2'1 Magnet Design Studies Alexander Zlobin - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

2'1 Magnet Design Studies Alexander Zlobin

Description:

Introduction. FY2005 status. FY2006 plan and budget. Summary. 2.1 Magnet ... New LHC IRs need high-field large-aperture magnets (D and Q) with high operation ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 22
Provided by: tdserve
Category:

less

Transcript and Presenter's Notes

Title: 2'1 Magnet Design Studies Alexander Zlobin


1
2.1 Magnet Design Studies Alexander Zlobin
Introduction FY2005 status FY2006 plan and
budget Summary
2
Possible LHC IR designs
Single-aperture IR design
Double-aperture IR designs
New LHC IRs need high-field large-aperture
magnets (D and Q) with high operation margin and
long lifetime
3
Scope of work
  • LARP magnet RD includes the following basic
    directions
  • technology development for Nb3Sn IR magnets
  • IR magnet design studies
  • Design Studies scope of work
  • Model magnet design studies and analysis
  • proposal generation or evaluation including
    magnet parameters, design concept, cost, schedule
  • preparation of key decisions
  • IR magnet conceptual design studies
  • magnet parameter space, radiation dose and
    life-time, exotic magnet designs (double-aperture
    dipole and quadrupoles with parallel and
    non-parallel apertures), etc.

4
FY2005 directions and tasks
  • In FY2005 we identified three key directions and
    five tasks for LARP Magnet Design Studies
  • 2.1 Design Studies
  • 2.1.1 Quadrupole 
  • 2.1.1.1 Shell Block design comparison
  • 2.1.1.2 Shell mechanical design study
  • 2.1.2 Separation dipole 
  • 2.1.2.1 D1 design
  • 2.1.2.2 D1 cooling study
  • 2.1.3 Cryogenics 
  • 2.1.3.1 IR cryogenics study
  • Practically all tasks are based on participation
    of at least 2 Labs.
  • Work coordination is performed through the
    personal communications, video and phone
    conferences and at collaboration meetings.

5
FY2005 budget
  • DS budget in FY2005 is lt10 of the total LARP
    Magnet RD budget
  • Due to limited budget in FY2005 most of the DS
    work at FNAL and LBNL is supported by Labs core
    program funding

6
Task 2.1.1.1 status
  • Task Name IRQ design comparison shell-type vs.
    block-type
  • Task leader P. Ferracin (LBNL)
  • Participating laboratories FNAL, LBNL
  • Task goals Investigate potential of racetrack
    quadrupoles for LHC luminosity upgrade, continue
    the comparison of racetrack-type and shell-type
    IR quadrupoles started in FY2004.  
  • Current status The task is making good progress.
    The comparison strategy was developed including
    the beam envelope, magnetic, mechanical, thermal,
    radiation and quench protection requirements.
    Several IR quad designs were generated and
    compared with 90 mm shell-type quads including
    magnetic and mechanical parameters. Next steps
  • radiation energy deposition analysis and its
    effect on magnet operation margin and life-time
    (thermal analysis, radiation dose)
  • quench protection
  • The task needs to be extended to FY06.

7
Block-type IRQ coils and mechanical structure
8
Task 2.1.1.2 status
  • Task Name Possibilities and limits of IR
    shell-type quad mechanical designs based on
    Al-shell and collarsSS-skin
  • Task leader G. Ambrosio (FNAL)
  • Participating laboratories FNAL, LBNL
  • Task goal Evaluation of advantages and
    limitations of different mechanical concepts for
    large aperture, high-gradient, shell-type
    quadrupoles
  • Current status The following mechanical concept
    are being studied
  • SS-collars and SS-skin,
  • Al-shell and iron pads using bladder and keys,
  • SS-collars and Al-shell using bladder and keys.
  • Mechanical analysis is in progress revealing
    potential mechanical problems in 4-layer 110-mm
    IR quads.
  • The analysis needs to be extended to smaller
    aperture magnets including 90-mm TQ models.

9
Task 2.1.2.1 status
  • Task Name D1 Dipole Design (open midplane)
  • Task leader R. Gupta (BNL)
  • Participating laboratories BNL, FNAL, LBNL
  • Task goal Develop a magnet design that satisfies
    the requirements for the dipole first optics of
    LHC IR luminosity upgrade.
  • Current status Conceptual designs of an open
    mid-plane dipole and its simplified POP model
    have been developed and reviewed. 2D magnetic and
    mechanical analysis has been performed.
    Alternative design approaches were also proposed.
  • Although the work on D1 hardware was postponed,
    D1 design studies will continue in FY06 to
    support LHC IR design studies.

10
Open midplane separation dipole (BNL)
Design/Quench/Peak Field 13.5 T/15 T/16 T, field
quality ???


Nominal horizontal coil spacing 120 mm
Nominal vertical coil spacing 40 mm
External absorber

Yoke OD 2 m

11
Larger-aperture separation dipole (LBNL)
Shell-type coil design
Block-type coil design
200 mm horizontal aperture, thick internal
absorber Bmax15-16 T, good field quality 1.5-2 m
iron OD
12
Task 2.1.2.2 status
  • Task Name D1 dipole cooling study
  • Task leader T. Peterson (FNAL)
  • Participating laboratories FNAL, BNL
  • Task goals To check the implications of large
    (100-200 W/m) heat loads on the internal passage
    sizes and magnet structure, and to check under
    what conditions, if at all, removing 1 KW or more
    from a 10 meter magnet is feasible.
  • Current status The work on this task has been
    started. The details of open midplane D1
    mechanical structure and alternative D1 designs
    will be used.
  • The duration of this task has to be extended.

13
Task 2.1.3.1 status
  • Task Name Conceptual design, parameters, and
    comparison of inner-triplet cryogenics at 1.9 K
    and 4.5 K.
  • Task leader R. Rabehl (FNAL)
  • Participating laboratories FNAL
  • Task goal Investigate and compare 1.9 K and 4.5
    K inner triplet cryogenic systems and coil
    temperatures for both single-bore and double-bore
    IR triplet designs.
  • Current status The work on this task is in
    progress. Figures of merit including DT from
    coils to feed box, required He II inventory, cold
    mass packing factor and compatibility with
    current cryostat diameter and feed boxes have
    been discussed.
  • This task will be continued in FY06.

14
FY2006 directions and tasks
  • Major DS directions have been modified based on
    the recent changes in program priorities (focus
    on IR quadrupoles).
  • Task reorganization was made to provide more
    flexibility to program needs and address
    important practical issues.
  • 2.1.1 IR Magnets
  • 2.1.1.1 Magnetic Design and Analysis
  • 2.1.1.2 Mechanical Design and Analysis
  • 2.1.1.3 Thermal Analysis
  • 2.1.1.4 Quench Protection Analysis
  • 2.1.1.5 Test Data Analysis
  • 2.1.2 Cryogenics
  • 2.1.2.1 Radiation Heat Deposition
  • 2.1.2.2 IR Cryogenics and Heat Transfer
  • 2.1.2.3 Cryostat Quench Protection

15
DS Working group
  • The DS working group in FY2006 will be reinforced
    including more experts from all three Labs
  • BNL R. Gupta, J. Muratore, J. Schmalzle, K.C. Wu
  • LBNL S. Caspi, P. Ferracin, A. Lietzke, G. Sabbi
  • Fermilab G. Ambrosio, S. Feher, V. Kashikhin, N.
    Mokhov, I. Novitski, T. Peterson, R. Rabehl, A.
    Zlobin
  • The DS team (the number of experts and their
    qualification) is sufficient to perform the
    planned work.

16
2.1.1 IR Magnets FY2006 Tasks
17
2.1.2 Cryogenics FY2006 Tasks
18
2.1.1 IR Magnets schedule
19
2.1.2 IR Cryogenics schedule
20
FY2006 DS budget
  • Total 400k (1.9 FTE)
  • Task budget
  • IR Magnets 290k
  • IR Cryogenics 110k
  • Lab budget
  • BNL 90k (0.4 FTE)
  • FNAL 190k (1.0 FTE)
  • LBNL 120k (0.5 FTE)
  • All three Labs agreed to provide support to LARP
    DS activities from their core magnet programs.

21
Summary
  • Design Studies are an important part of LARP
    Magnet RD.
  • Major DS directions have been identified.
  • Strong DS working group has been formed.
  • A good progress is expected in FY2005 in spite of
    limited resources.
  • FY2006-2007 DS work plan is focused on
  • supporting model magnet RD, data analysis and
    preparation of critical decisions in FY2007
  • Mechanical design and parameters of long
    quadropole (LQ)
  • Conceptual design of ultimate gradient quadrupole
    (HQ)
  • conceptual IR magnet design analysis in
    collaboration with AP group and CERN
Write a Comment
User Comments (0)
About PowerShow.com