Title: Earned Value Management
1Earned Value Management
- Professor Kim Meyer
- DAU Midwest
- kimberly.meyer_at_dau.mil
- 937-781-1040
2Workshop Learning Objectives
- EVMS Background and Criteria
- General EVM Terminology
- Standards, Policy, and Guidance
- ANSI Standard and Guideline Approach
- EVM Contract Implementation
- EVMS Analysis
- EVMS Training and References
3Whats In Your PM Toolkit?
4EVMS Background and Criteria
5Definition EV, EVM, and EVMS
Earned Value
usually refers to contractors' internal
EVMS
Management
management control systems that meet the
Systems
guidelines
6What is Earned Value Management?
- Use of an integrated management system that
coordinates work scope, schedule, and cost
objectives and employs earned value methods for
program planning and control. - Industry Standard Guidelines for EVMS
7Integration of Systems for an EVMS
8Definition EVM System
- An integrated management system and its related
sub-systems which allow for - planning all work scope for the program to
completion - breaking down program work scope into finite
pieces that can be assigned to a responsible
person or organization for control of technical,
schedule, and cost objectives - Integrating work scope, schedule, and cost
objectives into a performance measurement
baseline plan against which accomplishments may
be measured - controlling changes to the baseline
- using actual costs incurred and recorded in
accomplishing the work performed - objectively assessing accomplishments at the work
performance level - analyzing significant variances from the plan,
forecasting impacts, and preparing an estimate at
completion based on performance to date and work
to be performed and, - using EVMS information in the companys
management processes
9Traditional Measurement
COST 40
BUDGET 50
STATUS Variance Budget - Actual 10
Favorable
10Earned Value Measurement
STATUS Schedule Variance Earned - Budget -15
Unfavorable Cost Variance Earned
- Actual - 5 Unfavorable
11Whos Who in EVM Government
- Federal Policy Office of Management and Budget
(OMB) - DoD Policy OSD Acquisition, Technology, and
Logistics - Executive Agent Defense Contract Management
Agency (DCMA) (compliance) - Auditing Defense Contract Audit Agency (DCAA)
- Agency/Service Staff support organizations
- Primary Users Program/Project Managers
- Technical staff and integrated product teams
(IPT)
12EVM Standards, Policy, and Guidance
13Definition Standards, Policy, Guidance,
Contractual Direction
- Standards
- Issued by industrial standards organization
- Establishes a set of guidelines that must be met
and adhered to - Policy
- Issued by federal agency
- Mandatory
- Exceptions must have waiver
- Guidance
- Issued by either the Government or industry
- Non mandatory
- Provides additional insight, references, etc.
- Contractual Direction
- Terms and conditions of contract
- Binding on both contractor and government
14EVM Guidance and Policy
15Policy
- OSD policy letter, 7 March 05
- Interim policy until formal update of DoD
Instruction 5000.2 - New thresholds (in then year )
- gt 20M, lt 50M Compliance with EVM standard
- gt 50M Validation against EVM standard
16Why do we need a standard?
- Government awards contracts that may be
- Very large
- Risky
- Government contracts have special burden
- Funded with taxpayer money
- Government needs assurances that performance
data - Indicates work progress
- Properly relates cost, schedule, and technical
accomplishment - Provides program managers with information at a
practical level of summarization - Is valid, timely, and able to be audited
17ANSI Standard
- Published by Electronics Industries Alliance
- Reaffirmed in 2002 only minor revisions
- ANSI/EIA-748-A-1998, Earned Value Management
Systems - Subsequently referred to as ANSI 748A in this
course - Maintained by National Defense Industrial
Association, Program Management Systems Committee
(NDIA PMSC) - NDIA PMSC maintains close coordination with OSD
18EVMS GuidelinesANSI/EIA 748-98
32 Criteria
19Guideline Approach
- Government recognizes that it cannot impose a
single solution - No single EVMS meets the needs of all companies
- Guidelines define the criteria for system
adequacy - Specify desired outcomes
- Not prescriptive
- Broad enough to allow for commonsense application
- Comprehensive enough to result in reliable
performance data - Beware of myths, legends, and accepted rules of
thumb
20Discussion Point
- Guideline or prescription?
Define the authorized work elements for the
program, using the EZ WBS Maker software tool to
develop and define the WBS structure to Level 6.
Define the authorized work elements for the
program. A work breakdown structure (WBS),
tailored for effective internal management
control, is commonly used in this process.
21EVMS CONTRACTIMPLEMENTATION
22Statutes Related to EVM
- Establish performance Standards for Federal budget
- Government Performance and Results Act of 1993
GPRA
- Report cost, schedule and performance goals and
evaluate progress
- Federal Acquisition Streamlining Act of 1994 -
Title V (FASA V)
- Information Technology Management Reform Act of
1996 (ITMRA / Clinger-Cohen
- Report performance information systems acquisition
23Office of Management Budget EVM Policy
- OMB Circular A-11 Part 7 Capital Programming
Guide
- Unified guidance to support OMB reporting to
Congress
Circular A-11 Policy
- Capital Programming Guide
- Agencies must establish cost, schedule and
performance goals for major acquisitions and then
achieve, on average, 90 of those goals - Version 2.0 provides guidance on integration of
EVM, IBRs, and risk management.
24DoD EVM Implementation Instructions
Purpose
Policy Memo
- Implements OMB Circular A-11
- MAR 7, 2005 ATL Policy Memorandum directs
changes to DoDI 5000.2 regarding EVM
Table E3.T2 Regulatory Information Requirements
- Applies to cost and incentive contracts,
subcontracts, and intra-government work
agreements of 20M and above. - Formal EVMS Validation is required above 50M
- Discouraged for FFP, LOE, and TM contracts
- Optional for efforts less than 20M
- Implement EVMS guidelines in American National
Standards Institute (ANSI)/Electronic Industries
Alliance (EIA) 748-A-1998 (R2002) - DoDI 5000.2 also directs when EVM required
- Use of a MIL-HDBK-881 Work Breakdown Structure
- Completion of Integrated Baseline Reviews
- Contract Performance Report (DI-MGMT-81466A)
- Integrated Master Schedule (DI-MGMT-81650)
25DoD EVM Application Thresholds
Thresholds
Contracts
Requirements
26Decision Process for EVM Application
Cost or Incentive Contract?
Contract Value lt20M
- Contract contracts, subcontracts,
intra-government work agreements, other
agreements - If contract type is mixed, then apply guidance
separately to different parts of contract - All thresholds are in TY
27Decision Process for EVM Application
Contract Type
Y
FFP
NO EVM
N
Y
Nature Of Work
LOE TM
N
Y
Value
lt20M
EVM Required ANSI 32 EVMS Required EVMS Certified
No 7001 RFP 7002 RFP Contract CPR DID
Formats 1 5 Required Formats 2, 3 4
Optional IMS DID Can Be Tailored
EVM Required ANSI 32 EVMS Required EVMS Certified
- Yes 7001 - RFP 7002 RFP Contract CPR DID 5
formats IMS DID No Tailoring
N
N
Y
50 M
Based on the March 7, 2005 Policy
28Earned Value within the Contracting Process
29EVM Inputs in the Contracting Process
- Where do you address EVM in the
Solicitation/Contract - Section C - Description/Specs/Work Statement
- Section I Contract Clauses
- Section J - Exhibits/Attachments
- Section L - Instructions to Offerors
- Section M- Evaluation Factors for Award
- Note Sections L and M are included in
Solicitations only
30Section C - Statement of Work
- The Statement of Work should contain statements
requiring - Development of a contract work breakdown
structure (CWBS) at a level adequate for
management and contract control - The contracted technical effort to use a
guidelines-compliant EVMS that correlates cost
schedule performance with technical progress - Designation of critical subcontractors by name
for EVM compliance and flow down of EVMS
compliance to subcontractors - An Integrated Baseline Review (IBR)
- Reference to EVMS data items as part of
Integrated Program Management reporting and
Reviews
See EVMIG for Sample SOW Statements
31Section I - General Provisions
- New FAR Clauses July 2006
- FAR 52.234-2 Notice of EVMS Pre-Award IBR
- FAR 52-234-3 Notice of EVMS Post Award IBR
- FAR 52-234-4 EVMS The Gov will conduct an IBR
if a pre-award IBR has not been conducted. - FAR EVM clauses not tied to dollar thresholds
- DoD Interim guidance (new DFARS approved
4/23/08) - Apply existing clauses (252.242-7001 and
252.242-7002) directly on contracts gt 20M - DoD Policy EVM DFAR clauses are equivalent to
the EVM FAR clauses and only the EVM DFAR clauses
will be used on DoD contracts
32Section J - Exhibits/Attachments
- Work Breakdown Structure - Mil-HDBK-881A
mandatory common WBS for CPR, IMS CCDRs through
WBS Level 3 - EVM Related Data Item Descriptions (DIDs)
- Contract Performance Report DI-MGMT-81466A
- Integrated Master Schedule DI-MGMT-81650
- Contract Work Breakdown Structure
DI-MGMT-81334B - Contract Funds Status Report DI-MGMT-81468
- Contract Data Requirements List (CDRL) used to
put CPR and IMS reports on contract - EVM CDRLs can and should be tailored within
bounds of policy - Tailoring options are limited for contracts gt
50M - Most aspects are tailorable for contracts lt 50M
- Consider all risk factors when tailoring CPR and
IMS DIDs - Type of contract (determined by cost risk)
- Technology
- Schedule
- Past contractor performance
33Section J CPR DID DI-MGMT-81466A
- The CPR consists of five formats
- Format 1 Work Breakdown Structure
- Format 2 Organizational Categories
- Format 3 Baseline
- Format 4 Staffing
- Format 5 Explanations Problem Analyses
- Uses of CPR Data
- Integrated Cost Schedule EVM Data
- Identify the cost and schedule impact of actual
and potential problems - Provide valid, timely program status info for
higher management - The CPR provides timely, reliable summary-level
data with which to access current and projected
contract performance.
34Section J - CPR Tailoring
- CPRs must be tailored to meet the needs of each
individual contract - Tailoring usually involves the following
- Reporting levels, Defining future periods,
Specific items of interest, Variance reporting
thresholds - Reporting Levels
- WBS/OBS reporting levels on Formats 1 2 should
be defined - Typically to level 3 of the CWBS
- High risk elements should be identified for
reporting (below level 3) - CCDR and CPR should use a common WBS. CPR allows
for tailoring below the CCDR reporting level - Future periods
- Formats 3 4 show the PMB and staffing forecast
respectively - Periods need to be defined in CDRL, identifying
months, quarters, years, or combination - Typically the first 6 columns identify the
upcoming 6 months
35Section J - CPR Tailoring (contd)
- Format 5 Narrative Analysis Reporting Thresholds
- Format 1/2 CV, SV, VAC- e.g. top 5 variances that
exceed a dollar threshold/percentage threshold.
(i.e. 1M or 5) - Format 3/4 changes from the previous period that
exceed specified percentage - Using condition statements such as and or or
will affect the number of variances reported to
the customer (e.g. 1M and 5 vs 1M or 5) - May identify a fixed number of variances (i.e.
top 5 variances by WBS Level 2 item) - Reporting thresholds can vary greatly depending
on the size, complexity, and risk of the program
36Section J IMS DID DI-MGMT-81650
- IMS shall include all discrete tasks/activities,
work packages, and planning packages identified
in the contract Performance Measurement Baseline
(PMB) - IMS shall identify significant external
dependencies (i.e. GFE, test facilities) - Suppliers and government playing a bigger role
in producing products - IMS shall be statused and submitted prior to or
concurrently with Contract Performance Report
(CPR) - Standard scheduling definitions are to be used
37Section J - IMS DID DI-MGMT-81650 (cont)
- Critical Path calculated by software
- Total Program Critical Path from beginning to end
- Software can not be specified but must meet
DI-MGMT-81650 requirements - Examples of available software tools
- Open Plan Professional
- Primavera
- MS Project
- Schedule Risk Assessments are to be submitted as
specified in the CDRL and prior to the Integrated
Baseline Review (IBR) - Float/Slack is an asset of the program and not
for the exclusive use or benefit of the
government - Monthly analysis is required in order to identify
potential problems and an assessment of the
critical path and near-critical paths
38Section J - IMS Tailoring
- Factors to consider when tailoring requirements
- Program risk should be prime consideration
- Contract type, Size of contract, Technology
maturity - Complexity of integration, e.g. multiple
subcontractors, GFE/GFP - Reporting Frequency
- Status as of end of calendar/accounting month be
consistent with CPR - Cost/Incentive efforts typically reported monthly
and must be consistent with CPR - FFP efforts may have less frequent reporting than
cost/incentive contracts - Variance Analysis Reporting
- Schedule variance thresholds for task on the
critical path and near critical paths usually
expressed in calendar/work days - Projected Start / Finish variances for major
milestones - Narratives discussing next contractual milestone
39Section J - IMS Tailoring (contd)
- Level of detail of schedule can be tailored based
on program risk - Subcontractor IMS deliverable
- Schedule Risk Assessment
- Quarterly, Semi-annually, selected key milestones
(PDR, CDR, Flight Test) - LRIP may only warrant at program start
- FFP environment Waive requirement for SRA or
less frequent than Cost/Incentive efforts - Electronic Data Interchange
- Delivered in native digital format Contractors
schedule tool (MS Project, Primavera, Open Plan,
etc) - Additional guidance can be found in the EVMIG
40Section J - Award Fee Plan
- Program managers often wish to tie award fee to
EVM performance - Care should be taken not to mis-incentivize the
supplier - Award fee criteria should reference effective
management of cost and schedule with EVM data - Criteria should not reference specific values for
CV, SV, CPI, SPI, or VAC - See EVMIG for additional guidance
41Section L - Instructions to Offerors
- Guidance to bidders for the assembly of their
proposals - Each offerors proposal shall include a
description of the EVMS to be used in accordance
with the appropriate RFP DFAR clauses - Compliance with Validation requires
- Reference to an Advance Agreement or Letter of
Acceptance and a copy of the approved EVM system
description or - A plan to obtain EVM validation to include how
and when the system will be validated - Compliance Only requires a written summary of
the proposed EVMS reference in sufficient detail
to show how it addresses all ANSI/EIA-748
guidelines
42Section M - Evaluation Factors for Award
- Evaluation of the proposed EVMS is normally
undertaken as part of the proposal evaluation
process to determine the probability of the
system meeting the guidelines. - For Existing Systems - evaluation may consist of
a confirmation that the referenced validation is
accurate and current. The system should be
currently in use, and surveillance should not
have identified significant, uncorrected
problems. - For EVMS (without validation) - the EVM system
description should be evaluated for completeness
against the guidelines in ANSI/EIA-748. - An on-site examination of a proposed EVMS should
not normally be required during proposal
evaluation. But if deficiencies are identified,
written communications or an on-site visit may be
required when approved by the Source Selection
Board and Procuring Activity. - DCMA should be requested to provide insight
regarding EVMS capability, quality, and past
performance.
43EV ANALYSIS
44CLASSIFICATION (When Filled In)
Page 1 of 2
CONTRACT PERFORMANCE REPORT FORMAT 1 WORK
BREAKDOWN STRUCTURE
Form Approved OMB No. 0704-0188
Thousands
DOLLARS IN
The public reporting burden for this collection
of information is estimated to be 3.1 hours per
response, including the time for reviewing
instructions, searching existing data sources,
gathering and maintaining the data needed, and
completing and reviewing the collection of
information. Send comments regarding this burden
or any other aspect of this collection of
information, including suggestions for reducing
the burden, to Department of Defense Washington
Headquarters Services Directorate for Information
Operations and Reports (0704-0188), 1215
Jefferson Davis Highway, Suite 1204, Arlington,
VA 22202-4302. Respondents should be aware that
notwithstanding any other provision of law, no
person shall be subject to any penalty for
failing to comply with a collection of
information if it does not display a currently
valid OMB control number. PLEASE DO NOT RETURN
YOUR FORM TO THIS ADDRESS. SUBMIT COMPLETED
FORMS IN ACCORDANCE WITH CONTRACTUAL REQUIREMENTS.
3. PROGRAM
4. REPORT PERIOD
1. CONTRACTOR
2. CONTRACT
a. NAME
a. NAME
a. FROM
(YYYYMMDD)
a. NAME
FIREBIRD II
CyboRaptor
FIREBIRD II
YYYY0601
(Address and ZIP Code)
b. NUMBER
b. LOCATION
b. PHASE
RDTE
FDS601-20006C-DO23
b. TO
(YYYYMMDD)
1100 Carey Ave
c. EVMS ACCEPTANCE
c. TYPE
d. SHARE RATIO
YYYY0630
Waynesville VA 21345
N / A
70/30
CPIF
5. CONTRACT DATA
f. ESTIMATED PRICE
a. QUANTITY
c. ESTIMATED COST OF AUTHORIZED UNPRICED
WORK
d. TARGET PROFIT/ FEE
e. TARGET PRICE
h. ESTIMATED CONTRACT CEILING
b. NEGOTIATED COST
i. DATE OF OTB/OTS (YYYYMMDD)
N / A
0.00
28,310.70
25,167.20
23,000.00
2,737 / 11.9
25,737 20
6. ESTIMATED COST AT COMPLETION
7. AUTHORIZED CONTRACTOR REPRESENTATIVE
b. TITLE
a. NAME (Last, First, Middle Initial)
VARIANCE (3)
CONTRACT BUDGET BASE (2)
MANAGEMENT ESTIMATE AT COMPLETION (1)
- BEST CASE
- WORST CASE
- MOST LIKELY
c. SIGNATURE
d. DATE SIGNED (YYYYMMDD)
21,160.00
23,000.00
22,187.10
474.00
23,000.00
7. PERFORMANCE DATA
CUMULATIVE TO DATE
AT COMPLETION
CURRENT PERIOD
REPROGRAMMING ADJUSTMENTS
ITEM (1)
ACTUAL COST WORK PERFORMED (4)
ACTUAL COST WORK PERFORMED (9)
VARIANCE
BUDGETED COST
BUDGETED COST
VARIANCE
BUDGETED (14)
VARIANCE (16)
ESTIMATED (15)
SCHEDULE VARIANCE (12b)
COST VARIANCE (12a)
WORK PERFORMED (3)
BUDGET (13)
WORK SCHEDULED (2)
WORK SCHEDULED (7)
COST (11)
WORK PERFORMED (8)
SCHEDULE (10)
SCHEDULE (5)
COST (6)
1.1 Air Vehicle
2
11,588.10
11,246.80
341.30
3,887.90
-479.90
-382.50
4,270.40
4,367.80
1,423.47
1,295.97
-159.97
-127.50
1,455.93
1.1.1 Weapons Delivery
3
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.1.2 Airframe
3
649.70
634.00
15.70
195.00
2.00
9.00
186.00
193.00
65.00
0.67
3.00
62.00
64.33
1.1.3 Engine
3
5,892.00
5,729.90
162.10
1,673.00
-645.40
-525.50
2,198.50
2,318.40
732.83
557.67
-253.43
-175.17
811.10
1.1.4 C2 System
3
896.20
847.10
49.10
368.90
49.10
34.50
334.40
319.80
124.51
17.91
13.04
111.47
106.60
1.1.4.1 Radio
4
562.80
552.70
10.10
215.00
11.00
5.00
210.00
204.00
73.21
5.21
3.21
70.00
68.00
1.1.4.2 TV Camera
4
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.1.4.3 Avionics
4
333.40
294.40
39.00
153.90
38.10
29.50
124.40
115.80
41.47
51.30
12.70
9.83
38.60
1.1.5 Self Defense
3
4,150.20
4,035.80
114.40
1,651.00
114.40
99.50
1,551.50
1,536.60
550.33
38.13
33.17
517.17
512.20
1.1.5.1 Flares
4
1,482.30
1,425.30
57.00
602.60
57.00
49.50
553.10
545.60
184.37
200.87
19.00
16.50
181.87
1.1.5.2 Flight Control
4
2,267.70
2,218.50
49.20
891.10
48.70
42.50
848.60
842.40
282.87
297.03
16.23
14.17
280.80
1.1.5.3 Sensor
400.20
392.00
8.20
157.30
4
8.70
7.50
149.80
148.60
52.43
2.90
2.50
49.93
49.53
1.2 Grnd Cont. Terminal
2
3,402.50
3,301.00
101.50
1,226.20
43.70
25.70
1,200.50
1,182.50
395.97
408.73
14.57
12.77
394.17
1.2.1 Radio
3
1,660.50
1,561.00
99.50
550.70
0.30
0.20
550.50
550.40
183.50
183.57
0.10
.07
183.47
1.2.2 Control Software
3
1,742.00
1,740.00
2.00
675.50
43.40
25.50
650.00
632.10
216.67
225.17
14.47
8.50
210.70
1.2.3 TV
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3
0.00
0.00
0.00
0.00
0.00
LOCAL REPRODUCTION AUTHORIZED.
DD FORM 2734 /1, MAR 05
CLASSIFICATION (When filled in)
45CLASSIFICATION (When Filled In)
CONTRACT PERFORMANCE REPORT
DOLLARS IN
Page 2 of 2
Thousands
The public reporting burden for this collection
of information is estimated to be 3.1 hours per
response, including the time for reviewing
instructions, searching existing data sources,
gathering and maintaining the data needed, and
completing and reviewing the collection of
information. Send comments regarding this burden
or any other aspect of this collection of
information, including suggestions for reducing
the burden, to Department of Defense Washington
Headquarters Services Directorate for Information
Operations and Reports (0704-0188), 1215
Jefferson Davis Highway, Suite 1204, Arlington,
VA 22202-4302. Respondents should be aware that
notwithstanding any other provision of law, no
person shall be subject to any penalty for
failing to comply with a collection of
information if it does not display a currently
valid OMB control number. PLEASE DO NOT RETURN
YOUR FORM TO THIS ADDRESS. SUBMIT COMPLETED
FORMS IN ACCORDANCE WITH CONTRACTUAL REQUIREMENTS.
7. PERFORMANCE DATA
AT COMPLETION
CUMULATIVE TO DATE
CURRENT PERIOD
REPROGRAMMING ADJUSTMENTS
ITEM (1)
ACTUAL COST WORK PERFORMED (9)
ACTUAL COST WORK PERFORMED (4)
VARIANCE
BUDGETED COST
VARIANCE
BUDGETED COST
VARIANCE (16)
BUDGETED (14)
ESTIMATED (15)
WORK PERFORMED (3)
COST VARIANCE (12a)
WORK SCHEDULED (2)
WORK SCHEDULED (7)
COST (11)
BUDGET (13)
SCHEDULE VARIANCE (12b)
SCHEDULE (10)
WORK PERFORMED (8)
SCHEDULE (5)
COST (6)
a.
WORK BREAKDOWN STRUCTURE ELEMENT (continued)
0.00
1.3 Launcher
2
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.4 Sys Program Mgmt
2
1,294.40
1,185.70
1,330.30
-108.30
-144.60
5,178.60
395.23
431.47
-67.10
443.43
-36.23
1.4.1 Project Mgmt
3
408.20
408.20
427.00
0.00
-18.80
1,473.00
136.07
136.07
-6.27
142.33
0.00
1.4.2 Sys Engineering
3
886.20
777.50
903.30
-108.70
-125.80
3,705.60
259.17
295.40
-60.83
320.00
-36.23
1.5 Sys Test Evaluation
2
265.10
224.00
253.20
-41.10
-29.20
863.30
74.67
88.37
-6.17
84.84
-13.70
1.5.1
Dev Test Evaluation
3
144.10
122.20
132.90
-21.90
-10.70
489.70
40.73
48.03
-3.57
44.30
-7.30
1.5.2
Oper TE Support
3
55.30
52.80
55.10
-2.50
-2.30
144.00
17.60
18.43
-0.77
18.37
-0.83
1.5.3 Mock-Ups
3
65.70
49.00
65.20
-16.70
-16.20
229.60
21.90
21.90
0.17
21.73
0.00
1.6 Sys Data
2
88.20
84.10
87.80
-4.10
-3.70
296.70
28.03
29.40
-1.23
29.27
-1.36
1.6.1
Eng Data
3
40.70
39.90
28.20
-0.80
11.70
202.50
13.30
13.57
3.90
9.40
-0.27
1.6.2 Mgmt Data
3
47.50
44.20
59.60
-3.30
-15.40
94.20
14.73
15.83
-5.13
19.87
-1.10
1.7
Pec Support Equip
2
167.10
157.70
187.20
-9.40
-29.50
498.60
52.57
55.70
-9.83
62.40
-3.13
1.7.1 Test Measure
3
68.50
71.90
96.90
3.40
-25.00
279.40
23.97
22.83
-8.33
32.30
1.13
1.7.2 Support Handling
3
98.60
85.80
90.30
-12.80
-4.50
219.20
28.60
32.87
-1.50
30.10
-4.27
1.8 Common Supt Equip
2
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.9 Spares Rep
2
10.70
9.90
9.10
-0.80
0.80
642.20
3.30
3.57
0.27
3.03
-0.27
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
b. COST OF MONEY
2953.90
-32.10
-72.50
920.60
888.50
961.00
2916.71
37.19
c. G A (Non- Add)
-10.70
-24.17
306.87
296.17
320.33
d. UNDISTRIBUTED BUDGET
0.00
0.00
0.00
e. SUBTOTAL (Performance Measurement Baseline)
7,296.40
-520.50
7,417.90
6,775.50
22,187.10
282.90
22,470.00
-642.40
2,427.93
-169.43
2,469.07
2,258.50
-210.57
530.00
f. MANAGEMENT RESERVE
22,187.10
812.90
g. TOTAL
23,000.00
-642.40
-520.50
2,427.93
2,258.50
7,296.40
7,417.90
6,775.50
-169.43
2,469.07
-210.57
9. RECONCILIATION TO CONTRACT BUDGET BASE
a. VARIANCE ADJUSTMENT
0.00
0.00
0.00
812.90
-642.40
-520.50
b. TOTAL CONTRACT VARIANCE
DD FORM 2734/1 MAR 05
LOCAL REPRODUCTION AUTHORIZED.
6
CLASSIFICATION
(When filled in)
46Relationship of the Contract Price to the Earned
Value Management System (EVMS)
Contract Price
Equals Total Allocated Budget (TAB) if no
contract mods
Profit / Fee
Negotiated Contract Cost
Management Reserve
- Withheld for Unknowns - No Scope or Schedule
PMB
Undistributed Budget
Summary Level Planning Packages
Control Accounts
- Temporary Holding - Work Authorized but no
detailed Budget or Schedule
- Specific Scope _at_ higher WBS level - Time-phased
budget - Strict Controls
Work Packages
Planning Packages
- Integrated Scope, Schedule Budget - No
Detailed Plans
- Integrated Scope, Schedule Budget - Detailed
Plans
47Time-Phased Performance Measurement Baseline (PMB)
Management Reserve
PMB
Completion Date
48Assessing Contractor Performance
- Gather the vital signs
- Usually given in a cost report
- Terms such as BCWP, BCWS, ACWP, EAC, LRE, BAC
- Process the vital signs
- Calculate variances, indices, percents, forecasts
- A thorough analysis will use each category
- Determine what the vital signs mean
- Based on the goodness or badness of the vital
signs, what does that tell you?
16
49Step-By-Step Analysis Process
- Gather earned value data
- BCWS, BCWP, ACWP, BAC (from CPR Format 1)
- Calculate point-in-time performance
- Cost Variance (CV) and Schedule Variance (SV)
- Can find on CPR Format 1
- Calculate trend indicators
- Cost Performance Index (CPI) and Schedule
Performance Index (SPI) - Calculate performance against the budget
- Complete, Spent, Scheduled
50Step-By-Step Analysis Process(contd)
- Forecast the cost to complete
- Estimate at Completion (EAC) (govt estimate)
- Calculate efficiency necessary to achieve EAC (or
LRE or BAC) - To-Complete Performance Index (TCPI)
- Analyze performance
- Evaluate and discuss variances, trend indicators,
progress against budget, forecasted cost to
complete, efficiency needed to complete - What is the status of our program?
51EV Key Variables
BCWS BCWP ACWP
A actual B budgeted or planned C cost W
work P performed S scheduled
BCWS This is what the plan called for BCWP
This is what the actual work done should have
cost ACWP This is what the actual work actually
costs
52EV Metrics
CV SV
C cost S schedule V variance
CV Difference between the budgeted cost and
actual cost of work performed (negative is
unfavorable) SV Difference between the work we
planned to accomplish and the work that was
performed (negative is unfavorable)
?
?
53EV Metrics
CPI SPI
C cost S schedule P performance I index
CPI How much actual work are we getting for
each dollar spent SPI How efficient is the
contractor in terms of schedule
54Earned Value Measurement
- SPI schedule efficiency
- SPIProgram lt 1.0, program is currently behind
schedule - SPITask lt 1.0, task is currently behind
schedule - Program is only behind schedule if task is on the
critical path - CPI cost efficiency (how much work is done per
dollar spent) - CPIProgram lt 1.0, program is currently over
budget - CPITask lt 1.0, task is currently over budget
- Program may or may not be over budget
If either CPI or SPI lt 0.70, then may have to
re-baseline
55Variances vs. Performance Indices
BCWP 600K ACWP 700K
BCWP 50K BCWS 150K
CV BCWP - ACWP CV 600K- 700K CV (100K)
SV BCWP BCWS SV 50K- 150K SV (100K)
BCWP 600K ACWP 700K
BCWP 50K BCWS 150K
SPI SPI 0.33
CPI CPI 0.86
- Variances measure magnitude, indices measure
efficiency
56Earned Value Measurement
ACWP BAC
- Spent
- Complete
- If spent gt complete, unfavorable
- If spent lt complete, favorable
BCWP BAC
16
57EV Key Variables
BAC EAC
B budgeted or planned E estimate A at C
completion
BAC What the entire program is supposed to
cost EAC What we now think the entire program
will actually cost
58Mathematical Approach to EAC Concept
- EAC Actuals to Date Work Remaining
-
Efficiency Factor - Actuals to Date ACWPCUM
- Work Remaining BAC BCWPCUM
- Efficiency (Performance) Factors Various
- - CPICUM
- Composite (CPICUM x SPICUM)
- 3-Period (month)CPI
- 6-Period (month)CPI
- Weighted (.8CPICUM .2SPICUM)
59Representative EAC Formulas
Method
Formula 1. EAC (Cum CPI) ACWPCUM
2. EAC (Composite)
ACWPCUM 3. EAC (3/6 Month CPI)
ACWPCUM 4. EAC (Weighted)
ACWPCUM
BAC
BAC - BCWPCUM CPICUM
CPICUM
BAC - BCWPCUM CPICUM X SPICUM
BAC - BCWPCUM (BCWP) (ACWP) 3 MO/6MO
BAC - BCWPCUM .8 CPICUM .2 SPICUM
60Estimate at Completion (EAC)
- (Estimate of Total Cost Thru any Given Level)
Alternative Approach for Computing EAC
If assumption is made that contractor will not
use available MRto complete contract, use
following standard formula
61Earned Value Data Interpretation
- EVMS Analysis Which EAC to use? (that is, EAC
based on which efficiency factor?) Should you
use BAC or TAB to compute EAC? (Consider
Management Reserve) - Efficiency Factors
- Cumulative CPI tends to be the most optimistic
estimate - Composite (CPICUM x SPICUM) tends to be the
most pessimistic estimate weights cost and
schedule equally - Three period (month) CPI shows most current
cost performance - Six period (month) CPI shows longer timeframe
for cost performance may be more accurate (or
less accurate) regarding true trends - Weighted (.8 CPICUM x .2 SPICUM) weights cost
more than schedule
62EV Metrics
TCPI
T to C complete P performance I index
TCPI How efficient do I have to be to finish on
budget
CPI measures past efficiency TCPI measures
future efficiency
13
63To Complete Performance Index (TCPI)
- (Cost Efficiency Needed from Now to Achieve
a Specific Target Cost)
Alternative Approach for Computing TCPI
If assumption is made that contractor will not
use available MRto complete contract, use
following standard formula
64Earned Value Data Interpretation
- What Do the Vital Signs Mean? Questions to Ask
- Is the contractors current performance favorable
or unfavorable? - Evaluate CV, SV, CPI, SPI, spent, complete
- What are the cost/schedule drivers on our
program? What actions need to be taken to improve
performance? - Is the contractors EAC (LRE) realistic? Is the
Governments? - Compare TCPI to CPIcum
- Is the price to complete the program forecasted
to exceed the contract ceiling price? Exceed the
budget? - If significant unfavorable variances, is the
baseline still valid? Is re-baselining
necessary?
65DoD TripWire Metrics
- Primary Trip Wires
- - System Indicator EVM System Certification
- - Integrated Baseline Development Indictor
IBR within 6 months of contract award cost,
schedule, technical risk identified and
quantified at IBR - Secondary Trip Wires
- - CPI and SPI cum index lt .95
- - Baseline Execution Index (BEI) baseline
tasks actually completed/baseline tasks
scheduled for completion cum index lt .95 - - Critical Path Length Index (CPLI) of PMB
(critical path duration float duration (to
baseline finish) )/critical path duration cum
index lt .95 - - To Complete Performance Index (TCPI) Work
Remaining/Cost Remaining CPI to TCPI delta of
gt10 - - PMB Revisions compared to monthly PMB
value delta of gt5 - - Contract Mods compared to original base
value delta of gt10
Reference EVM Government-Industry Working Group
brief, 21 Feb 2007
66- EVMS Training and References
67DAU Acquisition Community Connection
https//acc.dau.mil/evm
68ACC Included References
- https//acc.dau.mil/evm
- DoD Policy
- OMB Recommended References
EVMIG
69EVMS TrainingACC EVMS CoP
70EVMS TrainingDAU Continuous Learning Modules
https//learn.dau.mil/html/clc/Clc1.jsp?cl
71EVMS Tailored Training
- DAU can provide targeted training
- Tailored to specific organization needs
- Part of our Consulting/Performance Support
efforts - Potential Topics
- Integrated Baseline Review Workshop
- Program Startup Workshop
- EVMS Basics/Intermediate
- Scheduling Basics/Intermediate
- Source Selection
- For More Info, Contact Professor Kim Meyer
- 937-781-1040, kimberly.meyer_at_dau.mil
72 73Three Minute Acquisition Strategy Exercise
Earned Value Management Required - Yes or No EVM
System Validation Required Yes or No DFARS
Contract Clause Names Numbers to be used in the
RFP EVM Data Item Description (DID) Numbers
Names to be used in the RFP What formats of the
CPR DID (if any) would you tailor out with the
CDRL.
74Example 1
75Example 2
76Example 3
77Example 4
78CONTRACT
Pop I Smith
79CONTRACT
80CONTRACT
81CONTRACT
JAN
FEB
MAR
APR
MAY
JUN
82CONTRACT
FY04
FY06
83CONTRACT
FY04
FY06
84UNCLASSIFIED
CLASSIFICATION
Form Approved
CONTRACT FUNDS STATUS REPORT
(Dollars in
000
)
OMB No. 0704-0188
The public reporting burden for this collection
of information is estimated to average 8 hours
per response, including the time for reviewing
instructions, searching existing data sources,
gathering and maintaining the data needed, and
completing and
reviewing the collection of information. Send
comments regarding this burden estimate or any
other aspect of this collection of information,
including suggestions for reducing the burden, to
Department of Defense, Washington Headquarters
Services,
Directorate for Information Operations and
Reports (0704-0188), 1215 Jefferson Davis
Highway, Suite 1204, Arlington, VA 22202-4302.
Respondents should be aware that notwithstanding
any other provision of law, no person shall be
subject to any
penalty for failing to comply with a collection
of information if it does not display a currently
valid OMB control number. PLEASE DO NOT RETURN
YOUR COMPLETED FORM TO THE ABOVE ADDRESS.
1. CONTRACT NUMBER
3. CONTRACT FUNDING FOR
5. PREVIOUS REPORT DATE
7. CONTRACTOR
(Name, address and zip code)
Increda Corporation 1100 W. Hollymolly St Los
Angeles, CA 90293
9. INITIAL CONTRACT PRICE
INC
03-09-30
DAAH01-03-C-0076
a. TARGET 72,412.2
FOR FY 03 - 06
b. CEILING 75,475.7
2. CONTRACT TYPE
4. APPROPRIATION
6. CURRENT REPORT DATE
8. PROGRAM
10. ADJUSTED CONTRACT PRICE
CPIF
RDTE
03-12-31
LAR SDD 2003
a. TARGET 72,412.2
b. CEILING 75,475.7
FUNDING INFORMATION
11.
CONTRACT WORK AUTHORIZED
FORECAST
ACCRUED
NET
APPRO-
FUNDING
TOTAL
FUNDS
EXPENDITURES
FUNDS
LINE ITEM/WBS
PRIATION
AUTHORIZED
REQUIRE-
CARRY-
OPEN
ALL
DEFINITIZED
NOT
SUBTOTAL
NOT YET
SUBTOTAL
REQUIRED
ELEMENT
IDENTI-
TO
MENTS
OVER
OTHER
COMMITMENTS
DEFINITIZED
AUTHORIZED
FICATION
DATE
TOTAL
WORK
e
f
g
h
j
i
m
a
b
c
d
k
l
LAR SDD
2040
20473
13548
72412
0
72412
0
0
0
72412
0
72412
CONTRACT WORK AUTHORIZED
(With Fee/Profit)
- ACTUAL OR PROJECTED
12.
04-03-26
04-01-30
ACTUAL
AT
04-07-02
04-09-30
05-09-30
04-02-27
TO DATE
COMPLETION
2825
0
1320
1295
1365
1223
1263
0
a. OPEN COMMITMENTS
60942
12183
27519
72413
19141
34738
15422
17668
b. ACCRUED EXPENDITURES
13548
30344
72413
18963
16742
20364
60942
36001
c. TOTAL
(12a 12b)
7870
8756
72413
13. FORECAST OF BILLINGS
2513
18237
3240
2384
6820
TO THE GOVERNMENT
10942
0
11367
9906
14. ESTIMATED TERMINATION
13211
11846
13961
12196
COSTS
15. REMARKS
UNCLASSIFIED
DD FORM 1586, AUG 96 (EG)
PREVIOUS EDITION MAY BE USED.
of
Pages
Page
CLASSIFICATION