Title: Request for Service (RFS)
1 Request for Service (RFS) Process and Metrics
Update June 24, 2008
2Todays goal is to update AITR members on the RFS
process and planned improvements
- This briefing
- Reviews RFS process goals and performance
objectives - Establishes process roles and responsibilities
- Identifies issue areas that are currently
impacting RFS execution - Discusses proposed actions to improve the RFS
process and monitor progress
3We have developed action plans to address key
issues with RFS and renewed efforts to improve
the process
- Executive Summary
- Request for Service is one of the top challenges
the organization has faced over the last two
years, and it remains a key point of customer
frustration and dissatisfaction - We are renewing our focus on this area by
identifying additional resources to work RFSs,
investigating root causes for delays, making
process improvements, establishing process
metrics and communicating changes - We are currently designing metric reporting tools
and analyzing data to identify on going process
improvements - We have set a target of July 1 as our goal to
resolve key issues identified and begin meeting
the defined performance targets for RFS project
delivery - Based on resource plan execution our target has
been redefined as Aug. 1st. - Active customer participation in certain areas of
the RFS process is essential to ensure that we
properly set and meet customer expectations - Customer participation is critical to help
improve the process and remain on track for the
delivery of RFS proposals
4What is Request for Service?
- Request for Service (RFS)
- Is a request from an agency to provide new or
enhanced services. These services typically
require some level of solution development and
unique pricing. - RFS Examples
- Facility relocation, provide Network, voice, PC
deployments, etc. - New System hosting
- Install Wireless network
- Phone System Upgrade
- Provide additional computing resources, servers,
PCs, etc. - Approximately 177 RFS requests currently in queue
(May 1, 2008, was 203) - 107 RFS requests in front-end phases (May 1,
2008, was 133) - 70 RFS requests in close-out phases (May 1, 2008,
was 70) - Cancellation of RFSs remains high
- 29.6 (91 of 308) of all RFSs opened in the RFS
register have been cancelled - Reasons for cancellation range from the customer
no longer desires the solution to budgetary
issues
5The RFS Process is organized into 10 Phases
- Lead Qualification
- Requirements Gathering
- Customer Requirements Analysis Review Sign-off
- Technical Solution and Cost Proposal Development
- VITA Solution Review and Pricing
- Customer Proposal Review Sign-off
- Authorization to Proceed
- Solution Implementation
- Customer Acceptance of Work Sign-off
- Invoicing and Archiving
6We have established target timeframes for each
RFS phase
RFS Phase Target
1. Requirements Gathering (Note 2, 4) lt 15 days from meeting
2. Date for a Date Commitment (Note 3) lt 10 days
3. Preliminary Solution Review ( Note 2, 4) lt 15 days
4. Solution Delivery to VITA (Note 3) or gt 95 on time delivery/year
5. Solution Delivery to Customer (Note 4) lt 7 days from item 4 above
6. Customer Solution Review (Note 2, 4) lt 10 days from item 5 above
7. Authorization to Proceed (Note 3, 4) lt 5 days from item 6 above
8. Implementation (based on Acceptance Criteria defined in SOW) (Note 3, 4) or gt 95 on time delivery/year
9. Completion Notice Sent to VITA lt 15 days from item 8 above
10. Sign Off (Note 3, 4) lt 10 days from item 9 above
Note 1
- All days are in business days (excludes
weekends) - 95 on time targets will be running monthly
measures and will be based on overall annual
performance - Beginning performance period for revised metrics
reporting is January 2008. - RFS Light (single platform project) is typically
shorter timeframe - Change orders may result in renegotiated or
adjusted target dates for implementation.
Note 1- Parallel events from Step 1 Note 2-
Formal customer meetings Note 3- Monthly
Performance Metrics Note 4- Requires customer
involvement
7- We identified areas where RFS delays generally
occur and identified actions needed to address
them
RFS Issues and Actions
Issue Area Recommended Action
Lead Qualification Identify and introduce projects as early as possible Mature CAT meetings to increase focus on strategic plans
Requirements Gathering Improve identification, understanding, agreement and sign off of business and functional requirements needed to develop solutions
Solution Development Add technical resources for solution development Add network, voice and server/mainframe resources to meet current demand
Pricing Add business management (pricing) resources Develop additional pricing models for RFS (new RUs, approach)
Performance Measures Continue to develop/implement actionable performance measures to manage the process and proactively address issues
Note Typically we have found that the RFS
pipeline gets clogged on the front end of the
process and not during implementation
8We are developing RFS Performance Metrics to
measure our progress and drive continuous
improvements
- Two Types of New RFS Monthly Performance Measures
- RFS In-Flight Performance or RFS Issues Log
- Description The Issues Log provides early
warning and actions needed for those RFS
proposals that are at risk, so we can monitor and
take actions to address and resolve issues - Goal Update on a daily basis, or as needed
basis, to Report on actions, owners and due dates
to resolve open issues for those projects that
are late or are at risk of being late to avoid or
reduce delays and customer impact - Status In production
- RFS Monthly Performance Metrics
- Description These metrics will provide rear
view mirror of actual performance and will be
reported in Monthly Program Reviews - Goal Produce actionable performance results
report on those that are in band and
manage/address those projects that are out of
band or missed targets - Status In final stages of development, pending
production
9How Our Customers Can Assist with the RFS Process
- Lead Qualification Ensure VITA is pulled in with
Agencies and consultants early to jointly develop
plans and identify projects - we are your
business partners and can help guide the process
and improve quality - Requirements Gathering Actively participate in
requirements gathering, preliminary solution and
final solution review meetings with timely
feedback and approvals - Authorization to Proceed (ATP) Provide ATP as
early as possible or identify concerns that need
to be addressed - Requirements or Scope Changes Update your APM or
Project Manager on requirements/scope changes
promptly, so we can effectively manage resulting
change orders and schedule impacts - Project completion sign off Provide prompt
project completion sign off, based on defined
acceptance criteria in SOWs
10Next Steps and Recovery Schedule
- Address Lead Qualification issues and develop and
execute customer communications plans related to
RFS process and customer involvement
Communications plan complete- communications
underway. - Resource commitment to address RFS solution
development and pricing issues - Adding a total of thirteen (13) dedicated
resources to address current RFS back-log - Target to add eight (8) resources by May 15
- Target to add five (5) resources by May 30
- Current status
- Currently we have added 9 of the 13 projected
resources - Remaining resource should be on-board by mid July
- Complete development of initial Monthly
Performance Metric Reports - Target is July 14,
2008
11Questions and Recommendations?