Title: Delivering a new hospital through PFI
1Delivering a new hospital through PFI
Steve Noon - University Hospitals Coventry
Warwickshire
2Presentation Overview
- Project Overview Timescale
- How PFI Contract has been Delivered
- Transition from Existing Hospital to PFI site
- Services Provided and by who
- How is Contract Managed
- The PFI Consortium
- UHCW
- Committees Sub Committees
- The Supporting Schedules
- Financial Main Points
- Learning points
- Conclusion
3Project Overview
- 360m new build University Hospital
- Includes providing Hard / Soft FM Equipment -
Rugby - Contract signed December 2002
- Joint Contract UHCW / Coventry PCT CRHC
- Physical
- Five storeys high
- ΒΌ mile in length
- 1200 beds
- Has 32 Operating Theatres
- Several retail outlets - Jewellers / Fashion/
Newsagent
4Project Overview (contd)
- Clinical Sciences Building
- 200 seat lecture theatre
- Training and meeting rooms
- Fully equipped mock operating theatre
- 600 Visitor car parking spaces 1200 staff
spaces (WIP) - New 200 unit doctors residence (still to be
built) - New Private Patient Hospital operated by BMI
5University Hospital (site Dec 2005)
6Main Entrance ( July 2006 )
7AE Entrance (July 2006)
8New Operating Theatre
9Outpatients Area
10Main Entrance
11Retail Area
12How was the PFI Contract Delivered
13How was PFI Contract Delivered
Business Case - OBC / FBC / Preferred Supplier
- Start mid 1990s - Signed approx 7
years later in Dec 2002 Construction - Started
immediately after contract signed with an end
date March 2007. Main hospital July06 Phased
opening of buildings - CRM Dec 2002 -
CNS Jan 2003 - Creche April 2003 - CSB
/ CSSD Dec 2003 - Main Hospital July 2006
- Landscaping / Car Parking March 2007
14Transition to PFI - Interim Services
- The contract provided for a period when the PFI
- Consortium managed the existing Hospital
services eg Catering, Cleaning, Maintenance
etc - During this period the Consortium were able to
- Assess the staff / Allocate jobs
- Shape the existing services before transfer
- Charge UHCW a management fee (TUPE staff)
- Work to UHCW budgets Pay Non pay
15Services provided in the contract
16Soft Facilities Management (ISS Mediclean)
- In scope
- Catering
- Porters
- Domestics
- Security
- Switchboard
- Linen laundry
- Car Park management
- Excluded Postage / General Office / Medical
Gases / Patient transport so some costs continue
17Hard Facilities Management (SRW)
- Maintenance of the site and buildings
- Energy Management
- Small Capital Works
- Waste Management
- Variations
18Certain Equipment Services (GE Medical Systems)
- Supply of the majority of medical and other
equipment - Maintenance of the larger and more expensive
equipment - Lifecycle of equipment ie replacement
- Excluded
- Maintenance of smaller equipment kept in house
19- How is the contract managed
20PFI Consortium
SRW
Hard Fm
UHCW
ISS
Soft Fm
Coventry Rugby Hospital Co
GEMS
Equipment
Cov PCT
Skanska
Construction
21UHCW Project Team
Project Director
Finance (3)
Admin/ Support (5)
Performance Monitoring (5)
Advisors Legal QS Finance (Bond)
Estates (2)
22Project Management
Project Liaison Meeting UHCW / Cov.PCT / Proj.Co
/ Skanska / ISS /SRW / GEMS
Project / Dev. Board UHCW/PCTs/SHA
Minutes / Actions
UHCW Proj.Team
Equip.Cttee
Fin.Mgmnt Group
Comm. Group
Jt.Design Const.
HR Group
Clinical Serv. Group
23Senior input
- Both the Strategic Health Authority / Private
Finance Unit (PFU) and - Department of Health Capital Investment Branch
have been - monitoring progress and have advised / input on
the following issues - Contractual Disputes
- Variations
- Amendments to the Deduction Mechanism as a result
of variations - Taken feedback to benefit other projects
24Other Parties in the contract
- In addition to those shown overleaf, the PFI
contract also has the following interested
parties - With UHCW
- Warwick University Medical School who occupy
Research Centre - Housing Association Medical Residences
- Coventry Rugby Hospital Co
- BMI Healthcare (Meriden Private hospital)
- Retail outlets
- Coventry Primary Care Trust PFI Partner for New
Mental Health Building
25- The PFI Contract Schedules
26Project Agreement (PA)
- The Project Agreement is the Umbrella contract
which - is supported by 41 more detailed Schedules
which cover various subjects matters - It is 130 pages long (although the Schedules
runs into thousands) - Deals with the main principles including
- Design Construction
- Quality Assurance
- Services
- Payment, Tax Financial Matters
- Changes in law
- Delay events
- Termination ie default or handback in 2042
27Schedules 41 in total
- The Schedules underpin the Project Agreement
stretch to 1000s of pages. Examples include - Schedule 1 Definitions Interpretations
- Schedule 8 - Construction matters
- Schedule 13 - Equipment
- Schedule 14 - PFI Services
- Schedule 18 - The Payment Mechanism
- Schedule 21 - Insurance
- Schedule 22 - Variation Procedure
- Schedule 24 - Handback Procedure
- Schedule 26 - Dispute Resolution
- Schedule 29 - Refinancing
- Schedule 36 - RoE based information
28Finance Main Points
29How has Project been Funded
- Source million
- Index Linked Bond 372 (92)
- Consortium Shareholder Funding 34 (
8) - Total Funding Required 406 (100)
- With additional Draw down facility within the
Bond for variations
Services
Unitary Charge
UHCW
Suppliers e.g. Skanska
Bond Finance
30Annual Cost
- The Unitary Payment ( up to Dec 2042 )
- at financial close was 47m pa
- Current Unitary Payment is 53m pa with the main
increases being - RPI Inflation (as applied to the majority of the
contract) - Soft FM (NHS pay awards) RoE staff
- Other NHS Pension increase (RoE) / Final
Employee List - Variations circa 25m with UP estimated increase
of 4m pa - Charges on top of the UP
- Energy ( for up to building efficiency cap)
- Pass Through Costs Telecoms / Hospitality /
Small Works - Volume Adjuster Catering / Linen / Waste
- Insurance Pain / Gain Share mechanism (annual)
- Demolition of Existing Hospital
31Annual Income
- Chiefly from dealings with BMI Healthcare
- Land Lease for Meriden Hospital
- Providing Medical Support Services
- Pathology
- Radiology
- Etc
- Share of BMI Annual Profits which is also
underwritten by Coventry Rugby Hospital Company
32Inadequate Performance
- Deductions are made voluntarily by Project Co for
inadequate performance (although UHCW has set up
a team currently to monitor performance and
liaise with both Soft and Hard FM providers) - Deductions classified as
- Quality Failures
- Unavailability
- Deductions calculated using
- The unitary payment as a basis
- Points system
- Weightings
33Learning Points
34What went well
- Construction ( delivered to time and on budget
) - The Programme
- Project Management Structure Committees work
well - Project Documentation Record
- Physical move well managed ( One year planning -
cost 1m) - Ring fenced technology update and estate
maintenance - Risk transfer to private sector
35What problems have we had
- Some of the schedules content is open to
interpretation. Disputes ( Car Parking ! ) - Long lead time resulted in many requests for
changes in design and equipment - NHS Project Team lack of retention / loss of
knowledge - Cost Improvements more restricted
36Conclusion
37Conclusion
- Chief Executive Comment
- PFI has given me / Coventry access to capital
that we would never have been given on this scale
to provide such tremendous state of the art
facilities - PFI captures the best of both Private and Public
Sector skills - Transfers risk to the private sector
- Ring fences maintenance and replacement of assets
that cannot be easily attacked for annual cost
savings - This contract is extremely complex but has
generally worked well