we need

OLD
NEW
5
Cost Schedule Performance
Scheduled Work 12.3 Performed Work
12.0 Actual Cost 11.3
  • Overall, on budget and on schedule
  • Cumulative SPI 0.98, CPI 1.05
  • Closely watching schedule performance and
    variance analysis
  • Formulating and reviewing possible mitigation
    plans

6
NSLS-II Management Team
Steven DierkerAssociate Lab Director for Light
Sources Project Director
Aesook ByonDeputy Project Director
Satoshi OzakiSenior Project Advisor
James YeckAssistant Project Director for
Conventional Construction
Qun ShenExperimental Facilities Division
Ferdinand WillekeAccelerator Division
Martin FallierConventional Facilities Division
Diane HattonProject Support Division
Wayne HendricksonAssociate Project Director
for Life Sciences
7
NSLS-II Director for Life Sciences
  • Wayne Hendrickson
  • Associate Director for Life Sciences, NSLS-II
  • University Professor, Columbia University
  • Investigator, Howard Hughes Medical Institute
  • Professional Background
  • Spokesperson for X4A/X4C PRT at NSLS
    (1987-present)
  • BSA Science and Technology Steering Committee
    (2001-2008)
  • NSLS-II Project Advisory Committee (2006-2008)
  • Responsible for developing establishing NSLS-II
    Life Sciences program
  • Development of strategic plans for the use of
    NSLS-II in life sciences research
  • Coordination with the life sciences community and
    representation of needs
  • Coordination with potential funding agencies
  • Representation of needs of life sciences in the
    design and construction of NSLS-II
  • Development, construction and operation of life
    science facilities at NSLS-II, including
    beamlines
  • Lisa Miller
  • Deputy Associate Director for Life Sciences,
    NSLS-II
  • Division Head for Life and Environmental
    Sciences, NSLS

8
NSLS-II Project Organization
9
High Level NSLS-II Project Organization
10
Progress on NSLS-II Staffing
  • 27 Open Requisitions with 8 offers in process
  • Total hires now at 183
  • Human Resources is now supporting both NSLS and
    NSLS-II
  • Better service and enhanced recruiting for both
    Light Sources Directorate Organizations
  • Helps with Transition Efforts

11
Great Progress
Light Sources Directorate Picnic
12
Aerial View
NSLS-II
CFN
NSLS
13
Conventional Facilities Progress
  • Ring building bid package released to industry on
    Oct 1, 2008
  • General Contractor bids received December 5
  • Torcon, Inc has been selected as the General
    Contractor for the Ring Building construction
  • Price consistent with baseline - enables
    retirement of significant risk
  • Site Preparation completed
  • Developing plans for ground breaking ceremony in
    May
  • Advancing LOB design construction schedule

Contract Signing February 18, 2009
14
Advancing LOB Design
  • Design paused after only conceptual design phase
  • Ring Building Contractor has indicated ideal time
    for LOB start would be mid FY10 from standpoint
    of constructability as well as efficiency
  • Advancing LOB design and construction
  • To improve constructability and efficiency
  • To capitalize on current market conditions
  • To fulfill (comply) ARRA justification
    (requirement)
  • To minimize risks and challenges during
    commissioning early operations of accelerator
    and beamlines

15
Accelerator Systems Progress
  • Storage Ring
  • All prototype magnets delivered to BNL
  • measurements completed met performance spec
  • Magnet RFP about to be released contract award
    by mid-August
  • Support Systems, girder positioning tests
    completed successfully
  • Vacuum 2nd dipole vacuum chamber prototype
    successfully bent
  • Electrical Systems
  • Main circuit schematics completed and component
    tests under preparation
  • Instrumentation
  • Prototype of High Stability BPM stand assembled
  • BPM Electronics BPM cables detailed
    requirements controls interface developed
  • Insertion Devices
  • Development of Bldg 832 for ID-Lab laboratory
    underway
  • Technical documentation for damping wiggler
    design contract prepared
  • Simulations of the NSLS-II Elliptically Polarized
    Undulator (EPU)

Magnet Measurements at BNL
Environmental Room for Magnet Alignment on Girders
16
Reviews Advisory Committees
  • GAO (Government Accountability Office) Audit
  • Site visit Apr 14-17 requested by Congress to
    examine DOEs cost estimating techniques/methodolo
    gies.
  • DOE reviews in 2009
  • Mini-review on June 9-11 focus on Accelerator
    Systems and Experimental Facilities
  • Full review in Sep-Oct focus on Conventional
    Facilities
  • Advisory Committee Meetings
  • CFAC March 10-11
  • ASAC March 26-27
  • EFAC April 23-24
  • PAC Summer date being finalized

17
Light Sources Directorate Strategic Planning
  • High Level Long Term Vision for Light Sources
    Directorate
  • Operate a world leading synchrotron with
    excellent reliability, a thriving user program,
    and outstanding scientific productivity and
    impact, and be recognized as a leader in
    developing new techniques and applications of
    synchrotron radiation
  • Achieving this requires
  • Delivering NSLS-II on-time and on-budget fully
    mission capable
  • Continuing excellent operation of NSLS until
    NSLS-II operations
  • Establishing outstanding NSLS-II operations

18
Light Sources Directorate
NSLS-II Operations
Working to better define
NSLS Operations
NSLS-II Project
Very well developed
19
Expected Funding Profile for Light Sources
Directorate
NSLS-II TEC 791M TPC 912M
Note NSLS and NSLS-II Operations MIE funding
are not part of TPC Does not include potential
NSLS-II WFO funding (e.g, NIH)
20
Notional Staffing Profile forLight Sources
Directorate
Note Does not include staffing required for
NSLS-II MIE projects or WFO Projects (e.g., NIH)
21
Light Sources Directorate Facilities
745
725
NSLS-II Bldg No Sq Ft 745 504,000 817 11,600 830M
4,100 832 6,900 902/905 11,300 945 3,900 820 1,1
00 703 9,900 Trailer 700 Total 553,500
NSLS Bldg No Sq Ft 725 155,200 726 3,300 727 3,900
728 2,500 729 7,100 751 700 820 6,600 535 16,300
Trailers 1,100 Total 195,600
817
726
727
728
832
Total Directorate 749,100 square feet
729
902/905
703
22
The Future will look very different from today
  • There has been tremendous growth and change
  • within the Light Sources Directorate,
  • and more is coming.
  • FY05 FY16
  • 5x growth in funding 40M/yr gt200M/yr
  • 3x growth in staffing 175 gt500
  • 4x growth in facilities 195,000 sf 750,000 sf
  • 50 increase in users/yr 2300/yr 3500/yr
  • 10,000x increase in x-ray brightness

23
Light Sources Directorate Issues
  • Safety
  • Organization
  • Staffing
  • Space
  • Funding (Project, Facility, MIE, Early Ops, NIH,
    etc)
  • Schedule
  • Communications
  • Stakeholder issues (Advisory Committees, User
    Groups, etc)
  • Scientific Strategic Plan
  • Commissioning and Build-out of NSLS-II
  • Decommissioning and reuse of NSLS
  • Scientific and technical risks
  • Managing growth and change
  • Productivity
  • Becoming best in class in future NSLS-II
    operations
  • other.

24
Planning Considerations
  • NSLS-II still has significant uncertainties and
    risks
  • However, with CD-3 approval, we have sufficient
    confidence in future developments to justify more
    detailed planning for the future
  • DOE will begin formulating the FY12 budget in
    FY10 ( one year from now) and we expect this to
    be the beginning of NSLS-II early operations
    funding and MIE funding
  • We want to develop more detailed plans during
    FY09 to better inform DOE in its budget
    development
  • There is also a need to develop more detailed
    plans for how a number of issues will be managed
  • It is essential that the management team within
    the Light Sources Directorate work together to
    coordinate activities, identify issues, develop
    solutions, and collectively implement them

25
Light Sources Directorate Strategic Planning
  • Management retreats to bring together senior
    NSLS-II and NSLS management to discuss strategic
    planning from now through to NSLS-II operations
  • 20 Senior Managers from NSLS-II and NSLS
  • Objectives of first retreat Feb 12, 13
  • Develop a better dialogue and broader
    understanding of the responsibilities,
    constraints, goals of the Light Sources
    Directorate, at the directorate, organizational,
    functional levels
  • Identify concerns, issues, areas that need
    further study
  • Objectives of second retreat Mar 12, 13
  • Develop a better understanding of the potential
    barriers to achieving our goals and
    identification of critical actions needed to
    mitigate risks
  • Provide input for development of a Light Sources
    Directorate Strategic Plan
  • Mission, Vision, Values, High Level Goals
    Strategies, Strategic Focus Areas
  • Develop a framework and schedule for moving
    forward

26
Next Steps
  • Working group (Dierker, Byon, Kao, Hatton,
    Terrano) is developing a draft plan based on
    retreat input iterating with larger group to
    refine
  • The plan will then be shared with our other
    stakeholders for input
  • The plan will be revised in light of that
    feedback and then adopted
  • We are working to achieve an internally agreed
    upon plan by early summer and a final plan that
    incorporates external input by end of summer
  • We expect that the plan will call for creation of
    task forces to further develop selected strategic
    focus areas
  • It is a large amount of work to prepare a quality
    document
  • This process is underway, and we will reach out
    to the appropriate communities, be forward
    looking, and obtain buy-in from all stakeholders
    as we proceed
  • Light Sources Directorate strategic planning is a
    major activity in FY09

27
Charge to EFAC
  • With RD and beamline design activities being deve
    loped and significant progress being made,
    completing the conceptual designs for all six
    project beamlines by end of FY09 is now the focus
    of the NSLS-II Experimental Facilities.
    Therefore, at this EFAC meeting, the Committee is
    asked to focus on reviewing recent progress in
    Experimental Facilities RD and in beamline
    conceptual designs.
  • Specifically, the Committee is asked to 
  • Review the 1 nm Optics RD program, including the 
    plan forward in optics fabrication and system
    designs
  • Review the 0.1 meV optics RD program, including t
    he plan forward in optics fabrication and system
    designs
  • Review the NSLS-II plan for mirror metrology and m
    irror development
  • Review the beamline conceptual design progress for
     all six project beamlines and provide feedback
  • Review the space allocation plan in Laboratory and
     Office Buildings (LOBs)