Title: Review of performance of privatised Caribbean utilities
1Review of performance of privatised Caribbean
utilities
- Presentation to UWICED/SIDS Unit Experts Meeting
on Capacity Building and Development of SIDS
Energy Sources - Niue 8 11 July, 2003
- Basil Sutherland Independent Consultant
2- Current policy framework a brief review of
industry structure, energy policy and utility
regulatory history in the Caribbean - How effective have these policies been? Have
developments yielded the expected benefits? - What lessons have been learned?
- What new arrangements are needed to ensure better
performance, particularly in the area of using
new and renewable energy?
3(No Transcript)
4Industry structure and current regulatory
practice in the region
- The structure of the industry and the regulatory
arrangements generally characterised by - The existence of vertical monopolies
- The existence of 20-50 year exclusive licences
- regulatory procedures which, with only few
exceptions, are not open to public scrutiny - Very few tariffs are incentive based
- Most utilities have cost-plus tariffs which
guarantee a rate of return on capital
5- Virtually all tariffs have fuel cost recovery
clauses but only very few of these also have - heat rate targets
- targets for transmission losses
- benchmarks are not widely used
- Although some have voluntary customer service
standards, very few have such standards imposed
in their licenses
6Liberalisation Privatisation
- Key energy policy initiative pursued most widely
by Caribbean governments in recent years has been
the privatisation of formerly state-owned
electric utilities - Privatisation is motivated by
- budgetary pressures
- desire to attract private capital
- need to improve efficiencies
7Issues relating to Liberalisation Privatisation
- Privatisation and liberalisation have raised
several questions - ability to address security of supply in the most
economical manner, - extend accessibility to energy services,
- and to promote sustainable development
- Questions also arise as to degree of control
governments have over privatised utility
8- Often, current sector arrangements do not reflect
the fact that the objectives of national economic
policy are often wider than the interests of the
power sector - Policy should not stop at ensuring the viability
of electricity generation and distribution in a
country - Viable electric utility only important within
context of overall economic development
9Antecedents - How did we get to this position?
- At one time electric utility industry
characterised by dozens of disparate and small
generating facilities scattered around each
country - Sometimes these were privately owned but more
often they were government-owned facilities - To allow for orderly expansion of facilities, as
well as the opportunity to reduce operating
costs, governments intervened to create unified
and centrally managed electric utilities
10- Several jurisdictions at one time had Public
Utility Commissions and legislation and other
judicial or quasi-judicial processes governing
the approval of requests for changes in
electricity tariffs - Processes usually involved complicated public
hearings - Dominica, St. Lucia and Jamaica
11Difficulties with earlier arrangements
- Firstly, regulators in those days were often
untrained in regulatory matters and had little or
no background in the sector - Secondly, utility commissioners probably
misunderstood their mandate and often saw
themselves solely as defenders of consumer
interests and paid little attention to
reasonable requirements of investors - Thirdly, and perhaps because of the first two
reasons, the process turned out to be exceedingly
time consuming resulting in considerable
regulatory lag
12- Hearings were often contentious
- The result was that tariffs were held at levels
significantly below the marginal cost of supply - There was significant under-investment in the
power sector leading to capacity shortages - private investors were unwilling to invest if
returns could not be assured - even governments themselves were loathe to invest
capital in enterprises which did not provide
positive returns - because subsidies were often needed, utilities
operated on hand-to-mouth basis and supply became
unreliable and efficiencies deteriorated
13- and some solutions ...
- In an effort to mobilise fresh private capital
for the sector, governments moved to simplify
regulatory arrangements - Repealed or allowed public utility commission
legislation to fall into disuse - Granted exclusive licences which provide
guaranteed rates of return on capital employed
14- Yielding largely positive results ...
- Increased investments resulted usually
accompanied by increased rates and most
jurisdictions with private involvement in sector
no longer suffer from significant shortages of
capital - Over time, forgetting the earlier period,
governments and customers have now become
dissatisfied with arrangements - Perception now is that there is insufficient
transparency in utility operations - Driven largely by developments outside the
region, perception is also that competition will
improve service and lower prices
15Where and how could such competition take place?
- Transaction costs are not insignificant
- estimated that the first IPP venture in Jamaica
incurred costs amounting to well over US2.5
million for legal fees alone - The conclusion appears to be that the scope for
meaningful competition at the core level of
supply is very limited - competition however possible in cases where
generation for own use permitted using grid for
back-up - more competition in procurement and the
competitive outsourcing of certain non-core
functions possible
16Conclusions regarding competition
- Market liberalisation therefore limited in scope
in Caribbean introduction of supply level
competition at the core cannot be used as a
reliable tool to minimise costs - Where competition is not possible or practical,
governments must ensure that regulation be
implemented to - protect consumers by attempting to use it to
approximate market value of service - protect utilities by allowing them to anticipate
a sustainable return on investment - determine standby connection tariffs,
transmission open access etc. for self generators
17Regulatory issues and options
- If utilities do not succeed, everyone loses
consumers, investors and government -
- Utility will need to be regarded as a
public/private partnership rather than a purely
private enterprise even if it is privately owned
18Context and purpose of the Case Studies
- Many privately owned utilities believe
- they should service their clients by focusing on
efficiency, including cost-effective
technologies and - making electricity available to the poor and
rural areas is mainly an issue for social policy
19- several utilities have established non-optimal
planning criteria for the retirement and
expansion of generation capacity - Very few include economic as opposed to purely
financial criteria in their planning - the absence of heat rate and technical line loss
targets in the tariffs in several countries means
that inefficiencies in the use of fuel are simply
passed on to the consumer via fuel surcharges
20- Because of absence of environmental analysis and
legislation which captures environmental
externalities and allocates costs to the utility
sector and consumers of electricity,
environmental consequences are rarely factored
into the analysis of privatization costs and
benefits
21Policy reforms needed
- Generally, the answer to several of the above
questions, is that there is a need for
policymakers to introduce effective, strong and
transparent regulatory frameworks while avoiding
detailed interventions by government in the
sector - This regulatory framework should be independent
and set clear guidelines as to what utilities are
supposed to do, and what incentives they will be
allowed for the pursuit of social objectives
22Privatisation objectives
- The purpose of the case-study evaluations is to
determine the extent to which each of the
privatisation objectives have been achieved where
previously stated, but more importantly, to
determine - whether the respective government has been
relieved of the financial burden of meeting the
financial needs of expanding the sector - the extent to which the service coverage and
quality of service objectives set during
privatisation negotiations have been achieved
23- the extent to which reliability of service has
been improved - the extent to which governments have received
optimum returns to national budgets from
privatisation/divestment of what is a significant
national asset - whether the objective of securing the lowest
possible prices for electricity has been met
24- the extent to which the privatisation within the
context of the existing regulatory arrangements
and sector policy framework has encouraged or
discouraged the use of renewable energy for the
production of electricity - how the regulatory environment has facilitated of
hindered the process of privatisation
25Outcomes
- While certain positive effects have resulted from
the privatisation of electric utilities also
several unexpected and unintended consequences - It is clear that several of the original
objectives of the privatisations were not
achieved in the arrangements eventually entered
into. For example
26- In several cases governments did not satisfy the
objective of receiving the maximum returns from
the divestment - Most privatisations have so far failed to achieve
a lowering of the real price of electricity - So far also, the levels of line losses have not
been reduced significantly, and generally,
privatised utilities do not show lower losses
than government owned bodies
27- It would appear that the only significant benefit
which has accrued from privatisation is that of
relieving governments of the financial burden of
expanding the sector - and even this has not been achieved in the case
of Dominica - privatised utilities have shown little regard for
governments desire to encourage renewable energy
development
28- On the other hand, the programme to attract
private power by way of independent power
projects has been largely successful in Jamaica - the lowest cost producer on the system in Jamaica
is now one of the IPPs.
29Lessons learned conclusions
- The main conclusion that can be drawn from this
review is that the chances of success in
privatisation of the power sector are more
assured when - the policy framework, including the regulatory
regime, is consistent with Governments
expectations for the sector - Any new regulatory regime is set up ahead of the
privatisation and has had sufficient time to
demonstrate regulatory independence over a
reasonable period of time
30Some preconditions for success in developing
renewable energy
- To assist utilities and their customers to
achieve efficient energy conversion and end-use,
and encourage renewable energy development,
governments and regulators should ensure that - electricity rates reflect the true cost of power
- tariffs are incentive-based and are not cost plus
- Over the long-run, the policy framework should
also take account of environmental externalities
31- to encourage the development of renewable energy
projects, governments and regulators could also
consider allowing electric utilities a margin of
preference of up to 15 external benefit for
power it generated itself or purchased from
Independent Power Producers -
- the utility would pay up to a 15 premium for
electricity generated from renewable sources
compared to the average price paid for fossil
fuel generated electricity and be allowed to
recover these costs in the tariff - this would ensure that renewable sources of
energy become a part of the electricity
generation mix this margin could be reduced on
a phased basis
32How can utilities contribute to achieving
governments objectives for developing renewable
energy?
- Utilities can assist in achieving objectives of
energy conservation policies and other policies
to reduce GHG emissions in several ways - reduce technical losses to economically optimum
levels - improve fuel efficiency of prime movers
- set up demand side management programmes
- give support to development of economically
feasible renewable energy projects - Build capacity among their staff to understand
the potential long-term benefits of renewable
energy use