FLOW Assessment Systems Milestone Presentation May 7, 2002 - PowerPoint PPT Presentation

1 / 58
About This Presentation
Title:

FLOW Assessment Systems Milestone Presentation May 7, 2002

Description:

Data based on individual daily usage average of 74 gallons. 7. 8. Current Techniques ... Specially designed mini-hydroelectric turbine. Monitors water flow ... – PowerPoint PPT presentation

Number of Views:106
Avg rating:3.0/5.0
Slides: 59
Provided by: rhodak
Category:

less

Transcript and Presenter's Notes

Title: FLOW Assessment Systems Milestone Presentation May 7, 2002


1
FLOW Assessment Systems Milestone
Presentation May 7, 2002
  • Philip Beddow Adam Franzen Marcus Diehl
    Garth Gillespie Rhoda K.
    Farris Elizabeth Lighthart
  • http//www.cs.odu.edu/cpi/cpi-s2002/flow/

2
Outline
  • Societal Issue, Background, and Need
  • Proposed Solution
  • Goal and Objectives
  • Management Plan
  • Staffing and Resources Plan
  • Funding Plan
  • Marketing Plan
  • Evaluation Plan

3
Societal Problem
  • Continued population growth and finite water
    resources are leading to chronic fresh water
    shortages

3
4
Increasing Population
4
5
Water is Recycled
5
USGS, http//ga.water.usgs.gov/edu/watercyclegra
phic.html
6
Earths Water Supply
  • 326 quintillion gallons of water
  • 97 salt water
  • 2 in glaciers and ice caps
  • 1 usable fresh water

6
7
Consumption
7
8
8
9
Current Techniques
  • Mandates limiting water usage (i.e. New York)
  • Penalties
  • Difficult to enforce
  • 1992 Energy Policy and Conservation Act
  • Regulates all U.S. manufactured water fixtures
  • Toilets to 1.6 gallons per flush
  • Urinals to 1 gallon per flush
  • Shower heads and faucets to 2.5 gallons/minute

9
Source http//ec.chias.org
10
Savings with Conservation Techniques
10
Source http//ec.chias.org
11
Goal
  • Provide a means of educating homeowners about
    their water usage habitsand steps they can take
    to reduce the amount of water they are using

11
12
Objectives
  • Increase awareness of excessive water usage
    byproviding effortless monitoring of
    consumptionpatterns
  • Provide data to water conservation agencies
  • Supply advice on methods of decreasing water
    usage
  • Follow advice, save money

12
13
Projected Water Usage
13
14
Our Aim
14
15
SOLUTION
15
16
FLOW Assessment System
16
17
Product Goals
  • Introduce to market before stiffer mandates are
    imposed
  • Market to
  • Homeowners
  • Government agencies
  • Water conservation groups
  • Provide a quality product at a reasonable cost

17
18
Technical Approach
  • Three Components
  • Wireless Sensor
  • Central Storage Unit
  • User Interface

18
19
Product Layout
19
20
Wireless Sensor
  • Located at each water source
  • i.e. faucets, toilets, dishwashers
  • Specially designed mini-hydroelectric turbine
  • Monitors water flow
  • Transmits data to Central Storage Unit

20
21
Internal View of Wireless Sensor
21
22
Central Storage Unit
  • Collects data from all sensors
  • Uses standard interface (USB)
  • Stores and analyzes data
  • Flash RAM, database(s)

22
23
Internal View ofCentral Storage Unit
23
24
User Interface
  • View data on various output devices
  • Stand alone touch screen, personal computer, PDA
  • Numerous formats to display data
  • Utilize existing software, i.e. Excel
  • Water and monetary savings displayed
  • Optional Tips data displayed

24
25
Product Demonstration
  • http//www.cs.odu.edu/cpi/cpi-s2002/flow/

25
26
Project Phases
  • Three years divided into phases
  • Phase 0 Initial Plan and Research
  • Phase I Proof of Concept
  • Phase II Detailed Design Specifications
  • Phase III - Production of FAS

26
27
  • Proven management structure for Phase 0

27
28
Phase 0
  • Conduct Preliminary Research
  • January 2002 - May 2002
  • Develop Phase I Plan
  • February 2002
  • Deliver Feasibility Presentation
  • February 2002 - March 2002
  • Deliver Milestone Presentation
  • March 2002 - April 2002
  • Deliver Web Page Demonstration
  • April 2002
  • Deliver Approval Presentation
  • April 2002 - May 2002
  • Deliver SBIR Proposal
  • April 2002 - May 2002

28
29
Phase I Staffing Plan
  • FAS project members continue current roles
  • Hire entry-level professionals
  • Software Developer
  • Engineer

29
30
Phase I
  • Finalize Software Specifications
  • June 2002
  • Build Prototype
  • June 2002 - September 2002
  • Prototype Testing
  • September 2002 - November 2002
  • Funding Demonstration
  • November 2002 - December 2002

30
31
  • Staffing Plan for Phase I

31
32
Phase I Personnel
  • Project Manager (1)
  • Financial Analyst (1)
  • Contracts Manager (1)
  • Software Developer (1)
  • Engineer (1)
  • Documentation Specialist (1)
  • Part-time personnel

32
33
33
34
34
35
Includes BASIC stamp kit, stamp RF kit, electric
generator, turbine, Plexiglas, PVC piping, water
valve TOTALS Subtotal GA Total Contracts
35
36
Phase I Budget Summary
  • Total Phase I Budget 69,995
  • Personnel 43,029
  • Miscellaneous Resources 6,650
  • General and Administrative Costs 19,872
  • Internet Connection Fees 444

36
37
Phase I Evaluation Criteria
  • Scientific/technical merit and feasibility
  • Experience qualifications and facility
  • Effectiveness of proposed work plan
  • Commercial merit and feasibility

37
38
Phase II
  • Final Management Plan
  • January 2003 February 2003
  • Software Development
  • February 2003 February 2004
  • Hardware Development
  • February 2003 February 2004
  • Installation and Testing
  • March 2004 September 2004
  • Shift to Production Phase
  • September 2004 December 2004

38
39
Phase III
  • Production Plan
  • January 2004 July 2004
  • Testing
  • January 2004
  • Marketing Plan
  • January 2004 June 2004
  • Manual Documentation
  • January 2004 June 2004
  • Shift to Out-Years
  • June 2004 July 2004

39
40
  • Staffing Plan for Phases II and III

40
41
Phases II and III Personnel
  • Project Manager (1)
  • Software Developer (1)
  • Engineer (1)
  • Financial Analyst (1)
  • Contract Manager (1)
  • Marketing Director (1)
  • Documentation Specialist (1)
  • Lobbyist (1)
  • Part-time personnel

41
42
Contractual Aspects
  • Celestica
  • Support Phases II and III requirements
  • Software/hardware development and testing
  • Production of FAS
  • Alternate Contractors
  • NASO Corporation
  • Support Phases II and III requirements
  • Lockwood Greene
  • Support Phase III requirements

42
43
Resources/Budget
  • Three phases
  • Each phase tied to design review
  • Minimizes investor risk
  • Maximizes motivation to deliver

43
44
44
45
Includes BASIC stamp kit, stamp RF kit, electric
generator, turbine, Plexiglas, PVC piping, water
valve TOTALS Subtotal GA Total Contracts
45
46
Total Actual Cost includes 40 overhead to
cover all fringe benefits Annual Salary used
to compute hourly rate and monthly salary
Part-time schedule
46
47
Service provided by Cavalier Telephone
47
48
Budget Summary
  • Total budget 999,581
  • Phase I 69,995
  • Phase II 600,000
  • Phase III 329,586
  • Unit cost of FLOW Assessment System 995
  • May vary according to options purchased

48
49
Funding Plan
  • NASA
  • 70,000 for Phase I
  • 600,000 for Phase II
  • Phase III funding dependent on success of Phases
    I and II
  • Environmental Protection Agency (EPA)

49
50
Marketing Plan
  • Legislation
  • Government agencies
  • Initial focus on city and state
  • Conservation organizations
  • Housing contractors and homeowners
  • Initial target area New York City and
    surrounding counties and boroughs

50
51
Target Market
  • New York City and surrounding counties and
    boroughs
  • Total Population 12 million people
  • Median Income 39,369/household
  • Top 10 income per household ranking in U.S.
  • FAS unit cost 995

51
52
Target Market Breakdown
52
53
Return on Investment
Homeowners figures based on monthly sales of 850
units at 995 each with 100 per unit
profit Government agencies/conservation
organization figures based on monthly sales of
1000 units Combined Markets include
Homeowners, Government Agencies/Conservation
Organizations
53
54
Evaluation Methods
  • Program Design Review(s)
  • Monitors project during early stages of phases
  • Critical Design Review(s)
  • Performed during each phase
  • Closely tied to funding of future phases
  • Factory Acceptance Test (FAT)
  • Conducted on fully assembled system prior to
    delivery
  • Customer Acceptance Test (CAT)
  • Performed on fully assembled system
  • Conducted monthly for first year after production

54
55
Potential Risks
  • Lack of significant clientele
  • Competitors in the market

55
56
Conclusion
  • Flow Assessment Systems is a moderate cost
    information device that provides residential
    water consumption awareness
  • FAS is an innovative solution to reduce water
    consumption
  • Project is on schedule and will meet
    objectives and goals

56
57
FLOW Assessment Systems
57
58
Questions?
58