Title: Great Lakes Legacy Act of 2002
1Great Lakes Legacy Act of 2002
- SAME Presentation
- November 3, 2005
- Dave Cowgill, U.S. EPA GLNPO
2Cumulative Sediment Volume Remediated In U.S.
Great Lakes
3So, How much is left?
- The U.S. Policy Committee has recently estimated
that 75,000,000 cubic yards, with an associated
cost range from 1.6-4.4 Billion for remediation. - The Legacy Act will help us make a dent in this
number - The Great Lakes Regional Collaboration
AOC/Sediment Strategy chapter emphasizes the
importance of the Legacy Act
4(No Transcript)
5Great Lakes Legacy Act of 2002
- a new tool in the Great Lakes sediment
remediation toolbox
6History
- The Great Lakes Legacy Act (GLLA) five year
authorization - 50M per year for contaminated sediment
remediation - 3M per year for new technology
- 1M outreach and education
- 9.9 Million appropriated in FY2004
- 22.3 Million in FY2005
- 30 Million in FY2006
7GLLA funding and project types
- Three types of projects must be in U.S. Areas of
Concern (AOCs) and - Remediation Implement a plan to remediate
contaminated sediment (highest priority) - Monitoring Monitor or evaluate contaminated
sediment - Source Control Prevent further or renewed
sediment contamination
8Funding Priority
- Under the Act, priority is given to the following
projects - Remedial action for contaminated sediment
- Projects that have been identified in a Remedial
Action Plan and are ready to be implemented - Projects that will use an innovative approach,
technology, or technique that may provide greater
environmental benefits, or equivalent
environmental benefits at a reduced cost or - Projects that include remediation to be commenced
not later than 1 year after the date of receipt
of funds.
9Cost-Sharing
Non-Federal Cost Share Must be at Least 35 of
Total Project Costs and 100 of Operations and
Maintenance Costs, and
- May include in-kind services,
- May include monies and in-kind services under an
administrative order on consent or judicial
consent decree, - May NOT include any funds pursuant to a
unilateral administrative order or court order.
10Project Requirements
- Remedial Alternatives Analysis
- Dredging, capping, natural recovery
- Short and long term effects of remedial
alternatives on human health and the environment - Site will not suffer significant, further or
renewed contamination
11How projects are paid for
- Non-Federal Cost Share Must be at Least 35 of
Total Project Costs and 100 of Operations and
Maintenance Costs - Not a grant not a contract
- Project Agreement with a partner
12Project Proposals Received
- Proposals for 12 AOCs from 6 States from initial
solicitation, but the door is always open! - Remediation
- Black Lagoon, Trenton MI
- Ruddiman Creek, Muskegon, MI
- Hog Island, Superior, WI
- Tannery Bay, Sault Ste. Marie, MI
- Assessment
- Ryerson Creek, Muskegon, MI
13Black Lagoon Trenton, MI
- Removed 116,000 cubic yards
- Total cost 9,600,000
14Black Lagoon Trenton, MI
- Follow up restoration and other activities
- City of Trenton has received 113K for
restoration of site - Funding for Detroit River International wildlife
refuge - Adjacent brownfields have been purchased
15Hog Island Inlet - Superior, WI
- 50,000 cubic yards of sediment being removed
- Excavation in the dry after dewatering not
dredging - Fish recovery during dewatering
- Projected mass removal includes 500 pounds of
PAHs and 7000 pounds of lead - Total Cost 6,300,000
16Hog Island Inlet - Superior, WI
- AOC has a habitat restoration plan in place
- Working with community, local and state partners,
and NOAA to undertake larger scale long term
restoration plan for site
17Ruddiman Creek Issues
- Historic discharge of industrial wastes
containing heavy metals, PCBs and hydrocarbons - Extensive filling of banks with foundry sand and
solid waste - Sediment, soil and groundwater contamination
present - Residential area with unrestricted access to
contaminated sediments
18- Three Primary Objectives
- Reduce risks to human health, wildlife, and
aquatic life in Ruddiman Main Branch Pond - Restore the aquatic habitat
- Prepare for recreational, residential, and
economic redevelopment of Main Branch and Pond
area
19Ruddiman Creek Watershed
20Step 1 Evaluation of Source Control
- Identify Industrial/Municipal Discharges
- Controlled through permit process
- Identify Municipal Storm Water Discharges
- Controlled through the Phase II storm water
permit process - Contaminated Ground Water
- Remediation of the Drum Dump
- 2004 groundwater investigation Control of VOCs
21Ruddiman Creek - Muskegon, MI
- 80,000 cubic yards of contaminated sediment is
being removed from Ruddiman creek and pond - Project has several components including creek
excavation and pond dredging - Sediments will be disposed of in a licensed
landfill near Muskegon
22Contamination Removal
- 80,000 cubic yards of contaminated sediment to be
removed estimated to contain
23Ruddiman Creek - Muskegon, MI
Water from the excavation areas is being treated
onsite, then pumped to the local wastewater
treatment plant for further treatment
24Ruddiman Pond - Muskegon, MI
- Sediments in the pond are being dredged with an
environmental dredging bucket - Silt curtains are used to keep resuspended
material contained - All dredging is followed by confirmatory sampling
25Characteristics of the Ruddiman Remediation
Project
- Install 58,200 sq. ft. of road
- Road construction with geotextiles and Swamp
Mats, use of aqua dams - Erosion control - 3 ft. fabric silt fence, straw
bales and wood chips
26Ruddiman Creek - Muskegon, MI
- Goal is to restore a more natural stream flow
- Braided streams
- Flow dissipation
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32Post Remedial Monitoring/Restoration
- Monitoring within all remedial areas to insure
sediment targets have been achieved-more dredging
as necessary - Monitoring one year after all remedial activities
complete - Complete restoration plan laid out in project
plan - Continue to work with community on restoration
projects
33438,000 sq ft restored
- Install Wing Dams, Riffle structures, Check Dams,
- control erosion during flood events and reduce
sediment migration - Cover bottom of channel with sand layer and side
slopes with a gravel layer - Geotextile on Main Branch and floodplain
- Grade excavated channels to 12 slopes
- Cover bottom and sidewalls with erosion control
blanket - Place coir log rolls along dredged stream bank
- Plant temporary annual grass seed
- 50,000 native wetland upland plants, permanent
grass/flower seed
34A Cooperative, Joint Effort
- USEPA, Great Lakes National Program Office
(GLNPO) - USEPA, Emergency and Rapid Response Services
(ERRS) Office - Michigan Department of Environmental Quality
(MDEQ) - US Army Corps Of Engineers (USACE)
35Projected Cost of Cleanup
- Total cost approximately 10.6 million
- 6.9 million Legacy Act funds (65)
- 3.7 Clean Michigan Initiative funds (35)
The Clean Michigan Initiative is a 675 million
bond to clean up, protect and enhance Michigans
environmental quality and natural resources.
36Ruddiman Creek - Muskegon, MI
- Project is driven by a very active community who
are participating in all aspects of the project
including restoration plans
37- Great Lakes Legacy Act http//www.epa.gov/glla
Contact Marc Tuchman (tuchman.marc_at_epa.gov) U.S.
EPA Great Lakes National Program Office