Title: Organization Structure and Integration MT 246 Module 17
1Organization Structure and IntegrationMT 246 -
Module 17
2This Lecture
- Review the way companies organize themselves
- Formally studied in the field of Organizational
Development - Review the Integration Process
3Business Organization Types
- Traditional
- Functional
- Geographical
- Customer
- Process
- Product
- Project
- Matrix
4Business Organization Objectives
- Organization success depends on the way
individuals and groups are organized - Employees can be organized by employee function,
product type, project, or geographic/customer
location - Managers in an organization will typically have 5
or 6 Direct Reports - Supervisors may have up to 15 or 20 technicians
in their group - Span of Control of a manager is determined by
position in the corporate hierarchy
5Business Organization Objectives (contd)
- Clearly define the flow of authority within the
company and the project - Typically have two types of organization charts
- Functional
- Project
- Deal with issues of reporting to both a project
and a functional manager - Two lines of authority
- Two bosses
- Authority matrix
- Deal with contractual authority to subcontractors
6Authority Matrix
7Integration Relationships on a Large Scale
Project
8Organization Design
- No best type of organization
- Unique for each organization
- Organization structure is dynamic
- Evolutionary responses to ongoing problems
- As organizations grow, or environment changes,
managers review and revise the organization
9Functional Organization Description
- Personnel in an organization are grouped by area
of expertise - Functional units or areas
- Marketing, finance, production, design
engineering, etc. - Accomplishment of a project requires coordination
between functional areas - A great deal can be learned by the study of Org
Charts
10Functional Organization Drawbacks
- When problems occur, functional managers must
resolve issues and set priorities - Problems can occur with this type of organization
when a functional manager has multiple projects
in progress simultaneously within his group - Schedule priorities and allocation of personnel
can allow a project to become an Orphan due to
manpower loading limitations, conflicts with
other projects, etc.
11Liaison Assignments
- This is the first step toward providing project
focus within a Functional Organization - Assign focal point within each organization to
interact across functional boundaries - Still has the problem of very complex management
interaction - Many individuals in each company responsible for
project health - No project manager
- Success of this type of organization depends on
the people involved, and their willingness to
own a problem - How do you interview and select/hire these
folks!!!
12Iron Butterfly Liaison Org Chart
13Project Team Assignments
- Assignment of Project Manager who reports to a
high level of the organization - Next step towards providing project management
focus - Accomplished by creating dotted line
relationship between project personnel - Weak Project Matrix
- Useful for small projects requiring fractional
headcount - Employees at the working level have two bosses
14Iron Butterfly Project Team Org Chart
15Project Organization Description
- For large projects, it is better to organize
around project deliverables - Allows excellent customer and project focus
- Combination of Functional and End Item
subprojects - Dedicated project personnel assigned only to your
project - Fractions of engineers are required for some
roles - Must assign people to multiple roles
16Iron Butterfly LOGON Project Org Chart
17Project Organization Drawbacks
- Temporary Organization
- At end of project, everyone has to scramble for
new project assignments - Different skills required at different project
phases - Hire/Release, or
- Use sub-optimal personnel skill mix if keep
project team intact throughout life of contract. - Small projects cannot justify dedicated project
manager and staff
18Project Organization Design Guidelines
- Carefully think through each key project role
- Consider several alternatives
- Organize around deliverable end items
- Change the organization with project phases
- Avoid weird org chart topologies and span of
control extremes
19Matrix Organization Description
- Grid-like structure of authority and reporting
relationships - Created by overlay of a project organization and
functional organization - Functional part of the organization is repository
for technical expertise and physical resources
(Labs, manufacturing areas, etc.) - Project manager negotiates personnel assignments
- Project manager controls money
- Functional manager controls personnel
(assignments, salaries, raises)
20Iron Butterfly Matrix Org Chart
21Drawbacks of Matrix Organizations
- Overlays horizontal resources onto Functional
vertical resources - Subject to authority conflicts between Project
and Functional managers - Engineers can be torn between dual loyalty to
Project Manager (tasker) and Functional
Manager(rater) - Required to wear two hats
- Functional manager controls promotions and raises
- Project manager recommends to the Functional
manger
22Org Chart Tips for New Employees
- New hires generally are not given org charts
- Must figure out organization upon assignment/hire
- Ask for and study Org Charts
- Study Telephone Directory
- Study company Web Site
- There are always two organizations
- Published Org Charts (Wiring Diagram)
- Informal Org Structure
- Usually derived from prior working relationships
- Family/school alums, etc.
23Org Chart Tips for New Employees (contd)
- Watch out for the Informal Org Structure!!!!
- It can hurt you if unaware
- It can help you if you figure it out
- Always treat upper managers, peers, and people
working for you with respect - They may shoot pool with the President
24How to Select a Project Organization
- Certain situations lend themselves to applying
certain types of organizations - No correct approach
- Depends heavily on the talent of the employees
- General guidelines apply
25Organization Criteria
- Frequency of new projects
- Duration of projects
- Size of projects
- Complexity of relationships required to succeed
26Large Scale Integration Projects
- Large projects often fail as a result of
incomplete definition of the lines of authority - Project manager must spend significant time and
thought on the organization of sub-projects and
sub-contracts - This can be quite complex
- If you have a complex reporting relationship, the
probability of failure goes up - Technical LSP develop and construct Complex
Systems - Systems Engineering
- Management of SE
27Large Scale Integration Projects(Continued)
- Large Government Projects
- Integration is Responsibility of Government
Agency - Integration Process is given to a Single
Oversight Body - Considerable Manpower
- Broad Technical Skills
- Usually Assigned to Lead or Prime Contractor
- Project Sponsor
- Contracts with Associate (Subsystem) Contractors
- Makes Major Decisions
- Resolves Conflicts
28Large Scale Integration Projects(Continued)
- Associates become Subcontractors to the Prime
- Take Direction
- Surveillance
- Approval
- Prime can be Given Even More of a Role
- Assists Sponsor with Choosing Subs
- Pricing Subsystems
- Allocating Funds
- Can be a Problem when Prime and Subs are
Competitors
29Large Scale Integration Projects(Continued)
- When Largest Primes Cannot Perform Alone, They
Team - One Company Assumes Prime Role
- Systems Engineering
- Management
- Appeals to Small and Medium Sized Companies
- Can Have Serious Interface Problems
- Sponsor may Force Prime to Sub in Selected Areas
30Large Scale Integration Projects(Continued)
- When Prime cannot Perform the Integration Role
- Sponsor Selects an Integration Contractor
- Performs Integration and Engineering Advice
- Have Expertise and Resources
- Can be a Conflict as Prime and Integrator are in
the Same Business - Can be Managing Their Competitors
31Integration in Systems Development Projects
- Integration of Functional Areas of the Project
Horizontal Integration - Integration of Phases of Project Vertical
Integration - Systems Development Project
- New Product Development
- Software Development
- Stages of Development Project are the Systems
Engineering Cycle
32Horizontal and Vertical Integration
33Integration in Systems Development Projects
(Continued)
- Nonintegrated Systems Development
- Traditional
- Work in Each Phase Performed by Functional Area
- Not Much Vertical or Horizontal Integration
- Each Phase Starts Over
- Process Involves little Interaction Between
Phases - Decisions are Made Sequentially and Independently
with Wrong Mix of People and Functional Areas
34Traditional Phases of Systems Development
35Integration in Systems Development Projects
(Continued)
- Life Cycle Costs
- Materials
- Production
- Distribution
- Operation
- Continue for as Long as it is Produced or Used
- Decision made Early Affect Entire Cycle
36Life Cycle Costs
37Integration in Systems Development Projects
(Continued)
- Two Approaches to Integration in Systems
Development Projects - Concurrent Engineering
- Organizational Approach
- Form a Single Team from All Functional Areas to
Work on Every Stage - Horizontal Works in Concert with Vertical
- Quality Function Deployment
- Vertical Integration Methodology
- Requirements First then Applied by Functional
Areas to Each Phase
38Concurrent Engineering
- Cross-Functional Teams
- Team may be
- Multifunctional Matrix
- Pure-Project
- Team Invites Different Functional Areas to
Participate as the Project Move from Stage to
Stage - Team Composition
- Engineers, Planners, Buyers, Marketers,
Suppliers, Customers
39Concurrent Interactions
40Concurrent Engineering(Continued)
- Cross-Functional Teams (Continued)
- Overlap in Design and Production Reduces Time
between Product Concept and Product Launch - Improves Design Trade-offs
- Product Features vs. Production Capabilities
- Sometimes Call Design-Build Teams
41Concurrent Engineering(Continued)
- Conditions Affecting Performance of Team
- Autonomy
- Committed Full Time and Full Duration
- Colocated
- Small Size
- Team of Multi-Talented Achievers
42Concurrent Engineering(Continued)
- Heavyweight Teams (Autonomous)
- A Core Team Approach
- PM and Small Group of Experts
- Strong Focus on Goals
- Free to Do Development in any Manner
- Draw from Functional Areas as Needed
- Con Small Team Cannot have Enough Technical
Depth
43Quality Function Deployment
- Methodology for Defining Customer Needs and
Requirements and Focus throughout Development
Process - Yields End-Items in Less Time and Lower Cost
- Process for Integrating Cross-functional Teams
and Activities - Developed by Mitsubishi Kobe Shipyards (1972)
- Toyota (1978)
- Ford (1983)
44Quality Function Deployment (Continued)
- House of Quality
- Translates Need into Technical Requirements
- Systematic Way of Organizing and Analyzing Data
- Prevents Things from being Overlooked
- Justifies Use of Resources
- Critical Few vs. Trivial Many
45Structure of the House of Quality
46Quality Function Deployment (Continued)
- QFD Process
- Create the First Matrix (A)
- The House of Quality
- Develop an Initial Project Plan
- In Parallel with HOQ
- Create the Design Matrix (B)
- Technical Reqs for House into Product Design
Features and Requirement - Create the Process Matrix (C)
- Takes Design Into Process or Production Reqs
47Quality Function Deployment (Continued)
- QFD Process (Continued)
- Create the Control Matrix (D)
- Takes Process Matrix into Process Tracking and
Control Procedures - Refine the Project Plan
- Improve based on (C) the (D)
- Process Ensures End-Item Traceabilty to
Requirements
48QFD Multiphase, Multimatrix Approach
49Preparing an Integrated Project Plan
- Information Needed to Build Plan
- Goal of Product or System
- Ranked List of Customer Needs or Reqs
- Ranked Technical Reqs Traceable to Customer Needs
- Target Values or Tech Reqs
- Information Quality(Pluses or Minuses) between
Reqs
50Preparing an Integrated Project Plan (Continued)
- The Matrices in the QFD Process connect Project
Tasks to Technical Requirements and Customer
Needs - Define the Relationships among tasks and the
order to Execute - Define the WPs and Project Network
- Do Schedule, Budgets
- You Have Worked the Process Hard at the Start
51LOGON Project
- Use Labor costs (An average of labor rates/task),
and Material costs. Do not worry about O/H or GA
expenses. Keep in mind that total costs of
Appendix C will not match with those in table 9-4 - Create your WBS, the PERT and GANTT charts
follow. Without them, any analysis is impossible.
Be sure all the tasks are connected properly
(levels, sublevels, etc). - Create a table of resources, identifying the
number of people and the Labor cost of step 1.
You can use material cost as a fixed cost. What
MS project calls Cost/use - Assign resources per task
- Check that resources are not over allocated, if
necessary, reassign them. Keep in mind that there
are labor requirements per task in table 9-4 - Now, Save your well designed budget , MS project
calls this budget the BASELINE. Do not type
Actual costs or completion before completing
this Baseline. (MS project has a tool, accessed
in the menu tools called tracking-save baseline)
52LOGON Project (Continued)
- Input percent complete and ACWP per task. This is
the table attached in the homework (MS project,
in the main menu, has an icon called task
information, it has a field called Percent
complete, and also, go to view-table-cost to
input ACWP). - Re-read subchapters 11-8 and 11-9. They will help
you as a guide in the process - Do cost and Schedule analysis, including BCWS,
BCWP, and ACWP. (MS project has a tool called
earned value, accessed in the menu
view-table-more tables-earned value). - Plot a graph costs vs time to analyze BCWP, BCWS,
etc - Create a table with variances like Table 11-1 to
have control of each work package of the project
(performance indicator, cost and schedule
variances)
53Next Lecture
- Managing Participation, Teamwork, and Conflict
- Read Nicholas Chapter 16