Title: Ohio Statewide Automated Child Welfare Information System
1Ohio Statewide AutomatedChild Welfare
Information System
- Partnership Forum
- August 18, 2006
2Opening Remarks/Confirm Agenda
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
3UAT and SACWIS Reports
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
- Angelo Serra
- Nancy DeRoberts
4User Acceptance Test (UAT)
- Functional Testing
- 139 of 154 UAT scenarios have passed
- Outstanding scenarios report dependent
- Using Muskingum data
- Functional Defects
- 9 Critical/High
- 65 Medium/Low
- System Is Stable And Number Of Open Defects Has
Declined Significantly
5User Acceptance Test (UAT)
6SACWIS Reports
- 81 Priority One Reports Delivered Into Pilot On
8/7/06 - 6 Priority One Reports On Hold Due To Financial
Interfaces Or Undergoing Additional Testing - Reports Are Being Utilized In The Day To Day
Workflow At Muskingum - Testing Of 60 Priority 2 3 Reports Remains A
Priority For All UAT Teams - 20 Priority 2 3 Reports Have Passed In UAT
- 18 Of The 20 Passed Reports Are Being Made
Available To Pilot - The Remaining Reports Will Be Moved Into Pilot No
Later Than 45 Days Into The Pilot Period
7SACWIS Reports
8Pilot Implementation Status Report
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
- Tom Heilman
- Ronda Hollingshead
9Pilot Implementation
- Pilot Implementation Successfully Initiated In
Muskingum PCSA On August 7th - On-site Project Team Working Hand In Hand With
Muskingum Staff - Overall Good Progress And A Positive Morale From
The County - Twice Daily Conference Calls With On-site Pilot
Team - OCF Training Complete (Pilot) 8/11/06
- On-Site Team at OCF during Week of 8/14
10User Support
- Self Help
- On-line Help
- WBT
- Training Materials
- Super Users
- Help Desk Support
- Super Users
- Super User Roles
- Two Help Desks
- Defects Reporting Process
- Knowledge Base
- http//www.webetools.com/drc/users/kb.php
- RRT
11Pilot Ticket Status
12Tickets by Area
13Pilot Implementation
- OCF Training Complete (Pilot) 8/11/06
- On-Site Team at OCF during Week of 8/14
14Conversion Status
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
15Muskingum County Pilot Conversion
- Data Converted The Weekend Of 8/5/06 For The
Start Of Pilot - 8/3/06 Production environment prepared
- 8/4/06 Core conversion processing
- 8/5/06 Verification process project county
- 8/6/06 Issue research and resolution
- 8/7/06 Muskingum begins using SACWIS
16Lessons Learned
- Data Conversion Process
- In general, process worked well
- Small adjustments needed i.e. - allow more time
to review control reports - Process flow chart allowed for effective progress
communication - Post Conversion Feedback
- Issues addressed and appropriate conversion logic
has been updated
17Next Steps
- Distribute Next Round Of Error Reports For SIS
Counties - Resume Contact With Each Metro County
- Incorporate Lessons Learned Into Metro County
Conversion Programs - Validate Conversion Process For Metro Counties
18Statewide Implementation
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
19Statewide Implementation Plan
- Currently Scheduled To Begin November 6th
- Revised Draft Of Statewide Implementation
Schedule Available - Revised Roll-out Now Includes Extended Wave 1 For
CAS Pilot
20Statewide Implementation
- Wave 1 Counties
- Project Implementation Liaisons In Place
- Complete LDAP Process
- Reviewing Error Reports
- Duplicate Reports
- Data Clean-up
- Workflow Review
- Staff Training Considerations
- Optionally Plan A Pilot Visit
21Statewide Implementation
- Future Waves
- Review Error Reports
- Duplicate Reports
- Data Clean-up
- Workflow Review
22Financial Interfaces
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
- Rob Plummer
- Nancy DeRoberts
23Overview
- Background
- Reimbursement Type And Vehicle
- Plan For Development And Testing Of Interfaces
- Cut-over To SACWIS Financials
- Changes In Timing Of Reimbursement
- Questions?
24Financial Interfaces Background
25Reimbursement Type and Payment Vehicle
26Plan for Development and Testing of Interfaces
- Auditors Interface Design Scheduled To Begin
Next Week - CAS Interface Design Scheduled To Begin In 3
Weeks - Auditors Interface Deployment Scheduled For
September - CAS Interface Deployment Scheduled For November
27Pilot Validation of Interfaces
- Auditors Office
- Interface will be validated by Muskingum County
during their pilot activities - CAS Interface
- An additional two weeks have been added to Wave 1
of Statewide Implementation to validate the
interfaces processing of FCM reimbursement - Adding Marion County to the Wave to ensure that
the interface is fully exercised - The first monthly run of the interface is
scheduled for November 21, 2006
28Financial Cutover to SACWIS AA SAMS
29Financial Cutover to SACWIS Foster Care
30Financial Cutover to SACWIS Foster Care
Training, PASSS, and Non-Recurring
31Changes in Timing of Reimbursement
32Implementation Readiness
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
33Additional Updates
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM
34Mobile Effort Scope of Work
- Duration
- Start approximately 30 Days into Pilot
- Three 30 Day Sessions, Six users each session
- Each Users/Participant To Receive 1.5 To 2 Hours
Of Training That Covers - Laptop Basics
- Security Basics and Usage
- Usage Tracking
- Solution Usage
- Support Information
- Responsibility Sign-Off and Unit Checklist
35Mobile Effort Support
- Special Point Of Contact For Support Of This
Effort - Weekly Follow-up Calls
- Final Satisfaction Survey
36Mobile Effort Progress
- Completed
- Configuration defined for the mobile SACWIS
laptop. - A test laptop has been built and configured using
the mobile wireless technology that is targeted
for use during the pilot. - The first set of wireless connectivity tests have
been completed second set to be completed this
weekend. - Next Steps
- Complete the wireless connectivity tests
- Complete security forms for Infosec to set up the
18 Muskingum laptop users - Configure 6 laptops for use by the first 6
Muskingum laptop users - Define and deliver a training solution
- Start the mobile SACWIS laptop pilot
37SACWIS Interfaces
- CRIS-E/MMIS Interfaces
- Amendment Currently being Finalized with DAS
- Interfaces Will be Available at Statewide
Implementation - Financial Interfaces
- Auditors Interface Will Deliver 45 days into
Pilot - CAS Interface Will Be Piloted In Wave 1 of the
Roll-Out - Wave 1 Has Been Modified and Extended (Now 30
Days) to Allow the CAS Interface to Be Fully
Exercised and Confirmed - SETS Interface
- Anticipate Delivery in 2007
38Wrap-Up/Next Meeting
OHIO STATEWIDE AUTOMATED CHILD WELFARE
INFORMATION SYSTEM