Title: Agenda
1Agenda
- Presentation of the Archuleta County Road System
- Questions
- Public Comment please limit your comments to 3
minutes
2Archuleta County
3Road Network Inventory
- 286 miles in current road network
- 43 miles of paved roads
- 22 miles of chip seal roads
- 221 miles of gravel roads
- In addition, County assists in the maintenance of
up to 172 miles of Forest Service roads - Seven functional classes identified (Major
Arterials, Minor Arterials, Major Collector,
Minor Collector, Residential, Other,
Forest/Rec.)
4Pavement Type Distribution
5Asphalt Pavement Network Evaluation
- Represents 15 of Total Road Network
6Excellent Surface Drainage
7Good Surface Drainage
8Fair Surface Drainage
9Results of Condition Survey For Asphalt Paved
RoadsRemaining Service Life
- Average asphalt paved network RSL 8.5 years
- 0 of road network with RSL 0 years
- Most common types of pavement distress
- Fatigue Cracking
- Utility Cuts (Potholes/Patching)
- Edge Cracking
10Remaining Service Life Distribution
11Asphalt Pavement Poor ConditionRSL 2 years
12Asphalt Pavement Fair ConditionRSL 8 years
13Asphalt Pavement Good Condition RSL 12 years
14Gravel Road Network Evaluation
- Represents 77 of Total Road Network
15Results of Condition Survey For Gravel Roads
- Average gravel road network RSL 6.0 years
- 0.5 of road network with RSL 0 years
- Most common types of distress in gravel roads
- Poor Cross-Section
- Potholes
- Corrugations
16Gravel Road Remaining Service Life Distribution
17Failed ConditionRSL 0 years
18Poor ConditionRSL 2 years
19Fair ConditionRSL 4 years
20Good Condition RSL 6 years
21Excellent Condition RSL 10 years
22Surface Treated Roads Chip Seal
- Represents 8 of Total Road Network
23Results of Condition Survey For Chip Seal Roads
- Average chip seal road network RSL 6.4 years
- 5.3 of road network with RSL 0 years
- Most common types of pavement distress
- Fatigue Cracking
- Edge Cracking
24Current Distribution of Remaining Service Life
for Chip Seal Road Network
25Fatigue Cracking in Chip Seal
26Probable Cost
- Asphalt Pavement 950,000/mile
- Chip Seal 130,000/mile
- Gravel 80,000/mile
- Engineering Design 7.5 of Construction
- Construction Administration 2.5 of Construction
Based upon 2009 cost
27Archuleta County2009 Projects
- County Road 975 Reconstruction
- 837,322.00
- Arboles RB Facility
- 450,000.00
- Park Avenue Reconstruction
- 1,812,982.91
- Holiday Avenue Paving
- 508,609.35
- Juanita Bridge
- 1,141,758.00
- Gravel Application
- 370,000.00
- Magnesium Chloride Application
- 460,000.00
TOTAL SPENT IN 2009 5,580,000
28Normal Criteria Used to Rate Projects
- ADT (Average Daily Traffic)
- Condition of Roadway
- Classification of Roads
- Drainage
- Safety
29What other criteria should we consider to decide
on the next projects?