Title: Overview
1Overview
BNL SNS Diagnostics Status/Handoff Meeting
February 5-6, 2004
2Outline
- Comments on the Agenda
- Summary and Conclusions
- Response to March 2003 FDR
- ASAC and DOE Review updates
- Important Dates
- General Status, Budget, Schedule
- System-by-System Status, Budget, Schedule
- More about Handoff
- Summary and Conclusions
3Agenda
4Summary and Conclusions
- FY03 commitments - all major purchases have been
placed, except - End Game Plan - funding for IPM magnets,
Beam-in-Gap kicker pulsers, and Incoherent Tune
kicker amplifiers moved from FY03 to FY05. - Unofficial End game possible delay of IPM
digitizer purchase (180K), delay of part of
rackmount PC purchase (70K). - During FDR, we listed among our concerns that a
possible sleeper was the noise environment.
Sleeper is now awake in the BCM system. - Beamline hardware/vacuum envelope
- HEBT complete and delivered (except Linac and
Injection Dump WS for LANL) - All Ring and RTBT hardware in detailing/checking/f
abrication. - DAQ/Electronics - Critical systems (as defined by
Diagnostics Review Committee and ORNL
AP/Diagnostics) are BLM (VME-based), BCM
(PC-based), and BPM (PC-based) - BLM installed and commissioned for DTL
- BCM delivered, mysterious front end failures
- BPM first article electronics (Baseband and RF)
are in-house at BNL - BNL version of PCI Interface/timing decoder is
in-house and at ORNL - We anticipate no difficulties in meeting schedule
for critical systems. - Budget trend in the most mature systems (BLM,
BCM) is disturbing - Major concerns are handoff (DOE Review action
item), BCM failures, spares
5 General Response to the Mar 03 FDR Report
- All general recommendations were directed at
handoff - The work effort has followed recommended
priorities - BLM, BCM, BPM, VFM, IPM, e-detect, Tune/BIG/Halo
- The recommended 3 FTE increase in staffing in
ORNL Diagnostics has not happened (and will not?)
- Recommended MOA to extend BNL expertise into
commissioning has not been implemented - Perception at BNL is that there has been no real
progress on handoff beyond prioritization
6Outline
- Comments on the Agenda
- Summary and Conclusions
- Response to March 2003 FDR
- ASAC and DOE Review updates
- Important Dates
- General Status, Budget, Schedule
- System-by-System Status, Budget, Schedule
- More about Handoff
- Summary and Conclusions
7ASAC and DOE Review Updates
- ASAC March 03
- Potential significant shortfalls include
installing and commissioning diagnostics. SNS
management should increase staff when needed to
avoid schedule slippage or loss of morale. - Include resonant quadrupole pickup
- DOE May 03
- Positive laser wire results - promote BIG and
bunch shape monitor - Present handoff/commissioning plan at next DOE
Review - Reduced set of Diagnostics for initial
commissioning - End Game plan - funding for IPM magnets, BIG
pulser, and incoherent tune kicker amplifiers
moved to FY05 (or beyond?) - ASAC September 03 - no presentation, request for
presentation on Ring Diagnostics at the next ASAC - DOE November 03
- Consider ways to supplement staff of SNS
Diagnostics group - Focus on BLM, BCM, BPM, VFM (no mention of wires)
8DOE Review(s) Action Item(s) - Handoff
- Action Item from Nov 02 and May 03 DOE Reviews
- Funding (2M) for installation support and
documentation was transferred from BNL
Diagnostics budget to ORNL 2 years ago - This money was used at ORNL to fund staffing of
the Diagnostics Group - Agreement at that time was
- ORNL will be responsible for documentation, will
provide system specialists one manweek/month at
BNL starting ASAP. - Assembly and Test will be accomplished at BNL
(except BLM) - ORNL responsible for Installation, System
Integration, Documentation, Commissioning
(requires early ID of BNL support requirements) - Acceptance criteria The delivered components
must meet the requirements of the final design
review. - BUT The resources needed to fulfill the
responsibilities of this agreement have not been
(and, according to the Project Office, will not
be) made available to the ORNL Diagnostics Group
9Handoff from BNL Perspective
- Deliver the Critical Systems (as defined by
Diagnostics Review Committee and ORNL
AP/Diagnostics) BCM, BLM, BPM, VFM - Support Installation and Commissioning of
Critical Systems - This is not presently funded in the BNL
Diagnostics budget - Direction from ORNL Diagnostics is to reduce
scope of non-critical systems to fund handoff - Reduction of Scope - first obvious choice is
End-Game hardware (Beam-in-Gap kicker pulsers,
Incoherent Tune kicker amplifiers,) - Request from ORNL is to have additional BNL
manpower available at ORNL in FY05 and FY06, but - BNL funding profile ends in FY05
- Non-permanent relocation to ORNL represents
personal and professional hardship to affected
members of BNL Diagnostics team - No clear solution in hand
10Outline
- Comments on the Agenda
- Summary and Conclusions
- Response to March 2003 FDR
- ASAC and DOE Review updates
- Important Dates
- General Status, Budget, Schedule
- System-by-System Status, Budget, Schedule
- More about Handoff
- Summary and Conclusions
11Important Dates
- Jul 03 - HEBT beamline hardware delivery
completed - Jul 03 - DTL tank 1 commissioning - BCM and BLM
- Apr 04 - DTL tank 3 commissioning BCM, BLM (RF
BPM) - Jul 04 - Ring and RTBT beamline hardware
complete - Mar to May 05
- beam to linac dump
- BCM, BLM (RF BPM)
- Jul to Nov 05
- beam to RTBT dump
- BCM, BLM, BPM,
- VFM, coherent tune
- Feb 06 - beam to target
12Beamline Hardware Progress
13Electronics Progress
14Budget
15Outline
- Comments on the Agenda
- Summary and Conclusions
- Response to March 2003 FDR
- ASAC and DOE Review updates
- Important Dates
- General Status, Budget, Schedule
- System-by-System Status, Budget, Schedule
- More about Handoff
- Summary and Conclusions
16BLM Status Richard Witkover
- Budget - 294K burdened
- Beyond baseline
- new ion chamber - development, higher bottle
cost - additional ion chambers in Ring, linac
- neutron detectors - HVPS and electronics
- MPS interface
- Successful commissioning for DTL tank one
- handoff - SNS Controls EPICS configuration
crashed (all) VME crates, BLM not brought back up - handoff - perception at ORNL that BLM didnt work
17LabVIEW Template Chris Degen
- creation of Wim Blokland
- major tool for easing handoff
- original plan was to have each system specialist
master the template - practical reality is that Chris Degen will be
the template specialist, will guide cognizant
engineers - all systems except BLM (which is in VME) use the
template
18PCI Interface/Timing Decoder Joe Mead
- Original plan was to use LANL interface
- Issues with delivery and support (LANL is off
the project next month) drove the decision to
develop in-house design - Improvements to the LANL design
- replaced fifos with SRAM - 50K savings
- replaced one-time with programmable gate array
flexibility - added timing decoder to gate array - 100K
savings plus a slot - single board for baseband BPM (LANL design has 4
boards) - Version 2 is under test focus on timing
decoder - This board will probably become project-wide
decoder
19BCM Status
- Budget - 312K burdened
- Beyond baseline
- ring toroid vendor error 120K
- differential current measurement 72K
- timing generator for MEBT commissioning 30K
- in-house PCI/timing decoder development
- mysterious electronics failures - commissioning
support 24K handoff - Mysterious electronics failures - Tennessee
mountain air? (best theory) - No failures at Berkeley/BNL in 2 years of
continuous operation - First ORNL failure - input resistor, one time
only - Succeeding failures - TI and AD amplifiers,
proven performers - handoff 3 and 10 week shelf times for tank 1,
then panic - Wim and his template saved the day (FBCM -
Saeeds suggestion) - Internal Review at BNL in early January - no
random changes - ready for full production (board stuffing) since
June - The Plan - continue testing thru tank 3, then
decision
20Fast DAQ Systems
- fast Acqiris digitizer in PC
- DP 235 - 1GS/s, 500MHz BW, 8 bits
- Slightly expensive 9K for 2ch board in qty 20
- Fast BCM
- 100 MHz analog output from all BCM IFEs
- Original purpose - characterization of bunch
edges, abort gap - Requires timing decoder card, no calibration,
only 8 bits, no gate array for pre-processing,
too much data(?), - Fast BLM (and BIG/Halo)
- PMTs in 18 locations, testing in Linac
- Electron Detectors
- Modified ANL style detectors at five locations in
SNS Ring - Laser Wire - the saving grace for BCM
21 BCM Fallback Kudos to ORNL/Wim
22Beam Current Monitor
23BPM Status
- Budget - 14K burdened
- Beyond baseline
- detail drawings and 2 PUEs for CCL
- 17 PUEs for HEBT
- in-house, then Bergoz (delivery problems due to
RF), now in-house - RF section for all Ring and RTBT
- in-house PCI/timing decoder development
- beam-based alignment
- Work has been seriously impeded by BCM failures
- manpower diverted
- hesitancy to proceed until BCM problem is
understood
24Ring and RTBT BPM Electronics
- Calibration - via S21 thru the PUE, also
Beam-based offset determination - IFE Electronics in Third Iteration
- Dual AFE (baseband shown below 400MHz RF) for
first turn capability, incoherent tune
measurement, easier calibration, - Dynamic range dual AFE, protected amp, gain
switching - PCI Interface evolved from LANL design - proven
with MEBT, DTL BCMs - Digital section is very similar to BCM - again
proven at MEBT - Does not share critical analog components with
BCM AFE
25RF BPM Electronics
26Video Foil Monitor Status
- Budget - 90K burdened
- Two locations primary and secondary stripping
foils - Beyond baseline
- detailed design for electron catcher
camera/cubby - fluorescent screen for low intensity operation,
position and profile measurements - Camera and DAQ for electron catcher not in
baseline
27IPM Status
- Budget - 272K burdened
- Beyond baseline
- cold electron calibration source
- increased aperture to improve S/N
- luminescence monitor studies when space charge
was still an issue ports included in IPM vacuum
chamber - electron detectors and their DAQ
- Magnets moved to FY05 official end game
- Digitizers moved to FY05 unofficial end game,
two boards (of 16) to be purchased so that
development work can continue
28IPM - Permanent Magnet Vacuum Chamber
29WS Status
- Budget - 91K burdened
- Beyond baseline
- six MEBT carbon wire scanners
- laser wire development effort at BNL
- two MEBT laser wires
- linac, injection, and rtbt dump vacuum chambers
- all chambers enlarged at request of LANL/ORNL to
keep forks out of beampipe aperture - ports for laser wire and vacuum chambers for
magnets/electron detectors provided all HEBT - Remaining BNL responsibility is vacuum chambers
only, proceeding on schedule
30Incoherent Tune Status
- Budget - 14K burdened
- Beyond baseline
- resonant dipole pickup, kicker, and amplifiers
- resonant quadrupole pickup, kicker, and
amplifiers - motion control for pickups
- damper kickers at request of ORNL AP group
- Original concept was to measure tune of injected
bunch in the space charge field of the
accumulated bunch separate WBS for incoherent
tune did not exist - Resonant quadrupole pickup used in RHIC 2003
(first application of this concept), spectral
signature of envelope oscillation seen. For RHIC
2004 pickup modified to 20 degree striplines,
resonant network just connected, looking at
spectra asap. - Caution from Prof. Hoffman (Halo 2003) on
interpretation of Schottky spectra in
space-charge dominated beams
31Coherent Tune/BIG/Halo Status
- Budget - 149K burdened
- Beyond baseline
- BIG Kicker
- BIG Pulser
- Ring Scrapers and motion control
- Original design was a current transformer, WBS
was BIG only - Prototype transformers were built, combination
of dynamic range and bandwidth was insurmountable - Discussion of need for gap cleaning arose in BNL
AP group, decision was made to build gap cleaner
and look at losses at collimators - Concerns about ability to see signal at
collimators, coupled with understanding of
space-charge driven envelope resonance at PSR,
led to inclusion of scrapers for halo monitoring - Emission current monitoring added to scrapers at
ORNL request - Coherent tune was moved to this WBS
32Spares Plan - BLM only
- Reasonable spares cost 400K, PCR turned down
by Project Office - Second iteration 200K, again turned down by
Project Office - Not possible to do spares for less than this our
concern is that if we agree to a partial spares
PCR, we open ourselves to failure and criticism - Solution spares for most critical system only
- PCR submitted to Project Office for 100K for
BLM system not yet approved - Remaining concerns
- this approach is not cost effective the time to
build spares is when youre in production for the
system - given manpower/money situation, spares unlikely
before beam
33More on Handoff
- Basic Plan is sound - prioritize BLM, BCM, BPM,
VFM (and wires) - BLM and BCM (and wires) will be brought to full
operational readiness of necessity during linac
commissioning - BPM will be parasitically brought to readiness
during the same time - Hardware and software similarities between BCM
and BPM - VFM will require additional attention (system
specialist shared with BLM, HEBT and Ring
Scrapers, Stripper Foil) - Concern remains regarding ONRL manpower, whether
they can give needed attention to systems to
complete handoff - We have been delivering BCMs for over two years,
but Craig Dawsons presence is still essential to
turn on the system - EPICS configuration problem killed the BLM during
tank 1 commissioning, with no BNL presence it was
not brought back up. - There is no money in the BNL budget to support
presence at ORNL - The plan is sound, but manpower and money to make
it work are not yet available. It requires
additional manpower at ORNL, and additional
travel money at BNL
34Summary and Conclusions
- FY03 commitments - all major purchases have been
placed, except - End Game Plan - funding for IPM magnets,
Beam-in-Gap kicker pulsers, and Incoherent Tune
kicker amplifiers moved from FY03 to FY05. - Unofficial End game possible delay of IPM
digitizer purchase (180K), delay of part of
rackmount PC purchase (70K). - During FDR, we listed among our concerns that a
possible sleeper was the noise environment.
Sleeper is now awake in the BCM system. - Beamline hardware/vacuum envelope
- HEBT complete and delivered (except Linac and
Injection Dump WS for LANL) - All Ring and RTBT hardware in detailing/checking/f
abrication. - DAQ/Electronics - Critical systems (as defined by
Diagnostics Review Committee and ORNL
AP/Diagnostics) are BLM (VME-based), BCM
(PC-based), and BPM (PC-based) - BLM installed and commissioned for DTL
- BCM delivered, mysterious front end failures
- BPM first article electronics (Baseband and RF)
are in-house at BNL - BNL version of PCI Interface/timing decoder is
in-house and at ORNL - We anticipate no difficulties in meeting schedule
for critical systems. - Budget trend in the most mature systems (BLM,
BCM) is disturbing - Major concerns are handoff (DOE Review action
item), BCM failures, spares
35Backup Material
- Following slides are backup material
36BNL Diagnostics Requirements Table
37HEBT Beam Instrumentation
38SNS Ring Instrumentation
39RTBT Beam Instrumentation