Title: Antiproton Acceptance
1Antiproton Acceptance
- Keith Gollwitzer
- Dept. of Energy Review
- March 30, 2005
2Outline
- Goal
- An admittance of AP2 and Debuncher in each plane
to be 35 ? mm-mrad - Accepting 320 ? mm-mrad beam emittance
- Transfer efficiently to Accumulator via D/A
- Mitigation
- Orbit Control
- Instrumentation
- Other Work
- Beam Studies
- Character of studies has changed from
predominately dedicated reverse proton studies to
mostly semi-parasitic stacking studies - Aperture Finding
3What Where - Mitigation
Extraction Kicker (SD2005)
Beam Stop (SD2004)
Move DRF2 (SD2004) and DRF3 (SD2003)
Injection Region (SD2004)
Shutdown
Open Debuncher Only Filled AP2Debuncher
Vertical Band 4 - Widen Array Gap (SD2005)
Italic underlined items discussed later
4Mitigation of Limiting Apertures Debuncher
Injection Area
- Debuncher Injection Area Modifications
- Injection septum common vacuum
- Replace D4Q4 SQC quadrupole with two LQB
quadrupoles - Motorize injection septum and kicker stands
- Vacuum system modifications
- Bigger D4Q4 vacuum chamber
- Move BPM to downstream of D4Q4
5Mitigation of Limiting Apertures Debuncher
Injection Area
6Mitigation of Limiting Apertures Debuncher
Injection Area
Added AP2 BPM just upstream of D4Q5
7Mitigation of Limiting Apertures Debuncher
Injection Area
D4Q4a
D4Q4b
Septum
8Mitigation of Limiting Apertures Debuncher
Injection Area
- Injection Septum Common Vacuum
9Mitigation of Limiting Apertures Debuncher
Injection Area
New
Old
Note Injected and circulating beam are
vertically separated.
10Mitigation of Limiting Apertures AP2 Beam Stop
- AP2 Beam Stop and Vacuum situation prior to 2004
Shutdown. Small vacuum leak at window next to
Beam Dump. Installed pair of windows between Q2
and Q3. Eventually, upstream end let up to air
(red section). Pair of vacuum windows at large ?
function multiple scattering.
Removed Q1 and Q2 to remove Beam Stop and
cantilevered beam tube from Steel Shielding. Took
opportunity to survey alignment of AP2 wrt to
pulsed magnet and map out the shielding
passage. Determined that Shielding forced
non-optimal alignment of Beam Pipe and Beam Stop
see slide. Moved Beam Stop downstream (pass
Q6) and installed a shorten beam pipe
cantilevered from Q1 see slide. Reduces
multiple scattering with removal of windows and
reducing path in air.
11Mitigation of Limiting Apertures AP2 Beam Stop
- Mis-alignment of AP2 beam stop beam pipe
mm
m
12Mitigation of Limiting Apertures AP2 Beam Stop
- Horizontal aperture after removal of AP2 beam
stop
mm
m
13Mitigation of Limiting Apertures AP2 Beam Stop
- Secondaries yield to downstream end of AP2 line
increased 10 as a consequence of the removal of
the AP2 beam stop. - Plans
- Plan to install new beam stop downstream of Q704
during the Fall 2005 shutdown.
14Yet to be Corrected Limiting Apertures
- Widen Vertical band 4 cooling arrays for pickup
and kicker - Upgrade arrays during 2005 shutdown
- Likely requires 8 week shutdown
- Debuncher extraction kicker Ceramic Pipe
module modifications - The upgrade will be installed during the 2005
shutdown. - Will also motorize extraction kicker stand
Injected Beam Profile
Current ceramic pipe
Downstream End
Upstream End
15Limiting Apertures
Not to be changed
The numbers in this column were calculated
using b-functions at Dp/p 0
Central orbit (?p/p 0) limiting apertures
Current Measurement Horizontal
36.0 ? mm-mrad 29.5 ? mm-mrad
Vertical 29.9 ? mm-mrad 24.9 ?
mm-mrad Combined effect of Band 4 Vertical and
Extr. Kicker upgrades is 7.4
(from particle tracking).
16What Where Orbit Control
DEX Bump Dipoles (SD2004)
2 Trim Dipoles (2002)
2 Trim Dipoles (2003)
Shunts (2001)
Shutdown
Motorized Stands 5 Quads (SD2000) 10 Quads
(SD2003) 20 Quads (SD2004)
Open Debuncher Only Filled AP2Debuncher
Now capable of bumping locally throughout the
Debuncher (all 3-bumps have been verified). Can
add additional AP2 trims as needed.
Italic underlined items discussed later
17Orbit Control Debuncher EXtraction Bump
- During reverse proton studies during 2004, we
achieved an admittance of greater than 35 ?
mm-mrad horizontally! - This was achieved with a closed orbit bump
through the extraction region horizontal
position bump at the Debuncher extraction septum. - However, not able to transfer efficiently to the
Accumulator via D/A beam line bumped to far away
from septum for extraction kicker. - This has led to adding a ramped Debuncher
EXtraction (DEX) bump.
18Orbit Control Debuncher EXtraction Bump
- Large Injected Beam
- Beam Cooled during cycle
- Rapidly ramp DEX bump at end of cycle to put beam
next to septum
Time in cycle
Extraction Channel of Septum
19Orbit Control Debuncher EXtraction Bump
- Status
- Two trim dipoles installed in Debuncher during
the Fall 2004 shutdown - All cables to the tunnel have been pulled
- Power supplies built by EE support
- Commissioning beam studies (March 2005)
- Ramps built and locality verified
- Implentation
20What Where - Instrumentation
Debuncher pbar TBT (2004)
Upgrade BPM system (Spring 2005)
Toroids (Spring 2005)
Debuncher Pbar Intensity Monitor (2005)
Shutdown
D/A Upgrade BPM system (Spring 2005)
D/A Toroid (Spring 2005)
Open Debuncher Only Filled AP2Debuncher
Upgraded BPM system Closed Orbit at 2.5MHz (2004)
Upgraded BPM system Closed Orbit at 53MHz (Summer
2005)
Accumulator pbar TBT (2005)
Italic items discussed later
21Instrumentation Recent and Ongoing
- Debuncher pbar Intensity Monitor see slide
- Ongoing modification of Debuncher BPMs for Closed
Orbit readout during stacking - AP2 and D/A BPMs see slide
- Deb. Extraction kicker noise issues resolved
- DAQ hardware software upgrade in progress
- Debuncher pbar Turn-By-Turn has been made more
robust - Accumulator pbar Turn-By-Turn has been built and
implemented see slide - Debuncher loss monitor system checked out and
calibrated during shutdown
22Instrumentation Debuncher Pbar Intensity Monitor
- Requires ramping DRF1 in the middle of the
stacking cycle and then ramp back down - Block diagram of temporary intensity monitor
- Working on modification to get pbar closed orbit
while stacking
23Instrumentation AP2 BPM Prototype Response
- Timelines have several types of slip-stacking
events (normal, switchyard NUMI) which cause
different AP2 orbits. - One can see the different timelines and the
number of each type of different slip-stacking
events. - Intensities in the Debuncher change with the
different slip-stacking events (not shown). - A target tune of an AP1 trim dipole was done and
the BPMs track. - BPM sum signals follow the established intensity
measurement in AP2.
24Instrumentation Accumulator Turn-By-Turn
Requires bunched beam at end of Debuncher
stacking cycle. There is no attempt to
phase/frequency match with ARF1. (ARF1 is the RF
system which is used for moving beam from
Accumulator injection to stacktail deposition
orbit.) Hence, stacking efficiency takes a hit
while closing the D2A line into the Accumulator.
Shown is a scan of the Debuncher Extraction
Septum and the TBT response for several settings
(right plot). The oscillations from a single
injection is also shown. Scales are arbitrary.
25Other Work
- Lattice Development
- Debuncher Lattice measurements have been
incorporated into model. - Updates and addition of more complete physical
aperture dimensions and locations - Survey
- Completion of optical/laser survey of AP1, AP2,
Debuncher D/A line performed during 2004
shutdown - Confirmed offset of V730 of AP2 and reset dipole
- D/A analysis completed and led to septa moves
- Cross checks of remaining data sets are being
done - AP2 Chromatic Studies
- Simulation studies of transport of beam from
target to circulating in Debuncher (LBNL)
26Beam Time
- Most of 2004 reverse protons
- Commissioning of Debuncher BPMs, motorized quad
stands and local bumps, Running Wave for
identifying aperture limitations see slides - Small gains made over several months
- Large gain Horizontally with bump at extraction
septum - However, kicker unable to compensate (essentially
no gain to stack rate) - Has led to ramped Debuncher Extraction (DEX) bump
earlier slides - Some work done with procedures and diagnostic
tests for reverse protons up AP2. - Since shutdown some reverse protons
- Commissioning of motorized quad stands and local
bumps (including DEX) - Recovery of admittance after shutdown
- Further tests of beam up AP2
- Since shutdown mostly semi-parasitic stacking
studies - Commissioning of instrumentation to see 108
pbars associated procedures - Component Centering see slides
- Bumping around the Debuncher see slides
27Aperture Finding Reverse Protons
- Running Wave
- Two trim dipoles playing sin and cos curves to
test for aperture limitations - Beam is heated in appropriate plane
- One period of curve is run to prep beam
- Inherent diffusion repopulates the beam edge
which is then scraped away by limiting
aperture(s) in successive periods of Running Wave
curve - Relies upon monitoring beam current and loss
monitors for each step of Running Wave curve - Made available fast updating beam current signal
- Loss monitors received full checkout and
calibration during 2004 shutdown
28Aperture Finding Reverse Protons
Beam Size (arb)
Phase Advance (arb)
Apertures Phase wrt to Running Wave
Beam Current (arb)
Running Wave Cartoon
Phase Advance (arb)
29Identification of limiting Apertures Reverse
Protons
- Aperture Finding Running Wave
30Aperture Finding - Stacking
- Semi-parasitic stacking studies
- Component Centering about beam
- Local Bumping Around Debuncher
- Centering and Bumping require
- Ability to determine pbar intensity in the
Debuncher earlier slide - Stability of upstream machines and/or offline
analysis to disentangle different slip-stacking
cycle effects - Patience to perform a bump since motorized quad
stands controls only allow moving a single stand
at a time - First component is changed make a 1-bump
- Second component is changed now have 2-bump
- Third component is changed closes to make a
local 3-bump - Can take several minutes to complete the bump
- Depending upon the number of motorized quad
stands in a bump, a scan can take 10 to 30
minutes to perform
31Identification of limiting Apertures Stacking
- Bumping around the Debuncher
- Center moveable devices on beam.
- Built high precision Debuncher intensity monitor
(DBPI10D). - Construct 3-bumps that cover the Debuncher (43
horiz. 42 vert. bumps) - During stacking, move each bump ?2 mm while
monitoring Debuncher intensity.
Measured during Stacking
32Summary
- Much work has been done in making tools and
procedures for Beam Based Alignment - Will continue-
- Rounds of local bumping in Debuncher
- Component centering about orbit after each round
of bumping - Completing DEX bump commissioning
- Commissioning AP2 and D2A BPM system
- Maximize Debuncher injection aperture via reverse
proton studies - Measure AP2 lattice
- Center orbit in AP2 using both reverse protons
and stacking secondaries