Title: Antiproton Acceptance
1Antiproton Acceptance
- Steve Werkema
- Temple Review
- January 20, 2004
2Scope
- Two Projects
- AP2 Beamline and Debuncher Acceptance
Improvements - Project Leader Keith Gollwitzer
- High Gradient Lithium Lens Upgrades
- Project Leader Jim Morgan
3Layout
- Layout of Antiproton Acceptance projects
- Target station downstream of target (Li Lens,
Pulsed Magnet, Target Dump) - AP2 beamline
- Debuncher ring
4WBS Overview
5Motivation
- Increase the number of antiprotons collected from
the target by - increasing the gradient of the collection lens
- increasing the admittance of the AP2 beamline
and the Debuncher
6AP2 Debuncher Acceptance Admittance
Measurement
- Improved Measurement of AP2 Debuncher
Horizontal Admittance - Figures at the right plot various measures of
beam loss and intensity as a function of
Debuncher horizontal scraper position. - Measurement performed while stacking.
- Top scan Scraper touch point
- Bunch Rotation ON, All Cooling OFF
- Loss Monitors downstream of scraper monitored as
scraper moved into beam at the end of a 30 sec
stacking cycle - Bottom scan Beam extinction point
- Bunch Rotation OFF, All Cooling OFF
- Monitor integrated power spectral density (log
scale) on longitudinal schottky at the end of a 6
sec stacking cycle as scraper extinguishes the
beam - Can determine extinction point to within 0.2 mm
by observing change in schottky power above noise
floor
7AP2 Debuncher Acceptance Momentum Acceptance
- Longitudinal Schottky profile ofps filling the
momentum aperture of the Debuncher. - Bunch rotation and stochastic cooling are off.
NOTE An earlier (11/2002) measurement gives
Dp/p 4.6
8AP2 Debuncher Acceptance -- Parameters
- AP2 Debuncher admittances reported at the
July 2003 review were - Horizontal 20 p mm-mrad, Vertical 12 p mm-mrad
Debuncher admittances reported at the July 2003
review were Horizontal 25 p mm-mrad,
Vertical 20 p mm-mrad
Design Goal is 40 p horizontal and vertical
admittance everywhere within a 2.00 momentum
acceptance
9AP2 Debuncher Acceptance -- Plan
- Identify Limiting Apertures
- Assemble Documentation and Drawings (FNAL Tech.
Div.) (WBS 26.2.2.1) - Optical Survey and Alignment (WBS 26.2.2.2)
- Beam based determination of limiting apertures
(WBS 26.2.2.9.2) - Improve AP2 and Debuncher Lattice models (WBS
26.2.2.8) - Required for Beam Based alignment
- Required for evaluation of chromatic errors
- Mitigate aperture restrictions
- Redesign/modify/rebuild/relocate beamline
elements (WBS 26.2.2.5) - Implement Beam Based Alignment
- Instrumentation upgrades (WBS 26.2.2.3)
- AP2 BPMs
- Debuncher BPMs
- Orbit control (WBS 26.2.2.6)
- Install additional dipole trims in AP2
- Motorized quad stands in the Debuncher
- Beam Based Alignment (WBS 26.2.2.4)
- Develop procedures
- Software development
10AP2 Debuncher Acceptance Beam Based Alignment
- Beam Based Alignment
- Excite quad ? Measure Response ? Correct Orbit
- We will be able to accomplish this because
- Most quads have shunts installed
- Upgraded BPMs in AP2 and the Debuncher
- Greatly increased orbit correction capability in
AP2 and the Debuncher
11AP2 Debuncher Acceptance Limiting Apertures
The numbers in this column were calculated
using b-functions at Dp/p 0
DRF3 was moved during the Fall 2003 shutdown
and is no longer an aperture restriction. Table
gives pre-move admittances.
12AP2 Debuncher Acceptance Status (1)
- Identification of limiting Apertures
- Documentation and Drawings
- Debuncher injection region drawing complete
- AP2 Physical Aperture table complete. Apertures
have been incorporated into the AP2 lattice
model. - Debuncher Physical Aperture table was recently
completed (still requires final error checking) - Optical Survey
- Tunnel work is 90 complete
- Survey data are being compiled
- Mitigate Aperture Restrictions
- Recent developments
- DRF3 move completed during the Fall 2003 shutdown
- Horizontal Debuncher aperture has improved from
25 p before the shutdown to present value of 28 p
13AP2 Debuncher Acceptance Status (2)
- Implement Beam Based Alignment
- Instrumentation
- AP2 BPMs
- Presently trying to mitigate Deb. Extraction
kicker noise - Est. Completion SD 2004
- DAQ hardware software upgrade Est.
completion Jan. 2005 - Debuncher BPM upgrade
- All 6 sectors installed and operational
- Console software is functional and in routine use
some improvements are still being made. - Orbit Control
- AP2 line trim dipoles
- 4 NDB dipole trims have been installed in the AP2
line 1 in Jan. 2002, 1 in June 2002, and 2 in
Jan. 2003. - Install moveable stands for selected Debuncher
quads. - 10 stands installed during the Fall 2003 shutdown
- Install an additional 20 stands during the Summer
2004 shutdown
14AP2 Debuncher Acceptance Status (3)
- AP2 and Debuncher Lattice modeling
- Working OptiM models of the AP2 line and the
Debuncher exist - AP2 model has been updated with physical aperture
information - Debuncher and AP2 models will be updated with
physical aperture and survey information as the
data becomes available - LBNL has developed a MAD model that includes
chromatic effects - Beam Studies
- Recently completed studies (Sept. 2003 Jan.
2004) - Reverse proton studies
- Observation of beam signal on all AP2 BPM cables
- Commissioned the new Debuncher BPM electronics
- Commissioned bumps with new moveable quads (in
progress) - Aperture measurements
- Stacking studies
- Measure AP2 Debuncher admittance
- (development of measurement techniques)
- Development of AP2 BBA using Debuncher TBT
- p bumps in AP2
15AP2 Debuncher Acceptance Chromatic Correction
- New Task added since July 2003
- Chromatic Correction of the AP2 Beamline
- Work being done by LBNL
- Model chromatic effects
- Beam studies to test model
- Propose correction scheme (August 2004)
AP2 line chromatic b-functions
16High Gradient Li Lens Goals Plan
- Goal Operate a Lithium lens --
- at a gradient of at least 1000 T/m (34 ?)
- for at least 10 million pulses
- Action Plan
- New solid Li Lens design (began 2000) (WBS
26.2.1.2) - General Li Lens RD (WBS 26.2.1.3)
- Autopsies of failed lenses
- FEA model of present design
- RD of various Lens technologies
- Improve present Li Lens design (WBS 26.2.1.1)
- Fabricate New Lenses (WBS 26.2.1.5)
17High Gradient Li Lens -- Parameters
18High Gradient Lithium Lens Present Li Lens
19High Gradient Lithium Lens New Design
- Features
- Diffusion bonded titanium body
- Improved cooling
- Li buffer volumes eliminated
- Diffusion Bonding
- Better, more uniform cooling of lens body
- Allows use of new Ti alloy (Ti 10V-2Fe-3Al has a
15 40 better fatigue endurance limit) - Simplified lens fabrication
- Elimination of weld joints on septum
20High Gradient Li Lens -- Status
- New Lens design (diffusion bonded lens)
- Complete and test new lens design prototype 1
- Presently on test stand
- Intend to pulse to failure
- Construction on prototype 2 expected to begin in
March 2004 - General Lens RD
- Lens 22 autopsy in process
- 2nd longest lived lens (9.2 million pulses). Did
not fail during pulsing. - Weld failure
- Continue to refine and expand FEA model
- Ti 10-2-3 testing in process
- Modifications to existing lens design
- Presently operating a lens constructed with
improved quality control procedures (Lens 28) - Original intention operate 28 for 1 month at 745
T/m then increase to 820 T/m. - Will not do because of too few operational spares
- Fabrication of new lenses
- Go into regular production of lenses with the new
design - Construction of lenses of new design scheduled to
start in early 2005
21Milestones
22Major Shutdown Work
- Shutdown 2004
- Replace D4Q4
- Wider Band 4 cooling arrays
- DRF2 Move
- Install additional 20 motorized quad stands
- Shutdown 2005
- Upgraded Debuncher Injection Septum
- Motorized stands for Debuncher injection
extraction kickers - Possible modifications to Debuncher extraction
kicker - Possible implementation of AP2 chromatic
correction - Shutdown 2006
- New Debuncher extraction kicker (if not modified
during SD2005) - Implement of AP2 chromatic correction (if not
implemented during SD 2005)
23Conclusion The Bottom Line
- Presentp yield
- 16?10-6p/POT
- Expectedp yield
- 36?10-6p/POT
- ? 52 ?1010p/hr
- Delivered to the Accumulator for stacking
- For
- 8?1012 POT/pulse
- (slip stacking)
- 2.0 sec cycle time