Title: PEP-II in Run 7 and Transition Planning


1
PEP-II in Run 7 and Transition Planning
  • John T. Seeman
  • Assistant Director PPA/LCLS

2
Talk Overview
  • Brief PEP-II Layout
  • Run 7 operations
  • Transition planning
  • PEP-II Minimum Maintenance State
  • Future possibilities for PEP-II tunnel and
    hardware

3
PEP-II Mission in FY2008
  • To provide ee- collisions to the BaBar Detector
    to carry out B-meson and other physics
  • Advance the State of the Art for accelerator
    physics for high luminosity colliders
  • Enter a Minimum Maintenance State after the
    collider programs terminates.
  • Start the study for Deactivation and
    Decommissioning.

4
The PEP-II Team
PEP-II was constructed by SLAC, LBNL, and LLNL
with help from BINP, IHEP, BaBar
collaboration. Many thanks to the US Department
of Energy And Machine Advisory Committee.

1x1034
5
Brief PEP-II History
  • 1987 Physics asymmetrical energies helps
    separate B mesons.
  • 1991 First PEP-II CDR.
  • 1993 Second CDR (9 GeV x 3.1 GeV).
  • 1994 Construction started.
  • 1997 First stored HER e- beam.
  • 1998 First stored LER e beam.
  • 1998 First collisions July 23, 1998, at 1205
    pm.
  • 1999-2007 Y4S data for BaBar (433 fb-1)
  • 2008 Y2S (30 fb-1), Y3S (15 fb-1), and small
    energy scan for BaBar.
  • 2008 Turned off PEP-II April 7, 2008, at 1122
    pm
  • just after setting an e current world
    record (3.2 A).
  • 1999-2008 Total delivered integrated luminosity
    557.4 fb-1.

6
PEP-II Layout

Two rings Circumference 2.2 km.
7
B-Factory Overall Parameters
  • Parameter PEP-II
  • (LER/HER)
  • Circumference (m) 2200
  • Beam energy (GeV) 3.1/9.0
  • Number of bunches 1732
  • Beam currents (A) 3.2/2.0
  • Horizontal emittance (nm) 30/45
  • by (mm) 9/11
  • xy 0.06/0.05
  • IP beam sizes (microns) (x/y) 120/4
  • Luminosity (x 1033/cm2/s) 12.1

8

The PEP-II Collider
9
PEP-II Interaction Region Components near BaBar
BaBar Detector
LER
HER
BaBar
Collision point
10
How the beams enter and exit the PEP-II
Interaction Region
11
IR Permanent Magnets
12
Interaction Region Support Tube
Be chamber
Silicon Vertex Tracker SVT
13
What worked with the PEP-II Accelerator design?
  • All components as designed worked to get above
    the design luminosity parameters (magnets, RF
    system, vacuum system, interaction region,
    background mitigation, beam instabilities,
    bunch-by-bunch feedbacks, injection, controls)
  • Major changes to get to x 4 luminosity and x 7
    integrated luminosity
  • Electron cloud instability needed 30 gauss
    solenoids on LER
  • Added cooling on IP Be chamber bellows.
  • Improved masking near IR
  • Added 7 RF stations to handle added current.
  • Improved feedback kickers
  • Improved RF controls
  • Higher power vacuum expansion bellows
  • Continuous injection mitigation
  • Shorten abort gap (3 to 1)
  • Improved quadrupole lattices
  • Improved x-y coupling control

14
PEP-II RF Cavity
Early design and testing at LBL. High power
production cells. Fully fitted cavity units with
HOM dampers.
15

B-Factory RF Klystrons (1.2 MW)

16
HOM Absorbing Bellows

Shield fingers
HOM tiles
17
Running before Trickle (Continuous) Injection

18
Continuous Injection for PEP-II

19
Luminosity Equation for a Circular ee- Collider
  • xy is the beam-beam parameter (0.06)
  • Ib is the bunch current (1 to 3 mA)
  • n is the number of bunches (1700)
  • by is the IP lattice optics function (vertical
    beta) (10 mm)
  • E is the beam energy (3.1 and 9 GeV)
  • (9 GeV varied to change Upsilon resonances.)
  • Luminosity (1033 cm-2 s-1)

20
Beam-beam parameters
sy 3.5-4.3 mm. xy 0.05-0.06 xx 0.03-0.09

By 4 Extended
By 2
I- increases LER y size. I increases LER x
size. I increases HER y size.
21
PEP-II Parameters for 3.1 GeV x 9.0 GeV
Parameter Units Design April 2008 Best Factor over Design
I mA 2140 3210 X1.50
I- mA 750 2070 X2.76
Number bunches 1658 1732 X1.04
by mm 15-25 9-10 1/2.0
Bunch length mm 15 11-12 1/1.42
xy 0.03 0.05-0.06 X2.0
Luminosity X1033/cm2/s 3 12 X4.0
Int lumi / day pb-1 130 911 X7.0
22
Upsilon Resonances
  • To change center-of-mass energy, PEP-II changed
    HER energy (8.0 to 10.1 GeV) but not LER due to
    permanent magnet focusing in the interaction
    region.

Resonance Data HER Energy
Y2S 14.5 fb-1 8.1 GeV
Y3S 30 fb-1 8.4 GeV
Y4S 433 fb-1 9.0 GeV
Scan above Y4S (5 MeV steps) 4.6 fb-1 8.9 to 10.1 GeV
23
PEP-II Peak Luminosity by Month (1999-2008)

Design
24
Design of 135 pb-1
25
(No Transcript)
26
PEP-II total integrated luminosity 557 fb-1
27

28
PEP-II Uptime and Luminosity Integration vs
Milestones

Uptime DOE Milestone Uptime PEP-II Actual Uptime Ratio PEP/DOE Integr. Lumin. DOE Milestone Integr. Lumin. PEP-II Actual Int. Lum. Ratio PEP/DOE
FY2002 80 84.0 1.05 35 fb-1 49.0 fb-1 1.40
FY2003 80 82.4 1.03 45 fb-1 39.9 fb-1 0.89
FY2004 80 88.8 1.11 45 fb-1 114.4 fb-1 2.54
FY2005 80 42.7 0.53 50 fb-1 53.5 fb-1 1.07
FY2006 80 82.4 1.03 100 fb-1 100.3 fb-1 1.00
FY2007 80 81.1 1.01 130 fb-1 90.2 fb-1 0.69
FY2008 80 85.4 1.07 30 fb-1 57.2 fb-1 1.91
29
PEP-II General Accelerator Achievements
  • Introduced beta-beats to help chromatic
    corrections near IR.
  • First collider to continuously inject into a ring
    with the physics detector taking data.
  • Installed 2 km of solenoids on the e LER ring to
    suppress the Electron Cloud Instability ECI.
  • Held the overall luminosity record for several
    years. Now second to KEKB (1.2 vs 1.7 x 1034)
  • Highest stored electron current (2.1 Amps)
  • Highest stored positron current (3.2 Amps)

30
Transition planning
  • PEP-II Run 7 ended April 7, 2008.
  • PEP-II has since been kept under PPS (safety)
    control.
  • Only a very few parts have been removed for other
    programs.
  • Power usage has been minimized.
  • Venting, coil drying, and component removal will
    proceed as approval, funding, and manpower is
    available.
  • Staff
  • Operators have all moved to LCLS operation.
  • Engineering staff moved to PEP-II minimum
    maintenance state, LCLS upgrades and maintenance,
    FACET, and PEP-X.
  • Physicists have moved to LCLS operations, PEP-II
    minimum maintenance state, FACET, PEP-X, and
    Super-B.
  • Operational PEP-II staff level (before April 7)
    250 FTEs
  • Present PEP-II staff level (after April 7) 5
    FTEs.
  • Power
  • Operational power 42 MW
  • MMS power 1.8 MW

31
Budgets for PEP-II MMS and DND planning
32
Future Potential Users of PEP-II Components
  • LCLS a few small parts corrector power
    supplies, gate valves, vacuum gauges, wire
    scanners,
  • SPEAR-3 a few small parts Loss monitors, streak
    camera, Bergos position monitor electronics.
  • PEP-X Tunnel, 6 RF stations, support building,
    e- injection line
  • Super-B All magnets, all power supplies, all
    electronics modules, 10 RF stations, all
    supports, all vacuum chambers
  • Project X Magnets with vacuum chambers for
    transport lines
  • LBNL ALS Chopper power supplies for ALS bends
  • J-Lab Electro-magnets for energy upgrade

33
PEP-X (SLAC Today July 3)
34
PEP-II 1998-2008 Thanks to all!