Title: Economic and Reliability Optimization for Central Energy Facilities
1F i n a n c i a l C o n s u l t i n g S e r v
i c e s
- Economic and Reliability Optimization for Central
Energy Facilities
James T. Drews, Presenter POWER-GEN
International Orlando, Florida November 30, 2004
2Two Case Studies
- Large university
- Optimized existing resource utilization
- Metropolitan newspaper
- Self generation upgrade evaluation
3Large University
- Two campus electrical load
- 2 gas turbine cogeneration units (13.6 MW)
- 2 power purchase agreements (46 MW)
- Campus-wide heating requirement
- 5 boilers (225 kpph) 2 HRSGs (48 kpph)
- Campus-wide chilled water system
- 15 electric chillers (23,500 tons)
4Management Model
5Operating Scenarios
Instantaneous Operating Conditions
Chilling (tons) Heating (kpph) Electricity (MW)
Scenario 1 20,000 11 32
Scenario 2 10,000 44 18
Scenario 3 5,000 31 6
6Scenario 1 Hourly Energy Cost
7Scenario 2 Hourly Energy Cost
8Scenario 3 Hourly Energy Cost
9Lessons Learned
- Distinct resource utilization option results in
lowest energy cost - Effective modeling will determine lowest energy
cost options - Management utilization of resource tool will
minimize energy costs
10Metropolitan Newspaper
- Approximate 4 MW peak load
- Installed 3 MW gas turbine
- Heat recovery steam generator (17 kpph)
- 3 chillers electric absorption
11Strategic Options Evaluated
Capital Investment Option Cost
Continue self generation with current unit 0
Procure all electric needs from utility 0
Install new 4 MW gas turbine 1.8 M
Install new 5 MW gas turbine 2.4 M
Install supplemental 1.4 MW engine 1.1 M
Install 700 kW turbine in steam cycle 0.7 M
12Hourly Electric Load Profile
13Hourly Chilling Load Profile
14Electricity and Natural Gas Prices
Gas Cost (/MMBtu) Electricity Cost (/MWh)
Base Case 4.00 65.00
Low Electricity High Gas Prices 5.00 45.00
High Electricity Low Gas Prices 3.00 76.00
15Nominal Electric / Gas Rates
16Low Electric / High Gas Rates
17High Electric / Low Gas Rates
18Supply Options Results
- Existing installation most cost effective
- Larger units inefficient given load profile
- Payback 11 years on other viable options
- Potential improvements
- Peak load reduction
- Third-party fuel supply
- Client avoided an undesirable investment
19The Bottom Line
- Hourly load profiling is critical
- Integrated annual hourly energy supply/use model
must be tailored for client specifics - Capital investment/supply contracting options
require detailed load analysis - Management accountability is critical