Economic and Reliability Optimization for Central Energy Facilities - PowerPoint PPT Presentation

About This Presentation
Title:

Economic and Reliability Optimization for Central Energy Facilities

Description:

Campus-wide chilled water system. 15 electric chillers (23,500 tons) Management Model ... 3 chillers: electric & absorption. Strategic Options Evaluated $ 0.7 M ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 20
Provided by: jamest50
Category:

less

Transcript and Presenter's Notes

Title: Economic and Reliability Optimization for Central Energy Facilities


1
F i n a n c i a l C o n s u l t i n g S e r v
i c e s
  • Economic and Reliability Optimization for Central
    Energy Facilities

James T. Drews, Presenter POWER-GEN
International Orlando, Florida November 30, 2004
2
Two Case Studies
  • Large university
  • Optimized existing resource utilization
  • Metropolitan newspaper
  • Self generation upgrade evaluation

3
Large University
  • Two campus electrical load
  • 2 gas turbine cogeneration units (13.6 MW)
  • 2 power purchase agreements (46 MW)
  • Campus-wide heating requirement
  • 5 boilers (225 kpph) 2 HRSGs (48 kpph)
  • Campus-wide chilled water system
  • 15 electric chillers (23,500 tons)

4
Management Model
5
Operating Scenarios
Instantaneous Operating Conditions
Chilling (tons) Heating (kpph) Electricity (MW)
Scenario 1 20,000 11 32
Scenario 2 10,000 44 18
Scenario 3 5,000 31 6
6
Scenario 1 Hourly Energy Cost
7
Scenario 2 Hourly Energy Cost
8
Scenario 3 Hourly Energy Cost
9
Lessons Learned
  • Distinct resource utilization option results in
    lowest energy cost
  • Effective modeling will determine lowest energy
    cost options
  • Management utilization of resource tool will
    minimize energy costs

10
Metropolitan Newspaper
  • Approximate 4 MW peak load
  • Installed 3 MW gas turbine
  • Heat recovery steam generator (17 kpph)
  • 3 chillers electric absorption

11
Strategic Options Evaluated
Capital Investment Option Cost
Continue self generation with current unit 0
Procure all electric needs from utility 0
Install new 4 MW gas turbine 1.8 M
Install new 5 MW gas turbine 2.4 M
Install supplemental 1.4 MW engine 1.1 M
Install 700 kW turbine in steam cycle 0.7 M
12
Hourly Electric Load Profile
13
Hourly Chilling Load Profile
14
Electricity and Natural Gas Prices
Gas Cost (/MMBtu) Electricity Cost (/MWh)
Base Case 4.00 65.00
Low Electricity High Gas Prices 5.00 45.00
High Electricity Low Gas Prices 3.00 76.00
15
Nominal Electric / Gas Rates
16
Low Electric / High Gas Rates
17
High Electric / Low Gas Rates
18
Supply Options Results
  • Existing installation most cost effective
  • Larger units inefficient given load profile
  • Payback 11 years on other viable options
  • Potential improvements
  • Peak load reduction
  • Third-party fuel supply
  • Client avoided an undesirable investment

19
The Bottom Line
  • Hourly load profiling is critical
  • Integrated annual hourly energy supply/use model
    must be tailored for client specifics
  • Capital investment/supply contracting options
    require detailed load analysis
  • Management accountability is critical
Write a Comment
User Comments (0)
About PowerShow.com