Title: Level 1 Muon Trigger Status and Commissioning


1
Level 1 Muon Trigger Status and Commissioning
  • Rob McCroskey
  • University of Arizona
  • for the
  • L1 Muon Group

2
Cabling
  • L1muo trigger crates (north, central, south) are
    85 complete
  • L1muo splitter crates (CFT, north, south) 30
    done - goal to finish by end of shutdown
  • L1muo centroid crates (2 north, 2 south) - FE
    cables run, not hooked up
  • In process of finding/fixing bad cables

3
Infastructure
  • All production power supplies installed and
    tested
  • Big thanks to Carl Lundberg for taking this
    project A-Z
  • Control/monitoring GUI supplied by Manas Maity
  • All rack prep done - Ed Arko Co.
  • Final PORC passed!!
  • Firmware written for next month of running -
    Mikhail Baturitskiy

4
Installed Hardware
  • All crate managers - cental, north, south, and
    manager
  • Trigger cards
  • CF
  • Five octants (0-4) CFTScint cards (05)
  • Five octants (0-4) PDTScint cards (10)
  • EFN, EFS
  • Two octants (0-1) CFTScint cards
  • Hope to add 1-2 more octants of 05 cards by next
    week
  • Centroid finding cards (MCEN)
  • EFN (A-layer)
  • One manager card
  • Four centroid cards

5
Triggers
  • Can trigger off Aphi, CMSC coincidences in CF and
    A, B pixel coincidences currently
  • Trigger is currently simple layer coicidence - no
    roads
  • Plan on putting in pixel roads soon
  • Working on PDT triggers currently - will start
    with simple deck trigger (e.g., 4/4 decks hit
    in A-layer)
  • MDT triggers questionable - work on getting MCEN
    cards running next week and sending centroids to
    L1muo trigger cards for A-layer north

6
Trigger List
  • 1. A.C scint coincidence central
  • 2. A.C PDT coincidence central
  • 3. A.B scint coincidence north
  • 4. A.B scint coincidence south
  • 5. A.C scint coincidence CNS
  • 6. A.C scint and PDT coincidence
  • 7. Central dimuon (coincidence in two central
    octants)
  • 8. Anywhere dimuon (coincidence in any two
    octants)
  • d0server4\\users\johns\xls\
  • mtm-terms-may-june.xls

7
July 1
  • Assuming some short accesses, we plan on
    installing more scintillator cards (05) in both
    CF and EF
  • Hardware is on hand, awaiting testing/debugging
  • Everything in place for plug and play operation
  • Wire boards (10) will require work - first batch
    (10/28) have some soldering problems on BGAs
  • Improved scint. coincidence logic in both CF and
    EF