Title: Stripline Kicker Project


1
Stripline Kicker Project
  • LBL
  • LLNLSLAC
  • KEK
  • DESY

2
  • Damping Ring Injection / Extraction Kicker Magnet
  • The TDR Kicker
  • 0.6 mrad (.01Tm), 5GeV, 50 m ß, 7e-4 stability,
    20 each, many meters long (kicker achromat not
    possible)
  • Counter-fed 50 ohm striplines
  • The conventional approach (SLAC)
  • Follow and extend the TDR design
  • FET / Hard tube / Saturable Ferrite
  • Alternatives
  • Coherent sum CW standing wave kickers (system)
    Gollin / KEK
  • Waveguide close to cut-off (system) Gollin /
    FNAL
  • Pulsed traveling wave RF structures (system)
    INFN / Cornell
  • Shorted-striplines (just the magnet) Wille
    (Dortmund) / SPEARIII
  • (Hard tube-based pulsers Frisch)
  • Consider the application of this technology at
    KEK-ATF

3
Counter-fed Stripline (power fed parallel to beam
direction gives no kick unless v_g is low) Rise
time depends on travelling wave kicker fill time
DESY Kicker RD Rummler / Shiltsev / BINP
4
DESY Kicker RD ITRP Poster (Obier)
5
(read µ)
DESY Kicker RD 2 stripline magnets
built Ongoing RD for XFEL switchyard
6
  • ATF Kicker development. (2 programs)
  • Program 1 Conventional pulse technology
    extremely fast kicker
  • Extract 20 bunches spaced by 330 ns to be used
    for testing ILC instrumentation in the ATF
    extraction line
  • Replace existing extraction kicker for test
  • 25mm aperture, 20KV, 1.3m kicker is enough to
    extract (3mrad at 1.3GeV)
  • (500A, 10MW peak)
  • Six 200 mm long stripline pairs - 12 pulsers
    (/)
  • Conventional solid state / planar triode pulser
    with many counter-fed striplines
  • Roughly 2x harder than ILC
  • Uses saturable ferrite shock-line technology
  • Program 2 long pulse kicker for fast extraction
    based on epoxy magnet technology (SLAC DR, ATF
    injection)

7
Plan
  • Reduce required kick power 4x TDR power(?)
  • 4 kickers ?
  • 10 mm diameter ?
  • DESY Behlke pulser basic unit is 10 ? each 20
    or 30 needed.
  • Still expensive
  • Vacuum chamber modifications will be more
    expensive
  • Stripline kicker
  • Needs a design and consensus esp between
    SLAC/KEK/DESY

8
Kickoff meeting LBL 07.12.2004
  • Caspers, Lambertson, Byrd
  • More interesting ideas (based on p_bar
    cooling/ring feedback exp.)
  • Slotted stripline slow speed
  • Tapered stripline wider band
  • Long, ceramic loaded line (?)
  • This group should produce kicker design and cold
    test it

9
Proposed project
  • Goal
  • Proof of 5 ns principle before 06.2005
  • Extraction using 5ns full width 3MHz kicker by
    01.2007
  • KEK/DESY/SLAC/LLNL pulser tests at KEK using
    existing stripline
  • LBL low beam-impedance kicker
  • KEK/SLAC ATF modifications and design