1LBNL Budget System Proposal
- Finance Network
- October 14, 2004
2Topics
- Historical Background
- Budget System Assessment Process
- Scope of Budgeting at LBNL
- Desired Functionality Common Themes
- Possible Solutions
- Recommendation
- Implementation Strategy
- Return on Investment
- Next Steps
3Historical Background
- 1996-1997 FMS implementation project
- One goal was the implementation of PeopleSoft
Budgets. - Determined that PeopleSoft Budgets was not
capable of meeting LBNLs needs. - Could not handle LBNLs complex burden and
overhead structures. - Overly rigid model for the dynamic nature of
project budgeting at LBNL.
4Historical Background
- 1998-1999 Budget System RFP
- Goal Identify a commercially available budget
system. - Determined that none satisfied the Laboratorys
requirements. - Lab management recommended the development of an
in-house system.
5Historical Background
- 2000 Janus system
- Development plan - phased release approach.
- Used by many for project budget formulation and
execution. - Addresses only a portion of original Budget
system requirements. - 2000-2001 Funding database project
- Requirements developed by FSD, Divisions, and
ISS. - Development put on hold by FSD and ISS to focus
on higher priorities.
6Historical Background
- 2003 Major areas of budgeting functionality
continued to lack automation and integration with
the Laboratorys enterprise financial management
and reporting systems. (and still do today.)
7Budget System Assessment
- In 2003-2004, a Budget System Assessment was
performed to - Reexamine the Laboratorys multifaceted business
requirements in the budgeting area - Study the available solutions and
- Make recommendations regarding the best course of
action for providing the Laboratory with a
comprehensive, integrated budget system. - The ultimate goal will be to implement a
comprehensive, integrated budget system which
standardizes Lab-wide budgeting processes,
improves reporting and controls, and reduces the
use of redundant systems.
8Budget System Assessment Team
- Chuck Axthelm
- Margretta Campbell
- Lauretta Corsair
- Bridget Haverty
- Executive sponsors
- Jeffrey Fernandez
- Gita Meckel
- Anne Moore
- Rich Nosek
- Ivy Tran
- Anil Moré
9Budget System Assessment Process
- Review existing requirements documentation.
- Conduct interviews with Laboratory Management and
staff to analyze current LBNL processes and
requirements. - Assess the PeopleSoft 8.8 Budgeting module.
- Assess budgeting solutions in use at other DOE
Laboratories. - Assess fit/gap with existing and future LBNL
systems. - Develop a recommendation for Management review.
10What is budgeting, anyway?
11Scope of Budgeting at LBNL
12Scope of Budgeting at LBNL
13Scope of Budgeting at LBNL
14Scope of Budgeting at LBNL
15Current System Capabilities (Janus)
16Desired Functionality Common Themes
- Timely funding information
- Institutional planning information
- The Spend Forecast (formerly known as the
Management Report - Resource (Labor) Planning
- System Integration
- Excel interfaces
- Quick Budget Tool
17Desired Functionality Common Themes
- What-if analysis capability
- Budget vs. actuals reporting
- Non-Project-Tree rollups
- More reporting, and more flexible reporting
18PeopleSofts Budgeting System
- Investigated the latest version (8.8)
- Still not capable of meeting LBNLs needs
- Cannot handle LBNLs complex burden and overhead
structures. - Overly rigid model for the dynamic nature of
project budgeting at LBNL.
19Other DOE Laboratories Solutions
- Based on information gathered at the annual FMSIC
and Budget Officers conferences, the team
investigated the following Laboratories systems
- Lawrence Livermore National Laboratorys FACTS
system (based on commercial software from
Comshare) - Pacific Northwest National Laboratorys FRx
system (commercial software from Microsoft) - Brookhaven National Laboratorys Budget and
Forecasting System, written in-house using the
PeopleSoft development tool set.
20Fit / Gap Analysis
21LBNLs Janus System
22LLNLs FACTS System
23PNNLs FRx System
24Brookhavens System
25Recommendation
- Implement Brookhavens System at LBNL.
- Advantages
- Best fit to LBNL requirements.
- Encompasses funds control and institutional
planning functionalities. - Easily integrated with our PeopleSoft FMS.
- Familiar look and feel.
- Easily supportable technology.
- Its free.
26Implementation Strategy
27Current LBNL System Configuration
28Implement ePME
29Implement Funds Control Functionality
30Integrate Funds Control with BLIS
31Deploy New Reporting and Analytics
32Implement Local Project Planning Functionality
33Interface Janus to the New System
34Provide a Quick Price Tool
35Provide Standard Excel Interfaces
36Implement Institutional Planning Functionality
37Extend Reporting and Analytics
38Provide Excel Download Capability
39Integrate Planning Information with BLIS
40Provide Additional System Integration
41Future -- Refine ePME
42Future -- Phase Out Janus
43Return on Investment
- Timely funding information
- This will be made possible via the BNL systems
funds control functionality. - Institutional planning information
- The Spend Forecast (formerly known as the
Management Report) - These will be facilitated by the BNL systems
institutional planning functionality.
44Return on Investment
- Resource (Labor) Planning
- This is a specific strength of the BNL system.
- System Integration
- System integration will be addressed at many
points during the implementation. Integration
with our other institutional systems will be
further facilitated by the BNL systems
PeopleSoft architecture.
45Return on Investment
- Excel interfaces
- This will be directly addressed through the
planned standard Excel interfaces, the Quick
Price Tool, and the standard Excel download
formats. - Quick Budget Tool
- This will be specifically provided in the
implementation.
46Return on Investment
- What-if analysis capability
- Integration with Excel will offer tremendous
flexibility in this area for local planning
purposes. Having an institutional planning
system will facilitate what-if analysis at the
institutional level. - Budget vs. actuals reporting
- This will be addressed as we add new reporting
options and flexibility.
47Return on Investment
- Non-Project-Tree rollups
- This is really a reporting issue, and will be
addressed as such. New trees to support
alternative hierarchies will be developed and
managed via the PeopleSoft tool set. - More reporting, and more flexible reporting
- Enhanced reporting will be a major focus. Ad-hoc
end-user reporting will be facilitated through
the use of the Cognos reporting tool set.
48Next Steps
- Get approval (and some incremental funding) from
the Enterprise Computing Steering Committee
(ECSC). - The implementation schedule will depend on
Management priorities, funding, and resource
availability. - Obtain a copy of the system from BNL for
demonstration and prototyping purposes. - When resources are available, begin work.
49?.