Title: Maintenance and Resurfacing Funding


1
North Carolina Department of Transportation
Report to the Joint Legislative Transportation
Oversight Committee
January 14, 2003
Steve Varnedoe
2
Condition Assessment Funding Needs For North
Carolinas Highway System
  • Reporting Requirements
  • Overview of the System
  • Assessment Methodologies
  • Current Conditions
  • Funding Needs
  • Maintenance Operational Improvements

3
Biennial Report on Maintenance Requirements.
G.S. 136-44.3
  • The annual cost of routine maintenance
  • The cost of eliminating maintenance backlog
  • Annual resurfacing cost based on a 12-year cycle
    for primary roads and a 15-year cycle for other
    systems
  • The cost of eliminating any resurfacing backlog

4
North Carolina State Highway System
  • Since the Highway Trust Fund was enacted
  • 1989
  • 76,808 road miles
  • 127,809 paved lane miles
  • 16,104 miles of unpaved roads
  • 16,900 structures
  • 61.1 M sf bridge deck area
  • 2003
  • 78,347 road miles
  • 155,960 paved lane miles
  • 6,644 miles of unpaved roads
  • 17,463 structures
  • 72.3 M sf bridge deck area

5
Highway System Growth(Paved Lane Miles)
System Growth
6
Bridge System Growth(Square Feet of Bridge Deck)
Deck Area Growth
7
Highway System Usage(Vehicle Miles Traveled)
Growth
8
Rating the Condition of the Highway System
  • Maintenance Condition Survey
  • Bridge Condition Survey
  • Pavement Condition Survey

9
Maintenance Condition Elements
  • Roadside
  • Mowing
  • Brush and Tree Control
  • Litter Debris
  • Slope
  • Guardrail
  • Environmental
  • Turf Condition
  • Miscellaneous Vegetation
    Management
  • Bridge
  • Decks
  • Rails
  • Expansion Joints
  • Superstructure
  • Substructure
  • Pavement
  • Flexible
  • Rigid
  • Traffic Control Devices
  • Traffic Signs
  • Pavement Striping
  • Words and Symbols
  • Pavement Markers
  • Drainage
  • Crossline Pipe
  • Driveway Pipe
  • Curb Gutter
  • Catch Basin Drop Inlets
  • Other Drainage Features
  • Roadway
  • Low Shoulder
  • High Shoulder
  • Lateral Ditches
  • Lateral Ditch Erosion

10
(No Transcript)
11
Roadway Performance Measures(Interstate)
  • Element
  • Pavement
  • Shoulders/Ditches
  • Roadside
  • Drainage
  • Traffic Control Devices
  • Environmental
  • Total

Target 93 88 88 88 88 88 90
Actual 86 74 70 73 68 47 76
Scale 1-100
12
RoadwayLevel of Service(2002 Survey)
Interstate
Primary
Urban
Secondary
13
Performance Measure Trends(Roadway)
14
Bridge Performance Measures(Statewide)
  • Element
  • Decks
  • Rails
  • Expansion Joints
  • Superstructure
  • Substructure
  • Total

Target 7 7 7 7 7 7
Actual 6.6 7.1 6.5 6.9 6.4 6.7
Scale 1- 9
15
Bridge Performance Measures(Statewide)
  • Element
  • Decks
  • Rails
  • Expansion Joints
  • Superstructure
  • Substructure
  • Total

Target 7 7 7 7 7 7
Actual 6.6 7.1 6.5 6.9 6.4 6.7
Scale 1- 9
16
BridgeLevel of Service(2002 Survey)
Bridges
17
Performance Measure Trends(Bridge)
18
Pavement Preventive Maintenance
Retreatment
  • Program has doubled since 2000
  • 2002 - 2800 miles at 31.3 million

Goal - 5000 miles per year at 77.5 million
19
Traffic Systems Maintenance
  • Signal Preventive Maintenance Program
  • (7,000 Traffic Signals Statewide)
  • Intelligent Transportation System/Incident
    Response Program
  • Total 26.8 million

20
Maintenance Funding Needs(Millions)
Needs Budget Shortfall (03-04) Routine
Maintenance (Roads Bridges) 620.6 428.1
192.5
21
Maintenance Funding Needs(Millions)
Needs Budget Shortfall (03-04) Routine
Maintenance (Roads Bridges) 620.6 428.1
192.5 Backlog (247.30 Million) 36.0
36.0
22
Contract Resurfacing
23
Contract Resurfacing
Resurfacing Cycles Per G.S. 136-44.3 Primary
System 12 yrs All Other Systems 15 yrs Total
Cost 227.4 million
24
Maintenance Funding Needs(Millions)
Needs Budget Shortfall (03-04) Routine
Maintenance (Roads Bridges) 620.6 428.1
192.5 Backlog (247.30 Million) 36.0
36.0 Contract Resurfacing 227.4 157.4
70.0
25
FEMA/FHWA Emergencies and Disasters (millions)
Storm Cost
26
Maintenance Funding Needs(Millions)
Needs Budget Shortfall (03-04) Routine
Maintenance (Roads Bridges) 620.6 428.1
192.5 Backlog (247.30 Million) 36.0
36.0 Contract Resurfacing 227.4 157.4
70.0 Backlog (103.70 Million) 10.4
10.4 Disasters 25.0 25.0
27
Maintenance Funding Needs(Millions)
2003-04
Needs Routine Maintenance (Roads
Bridges) 620.6 Backlog (247.30
Million) 36.0 Contract Resurfacing
227.4 Backlog (103.70 Million)
10.4 Disasters 25.0 Total Maintenance
Funding Need 919.4
28
History of Routine Maintenance Funding
94.6 M
Millions
29
History of Resurfacing Funding
28.4 M
Millions
30
Supplemental Maintenance Funds(Annual Basis)
  • TIP Funding
  • Traffic System Operations - 10 million
  • Positive Guidance Program - 6.6 million
  • ITS Traffic Operations - 11.3 million
  • Bridge Preservation Funds - 2 million
  • Senate Bill 1005
  • Traffic Mgmt. System Improvements - 15 million
  • Primary Pavement Preservation - 135 million

31
Impact of SB 1005 on Pavement Needs
  • Authorized use of Highway Trust Fund cash
    balances
  • Targets major primary system corridors
  • Provides approx. 423 million over 3 years
  • Approx. 5,500 lane miles will be strengthened and
    resurfaced
  • Helps eliminate resurfacing backlog
  • Reduces pavement needs

32
Primary Route Preservation ProjectsSB 1005 (Year
1 and 2)
Primary
33
Maintenance Funding Needs(Millions)
Needs Routine Maintenance (Roads
Bridges) 620.6 Backlog (247.30
Million) 36.0 Contract Resurfacing
227.4 Backlog (103.70 Million)
10.4 Disasters 25.0 Total
Maintenance Funding Need 919.4 Supplemental
Maintenance Funds - 179.9 Adjusted
Maintenance Funding Needs 739.5
34
Maintenance Funding Needs(Millions)
Needs Budget Shortfall (01-02) Routine
Maintenance (Includes Backlog) 521.6 378
143.6 Contract Resurfacing 229.0 115
114.0 (Includes Backlog) Disaster Recovery
35.0 0 35.0
35
Maintenance Funding Needs(Millions)
Needs Budget Shortfall (02-03) Routine
Maintenance 521.6 378 143.6 Contract
Resurfacing 229.0 115 114.0 Disaster
Recovery 35.0 0 35.0 Grand
Total 785.6 493 292.6
36
Statewide Annual Maintenance Funding Plan
37
Statewide Annual Maintenance Funding Plan
38
Maintenance Operational Improvements
  • LED Replacement for Signal Bulbs
  • Signal Preventive Maintenance
  • Improved Primary Pavements (SB)
  • ITS (IMAP) Initiatives
  • Road Oil Incentive Pay Program
  • DOC Litter Pickup Program
  • Pavement Preservation Implementation

39
Questions?