ILCAmericas Program Overview - PowerPoint PPT Presentation

1 / 53
About This Presentation
Title:

ILCAmericas Program Overview

Description:

ILCAmericas Program Overview – PowerPoint PPT presentation

Number of Views:73
Avg rating:3.0/5.0
Slides: 54
Provided by: geral168
Category:

less

Transcript and Presenter's Notes

Title: ILCAmericas Program Overview


1
ILC-Americas Program Overview
  • G. Dugan
  • ILC/GDE and Cornell University

DOE/NSF ILC Program Review Apr. 4-6, 2006
2
Outline
  • Overview of ILC and GDE
  • GDE mission and goals, ILC challenges
  • ILC baseline configuration
  • ILC Reference Design Report (RDR) and cost
    estimate.
  • Organization of the Americas Regional Team
  • MoU process
  • WBS and FY06 budgets WBS 1.x
  • FY06 Program
  • FY06 ILC RD program highlights, including
    university RD program
  • FY06 program concerns
  • Outlook for FY07 and beyond

3
International Linear Collider The Global Design
EffortMission
  • Produce a design for the ILC that includes a
    detailed design concept, performance assessments,
    reliable international costing, an
    industrialization plan, and a siting analysis, as
    well as detector concepts and scope.
  • Coordinate worldwide prioritized proposal driven
    R D efforts (to demonstrate and improve the
    performance, reduce the costs, attain the
    required reliability, etc.)

4
Formation of the Global Design Effort
  • Director Barry Barish Appointed in March 2005
  • Appointed Regional Directors (Gerry Dugan
    (Americas), Fumihiko Takasaki (Asia), Brian
    Foster (Europe))
  • Three regional directors identified GDE members
    (with agreement from BB)
  • Currently 66 members, representing approximately
    25 FTE
  • GDE Central Team consists of
  • core accelerator physics experts
  • 3 Conventional Facilities experts (1 per region)
  • 3 Costing engineers (1 per region)
  • 3 Communicators (1 per region)
  • representatives from World Wide Study

5
GDE RDR / RD Organization
FALC
ICFA
FALC Resource Board
ILCSC
GDE Directorate
GDE
GDE Executive Committee
GDE R D Board
GDE Change Control Board
GDE Design Cost Board
Global RD Program
RDR Design Matrix
ILC Design Effort
ILC RD Program
6
  • International Linear Collider Timeline

2005 2006 2007 2008
2009 2010
Global Design Effort
Project
Baseline configuration
Reference Design
Technical Design
ILC RD Program
Expression of Interest to Host
International Mgmt
7
Parameters for the ILC
  • Ecm adjustable from 200 500 GeV
  • Luminosity ? ?Ldt 500 fb-1 in 4 years
  • Ability to scan between 200 and 500 GeV
  • Energy stability and precision below 0.1
  • Electron polarization of at least 80
  • The machine must be upgradeable to 1 TeV

8
Scope of the 500 GeV machine
  • Main linacs length 21 km, 16,000 RF cavities
    (total)
  • RF power 640 10-MW klystrons and modulators
    (total)
  • Cryoplants 11 plants, cooling power 24 kW (_at_4K)
    each
  • Beam delivery length 5 km, 500 magnets (per
    IR)
  • Damping ring circumference 6.6 km, 400 magnets
    (each)
  • Beam power 22 MW total
  • Site power 200 MW total
  • Site footprint length 47 km (for option to
    future upgrade to 1 TeV)
  • Bunch profile at IP 500 x 6 nm, 300 microns long

9
Accelerator physics and engineering challenges
  • Developing efficient high gradient
    superconducting RF systems
  • Requires efficient RF systems, capable of
    accelerating high power beams (MW).
  • Achieving nm scale high-power beam spots
  • Requires generating high intensity beams of
    electrons and positrons
  • Damping the beams to ultra-low emittance in
    damping rings
  • Transporting the beams to the collision point
    without significant emittance growth or
    uncontrolled beam jitter
  • Cleanly dumping the used beams.

10
Affordability challenges
Civil
Pie chart From US Tech. Options Study
SCRF Linac
11
ILC Baseline configuration Document (BCD)
  • A baseline configuration for the ILC machine,
    with a conceptual layout, and beam parameters,
    was defined at end of 2005.
  • The baseline made forward looking choices,
    consistent with attaining performance goals. The
    choices were understood well enough to do a
    conceptual design and reliable costing by end of
    2006.
  • Alternate configurations were established,
    which may have cost and or performance benefits,
    but which need further RD for validation.
  • - The baseline is under configuration
    control,with a defined process for changes to
    the baseline.

12
ILC Baseline Configuration
  • Configuration for 500 GeV machine with
    expandability to 1 TeV
  • Some details (locations of low energy
    acceleration, crossing angles) are not indicated
    in this cartoon.
  • Tor Raubenheimer will present more details on the
    BCD

13
ILC Reference Design Report (RDR) and Cost
Estimate
  • Based on the Baseline Configuration, a reference
    design and cost estimate will be carried out in
    2006. Technical performance and physics
    performance will be evaluated for the reference
    design report.
  • This process began after the Frascati GDE
    meeting and will conclude late in 2006.
  • This is a global effort, with participants from
    all three regions.
  • Tor Raubenheimer will describe the RDR process
    in more detail.

14
From Baseline to a RDR
2006
July
Dec
Jan
Bangalore
Frascati
Vancouver
Valencia
Freeze Configuration Organize for RDR
Review Design/Cost Methodology
Review Initial Design / Cost
Review Final Design / Cost RDR Document
Design and Costing
Preliminary RDR Released
15
ILC Value estimate
  • The ILC will be built as an international joint
    project, in which the three regions will
    contribute mainly in kind (specific components)
  • Cost estimates must be done in the context of the
    in-kind contribution model. We will need to
    secure regional component cost estimates and
    evaluate these in terms of a globally defined
    value unit. (ILC unit)
  • The complete value estimate will be translatable
    into a given regions currency and cost
    estimating methodology.
  • Peter Garbincius will describe the plans and
    methodology for the value estimate in more detail.

16
ILC Program Execution
In the Americas region, the ILC program (the RDR
effort, and supporting ILC RD), is executed by
the Americas Regional Team.
ILC-Americas Regional Team Leaders
ANL-Kwang-Je Kim
BNL-Mike Harrison
Fermilab-Bob Kephart, Shekar Mishra, Sergei
Nagaitsev
Cornell LEPP- Hasan Padamsee, Mark Palmer
Jefferson Lab -Swapan Chattopadahay, Warren Funk
LBNL -Mike Zisman, Christine Celata
LLNL -Jeff Gronberg
SLAC -Tor Raubenheimer, Nan Phinney, Tom Himel
TRIUMF -Shane Koscielniak
Universities- Project Leaders
17
Organization of the ILC-Americas Program
  • The work is broken down into a series of
    technically-based work packages.
  • GDE and each DoE lab sign MoUs detailing the
    co-operative arrangement for the execution of
    work packages at each lab.
  • Yearly scope of work is spelled out in Addenda to
    the MoU, which detail the work packages.
  • For university RD work, each university project
    is a work package.
  • Labs report financial status at the work package
    level quarterly, and technical status
    semi-annually. (Actuals not yet available for
    FY06 for all work packages. Some actuals will be
    covered in presentations)
  • About 100 work packages for FY06 are organized
    into a WBS.
  • The list of work packages, and associated
    resources, as well as the MOU Addenda, are posted
    on the ILC-Americas web site
  • https//wiki.lepp.cornell.edu/ilc/bin/view/Public
    /Americas/WebHome

18
FY06 ILC-Americas Budget Breakdown by WBS
element
19
FY06 ILC-Americas Budget Breakdown by machine
Area
20
FY06 lab budgets
FY06 ILC-Americas Budget Breakdown by Laboratory
Most labs are also putting additional funds into
ILC RD. For example, Fermilab is devoting an
additional 12 M to developing SCRF
infrastructure.
21
ILC-Americas University FY05 RD Program
  • SCRF materials and surface preparation Wisconsin
    (64K), Northwestern(40K), Old Dominion (58K)
  • RF power sources Yale (60K), MIT(30K)
  • Polarized electron source Wisconsin (35K)
  • Polarized positron source Tennessee (40K),
    Princeton
  • Damping rings Illinois (17K), Cornell (75K,
    46K) NSF
  • Instrumentation, diagnostics Berkeley (35K),
    Cornell (24K) NSF
  • Mover systems Colorado State (49K) NSF
  • Radiation hard electronics UC Davis (38K), Ohio
    State (75K)
  • Ground motion Northwestern (28K)
  • Linac beam dynamics design-Cornell (21K)
  • High-gradient SCRF RD- Cornell (140K) DOE

22
WBS 1.xProgram direction and administration
23
ILC RD and RDR efforts for FY06
During this review, the names in bold will
discuss in detail the indicated WBS areas
  • WBS x.2. Global Systems (Larsen, Himel, Ross)
  • WBS x.3, x.4 Sources (Sheppard)
  • WBS x.5 Damping rings (Kim)
  • WBS x.6 Ring to Main Linac (Tenenbaum)
  • WBS x.7, x.8, x.9 Main Linacs (Mishra, Solyak,
    Adolphsen, Kephart)
  • WBS x. 10 Beam delivery systems (Seryi)
  • WBS x.11 Site development (Kuchler)

I will give an abbreviated overview of the FY06
program by WBS category in the next few slides.
24
WBS x.2 Global Systems
  • System availability studies (SLAC)
  • Design of high availability hardware (SLAC, LLNL)
  • Kickers, Power supplies, diagnostics, and control
    system
  • General control system design (ANL, Fermilab,
    SLAC)

Fast (redundant) kicker for DR
25
WBS x.3, x.4 Sources
  • Laser and cathode for polarized electron source
    (SLAC)
  • NC structures design and test (SLAC)
  • Undulator design, E166 (SLAC, Cornell)
  • Positron Source simulations (ANL)
  • A comprehensive start-to-end simulation of
    conventional, polarized, and keep-alive sources.
  • Positron target design (LLNL)
  • Detailed engineering
  • Target simulations
  • Energy deposition
  • radiation damage, activation

Positron capturestructures
26
WBS x.5 Damping rings
  • Damping ring component optimization wigglers,
    fast kickers
  • s of the use of CESR as an ILC positron damping
    ring test facility (in 2008) (Cornell)
  • Damping Ring Design and Optimization (ANL)
  • Lattice design and optimization particle
    tracking for single-bunch instabilities with 3-D
    wakefield studies of ion instability in the APS
    ring design of a hybrid wiggler satisfying the
    field quality tolerance
  • SEY studies in PEP-II (SLAC)
  • ATF damping ring experiments (SLAC, LBNL,
    Cornell)
  • Lattice designs for damping rings and
    injection/extraction lines characterization of
    some collective effects, including space-charge,
    IBS and microwave instability physics design of
    stripline kickers for single-bunch extraction at
    KEK-ATF (LBNL)

27
WBS x.6, x.7 RTML and Main Linac Optics, beam
dynamics, instrumentation
  • RTML design (SLAC, Cornell)
  • Main linac optics design (SLAC, Fermilab)
  • Low emittance transport simulations and BBA
    design (SLAC, Fermilab, Cornell)
  • Wakefield calculations (SLAC)
  • Linac beamline Instrumentation (SLAC)

TTF HOM Signal800 monitors installed
RF BPM for linac
28
SLAC End Station B (RF Test Fac.)
WBS x.8 Main Linac RF sources
  • Linac rf sources (SLAC, LLNL)
  • Marx generator modulator
  • Develop 5 MW station in FY06, and 10 MW station
    later
  • Test rf system components
  • Reuses extensive infrastructure

29
WBS x.8 Main Linac RF sources
  • Coupler Test Stand (LLNL)
  • Evaluation and analysis of RF coupler designs
  • Linac SC quad and BPM (SLAC)
  • Studies of magnetic center stability with
    excitation

SC Quad for magnetic center tests
30
ILC Cavities and test facilities
WBS x.8 Cavities and Cryomodules
Bead pull RF Testing _at_ FNAL
Joint ANL/FNAL BCP/EP Facility
  • Industrial fabrication of cavities (12 cavities
    in FY06) (FNAL)
  • BCP and vertical testing (FNAL, Cornell)
  • EP process development and vertical testing
    (FNAL, Jlab).
  • Joint BCP/EP facility being developed at ANL
    (late 06)
  • Horizontal test facility _at_ FNAL (ILCTA-MDB)
    (complete Fall 06)
  • Vertical test facility under development _at_ FNAL
    (ILCTA-IB1) (complete 07)
  • Single/large grain Crystal cavity development
    (FNAL,Jlab).

31
Cryomodule assembly and test infrastructure at
Fermilab
WBS x.8 Cavities and Cryomodules
PPD Machine shop (MAB)
Meson Detector Building (MDB)
ILCTA-MDB Cryogenics Installation 60 W _at_ 1.8 K
TD MP9 Cryomodule Assembly Facility (CAF)
First 1.3 GHz TESLA Cavity in MDB Cold and RF
power in Dec
AD Cryo Dept.
32
Cryomodule Design
WBS x.8 Cavities and Cryomodules
  • Industrial fabrication and cost reduction of the
    ILC cryomodule are both crucial issues for a
    realistic ILC cost estimate
  • In FY05 Fermilab started on converting drawings
    of the DESY/INFN design of the ILC cryomodule
    (Type-III) to US standards for U.S. vendor
    fabrication and for cost reduction.
  • IN FY06, as part of a co-ordinated global effort,
    design has started for an improved ILC cryomodule
    (Type-IV).

33
Cryomodule string test ILCTA-NML at Fermilab
WBS x.8 Cavities and Cryomodules
New Muon Lab (NML)
FNPL Photo-Injector
  • Building a dedicated ILC cryomodule string test
    facility in the New Muon Lab
  • Building is cleaned out except for removal of CCM
    ( in progress)
  • Started to install cryogenic system-complete in
    FY07
  • Move FNPL Photo-injector to provide electron beam
    (FY07)
  • Upgraded FNPL will provide beam tests of ILC
    cryomodules (FY08 and 09)

34
Fabricate, process and test cavities from
large-grain/single-crystal material (JLab)
WBS x.8 Cavities and Cryomodules
  • Objectives
  • Several single cell and at least one multi-cell
    cavity made from large grain/single crystal
    niobium
  • Improved BCP system for producing very smooth rf
    surfaces on large grain/single crystal material
  • Test cavity for superconducting rf joint
    investigations
  • Optimization studies of superstructure
    configuration based on superconducting joint
  • Two cavities suitable to be combined into a
    superstructure
  • Engineering package for the completion of a
    superstructure assembly ready for cold tests

35
Re-entrant Cavity Shape47 MV/m at CornellLater
52 MV/m at KEK9-cell re-entrant cavity ordered
from AES
WBS x.8 Cavities and Cryomodules
Cornell LEPP ILC SCRF activities
36
WBS x.10 Beam Delivery System
  • Beam delivery system design (SLAC)
  • ATF-2 (SLAC)
  • Construction of magnets, PS, and instrumentation
  • ESA MDI Test Facility (SLAC)

ATF2 Optics
ESA Energy Spectrometer
- NanoBPM for ATF2 (LLNL)
37
ILC Final Focus Magnet Development (BNL)
WBS x.10 Beam Delivery System
  • FY06 goals
  • Continue to support the baseline design efforts
  • Support the development of the Conceptual
    Design/Cost Estimate for the Beam Delivery System
  • Fabricate and test a short proof of principle
    shielded final-focus-like quadrupole coil
  • Fabricate and test a short proof of principle
    sextupole/octupole corrector-like coil

Winding tests, octupole coil - how small can you
go ?
Shielded quadrupole proof of principle coil
fabrication
38
ILC Civil Design for the RDR
WBS x.11 Conventional Facilities
  • Design to sample sites from each region
  • Americas near Fermilab
  • Japan
  • Europe CERN DESY
  • Americas Site - in Illinois location may vary
    from the Fermilab site west to near DeKalb
  • Design efforts ongoing at Fermilab and SLAC

39
Potential TRIUMF Accelerator RD Resources for ILC
TRIUMF
The specific nature of Canadian involvement is
under development. Some potential collaboration
areas have been identified, along with relevant
LHC experience
  • The design of kicker magnets and the construction
    of associated pulse-forming networks and fast
    switches using power semiconductors
  • Precision room temperature magnet systems
  • e.g. 52 twin-aperture quadrupoles built at Alstom
    Canada
  • Beam instrumentation and readout systems
  • e.g. 2000 matched-pair 70MHz low pass filters
  • e.g. VME64x compliant Digital Aquisition Board
    (DAB)
  • Contributions to beam dynamics lattice
    calculations for damping rings.

40
TRIUMF
  • Building on expertise developed for TRIUMF ISAC
    radioactive beams accelerator, additional
    possible areas are
  • Remote handling design/consulting of target
    stations possible applicability to conventional
    positron source
  • Peripheral aspects of superconducting r.f., such
    as cryogenic coolant distribution system,
    design/consulting, small quantity e-beam welding
    of niobium

UBC -Tom Mattison Vibration control systems and
alignment of components for final focus system
also interest in abort kickers
41
FY06 program concerns
  • Do we have sufficient resources available to
    complete the RDR and cost estimate? Some funds
    have been held in reserve to pay for additional
    help, but also we will need to divert some effort
    from RD program.
  • Key RD concerns
  • Development of reliable high-yield processes for
    the production of high-gradient ILC cavities
    remains a critical item. Cavity fabrication and
    studies of processing are high priority parts of
    the program.
  • Thales klystron problems emphasize need to put
    more effort into klystron development. Difficult
    to do this before FY07.
  • Additional efforts are needed to co-ordinate
    Americas RD program and to plan for the future,
    both within the region, and with programs in
    other regions.

42
FY07 outlook
  • PB doubles ILC program budget to 60M (This
    includes ILC detector RD at labs and
    universities)
  • However, the requested (technically limited)
    program exceeds the available funding. A process
    of prioritization will be required.
  • This process should look to GDE for guidance on
    priorities. Advice will be sought from GDE RD
    Board for general ILC RD efforts, and from
    Linear Collider Steering Group for the Americas
    (LCSGA) for region-specific Americas bid-to-host
    related activities.
  • First steps document FY07 lab program requests
    (April 26) Regional team meeting to discuss FY07
    requests and future plans (May 3-4, SLAC)

43
FY07 program lab requests
44
FY07 ILC program request details
  • TDR engineering efforts (50 FTE)
  • Cavity and cryomodule work
  • RF system development
  • Sources, Damping rings, beam delivery
  • Global systems
  • Americas region bid to host

45
Cavities, cryomodules and test infrastructure
FY07 Lab requests
  • Fabricate (in industry) and process (at labs) 12
    more ILC high-gradient cavities.
  • Continue RD on large-grain and high-gradient
    cavities.
  • Continue RD on EP processing, field
    emission/dark current issues, thin film systems.
  • Develop EP facility at ANL.
  • Horizontally test 10 cavities at Fermilab.
  • Build first US-built cryomodule and receive parts
    for 2nd cryomodule (to be built in FY08).
  • Complete design of Type IV (ILC-style)
    cryomodule.
  • Complete vertical test facility, and second
    horizontal test facility, at Fermilab (IB1).
  • Install cryogenic systems support for cryomodule
    tests in Fermilabs ILCTA-NML.
  • Upgrade and move Fermilab photoinjector to
    ILCTA-NML.
  • Purchase 10 MW klystron and another bouncer
    modulator for ILCTA-NML at Fermilab

46
Linac RF systems
FY07 Lab requests
  • Continue development of Marx modulator, and
    evaluation of DTI and SNS modulators downselect
    modulator choice by end of FY07.
  • Purchase two 10 MW klystrons from CPI and
    Toshiba. Contract with CPI to develop a
    high-efficiency 5 MW klystron. Fabricate two
    sheet-beam klystron prototypes, following SLAC
    design (split funding in FY07 and FY08). Goal is
    klystron choice by end of FY08.
  • Investigate cost reduction options for RF
    distribution system and couplers.
  • Continue development of LLRF systems

47
FY07 Lab requests
Sources
  • Electron source develop improved photocathodes,
    more robust materials, laser system for polarized
    gun (using SLAC infrastructure), and investigate
    polarized RF guns.
  • Positron source
  • Optics and system design study image current
    heating of target in AMD field
  • Begin detailed design of undulators
  • Continue positron source simulations construct
    prototype AMD
  • Both Design and build 4.3 m NC traveling wave
    structure

48
Damping rings
FY07 Lab requests
  • Continue detailed development of ring design and
    simulations for the TDR
  • Pursue experimental and theoretical studies of
    electron cloud effects
  • Begin detailed calculations of other collective
    effects in the rings
  • Begin detailed engineering design of vacuum
    systems, feedback systems
  • Continue and refine designs of fast damping ring
    kickers and pulser systems
  • Conduct damping ring studies at ATF and ALS
  • Develop detailed plans for CESR conversion to a
    damping ring test facility

49
FY07 Lab requests
Optics and beam dynamics for RTML and Main Linac
  • Continue and expand tuning and BBA studies of
    LET.
  • Continue SC quad magnetic stability and
    alignment/vibration studies.
  • Continue wakefield calculations for candidate
    structures.

Beam Delivery System
  • Continue detailed development of optics design,
    collimators, etc.
  • Continue magnet fabrication for ATF2.
  • Continue experimental program at ESA.
  • Begin 3 year program to prototype and test QD0
    (IR FF quad) at BNL.
  • Begin engineering design of the FF region
  • Continue experimental vibration studies for FF
    quads.

50
Global systems
FY07 Lab requests
  • Continue development of high availability
    programs in power supplies, damping ring kicker
    systems, diagnostic processors.
  • Begin installation planning for TDR. Investigate
    new alignment techniques based on X-rays.
  • Controls and instrumentation continue
    development of ATCA hardware platform. Plan
    timing/rf phase demonstration.
  • Diagnostics develop laser system for laser
    wires, time resolved photon diagnostics continue
    development of linac BPM system.

51
Civil design
Americas Bid to Host
Preparing for the Americas Region Bid to Host
  • Begin design studies to fully develop an
    expression of interest for an American site for
    the ILC

Industrialization
  • Initiate procurements for the fabrication of the
    first of three complete RF units (cavities,
    cryomodules, RF system components) by industrial
    firms in the Americas. Cavity processing and
    cryomodule assembly would use existing lab
    infrastructure.

52
Conclusions
  • The ILC Global Design Effort has co-ordinated the
    development of the ILC Baseline Configuration, is
    directing the production of a Reference Design
    Report and cost estimate this year, and is
    providing guidance on the overall ILC RD
    program.
  • In the Americas region, the Americas Regional
    Team is playing a major role in the development
    of the ILC RDR and cost estimate.
  • A vigorous RD program, in support of the GDE
    goals, is underway in FY06 at national labs and
    universities throughout the Americas region. You
    will hear the details of this program in
    subsequent talks at this review.

53
Conclusions
  • Next year, as the project enters the TDR phase, a
    significant increase in resources will allow
    development of the TDR, expansion of the RD
    program, and the start of efforts to develop the
    Americas region bid to host the ILC.
  • The requested resources for an FY07 technically
    limited program exceed those expected to be
    available.
  • Challenges remain in completion of the RDR and
    cost estimate this year, in cavity processing and
    klystron RD, and in effective co-ordination of
    the regional RD programs.
Write a Comment
User Comments (0)
About PowerShow.com