Title: PPP and PFI Delivery Through Partnerships
1PPP and PFI Delivery Through Partnerships
- Peter Livesey
- Senior Policy Analyst
- Corporate and Private Finance
2Drivers of PFI procurement
- PFI as off-balance sheet investment
- 1992 facilitating investment unaffordable in
the public sector - 1997 financing investment within previous
govts spending plans - Focus shifted to value for money, but legacy of
balance sheet treatment remains - PFI allocates risks to those that are in the
best position to manage them - Cost time overruns associated with conventional
procurement. - Key is whether cost of private finance over
gilts outweighs benefits in terms of bank
discipline, risk transfer and efficient
management.
3Project Delivery
Conventional Procurement
Projects over budget 73
Projects late 70
Source UK National Audit Office
4UK Procurement Policy
HM Treasury Corporate and Private Finance
Team Private Finance Unit
Future PPP approaches
Mandatory PFI Contract
PPP/PFI procurement policy
5PFI / PPP legislation in UK
- Not a lot has been needed there is no single
PFI Act - Specific modest steps have been needed to
facilitate PFI / PPP at the local level in the
NHS - E.g. Local Government (Contracts) Act 1997
- Beyond this existing UK law has been sufficient
for PFI / PPP contracts to go ahead. - To think about
- Does the Government have the power to enter
long-term agreements with the private sector - Are the underlying elements of PPP / PFI
contracts legal? E.g. exotic hedging instruments.
6PFI has been effective procurement tool
- 2006 was biggest year so far for the value of
deals signed - closure of a small number of big deals
- progress of projects initiated 2/3 years ago
- Key sectors of PFI investment
- Health - 8.3bn has delivered 64 operational
PFI hospitals - Education - 4.4bn covering 836 schools
- Defence - 5.6bn in 47 projects
- Transport - 4.9bn in 46 projects (not
including tube deals)
7PFI is a small part of total investment
- PFI has played a small role providing 10 15
of total investment - HMT ring-fences local authority PFI through
credit regime (incl schools), no separate control
for central govt (incl hospitals) - HMT sets qualitative and quantitative VFM tests,
standardised contract terms, provides scrutiny/
approvals, and sets policy/guidance on, for
example, workforce issues - Partnerships UK (45 HMT owned) provides project
specific support
8Project Delivery
PPP/PFI delivers benefits on time and on budget
Conventional Procurement PFI
Projects over budget 73 20
Projects late 70 24
Source UK National Audit Office
9Major Rail Project Channel Tunnel Rail Link
- A high speed rail link connecting the Channel
Tunnel to London, the CTRL was initially procured
in 1996 as a privately financed concession. - It has been restructured twice. HMG now
guarantees the entire 6bn financing and, as part
of the first restructuring, the project was split
into two. -
- CTRL Section 1 opened on time in Sept 2003 and
within budget. - CTRL Section 2 opened in 2007.
- Total cost about 6bn.
10MoD FSTA
Provides a modern, highly capable air-to-air
refuelling and passenger air transport capability
based on a fleet of new Airbus A330-200
aircraft. Cost effective, integrated, 27-year
service, covering provision of aircraft to
training and maintenance services, as well as new
infrastructure. Enters service in 2011. Key
parts of the aircraft will be manufactured in
the UK. Capital value c. 2.2bn Off balance
sheet.
Source MoD
11MoD Heavy Equipment Transporter
Signed December 2001 Term 20 years Full service
date July 2004 Capital value c65.0
million Annual unitary charge c15.1 million
(07/08) On balance sheet Objective Service to
move battle tanks and other heavy equipment
during peacetime and on operations. Sponsored
reserves make up one third of the manpower
required to deliver the service.
Source National Audit Office
12Advantages and disadvantages
- Conceptual advantages
- Integrated whole life management
- Risk transfer to private sector
- Design Risk
- Construction Risk
- Financing Risk
- Technology Obsolescence
- Operating and FM Risk
- Focus on output specification
- Opportunities for innovation in service delivery
- Long term certainty
- Private sector capital
- Can be off Government Balance Sheet
- Conceptual disadvantages
- Cost associated with risk transfer
- Price must include profit margin
- Inflexibility
13HMT assessment PFI benefits
- Captures private sector management expertise
- Incentivises whole life costing in provision of
serviced assets - Real risk transfer 90 projects completed on
time - Operational satisfaction levels are high 80 or
higher - HMT policy control increases contract discipline
and ensures projects are well scrutinised - PFI now a reasonably well understood procurement
model with a mature market
14Reducing congestion - M6 Toll Road
Only example in the UK All risks
transferred Power to set tolls with private
sector no restrictions 56 year
concession Refinanced 2006
15HMT assessment issues
- Perceived lack of flexibility
- Operational issues capacity to facilitate minor
service changes - Adaptability to meet high level policy changes
- Locks in public sector revenue spending on
servicing assets (but gives certainty) - PFI less suited to some areas lack of specified
outputs (e.g. IT), smaller projects - Private sector returns debt refinancing (action
taken to put in place gain share arrangements),
significant equity returns - Public sector skills PFI is complex making it a
challenge for public sector bodies to act as a
client. Procurement times too long average of
25 months in education, 38 months in health. - Additionality Risk that PFI is used for
additional / non-essential infrastructure
investment
16Where does value for money arise
- Whole life integrated service - design, build,
finance, maintenance, service - Innovative design
- cheaper construction cost
- cheaper whole - life maintenance
- Output specification
- services provided in different ways
- Possible third party income
- catering, nursery facilities, tolls
- Risk transfer
- More efficient utilisation of assets
17If on balance sheet, what happens to PFI?
- Projects in procurement continue to extent
departments have capital cover - Future pipeline likely to shrink, although where
programmes have momentum PFI may continue - Education programme Building Schools for the
Future given momentum, may continue - Waste programme gaining momentum and may
continue - Local authorities complexity means could cease
to use PFI for sectors such as housing and street
lighting - Health limited future pipeline.
- Defence limited to few very large projects
- Transport limited
18And PFI could evolve into a greater range of
models
-
- Debt underpinning (Woolwich extension, M25)
- Could reduce cost of borrowing by c. 50-70 basis
points - Risks undermining contractor discipline
- Flexible contract lengths e.g. contract
termination / asset transfer triggered at
threshold level of profit (Croydon Tram, Second
Severn) - May enhance refinancing gains
- Risk of undermining whole life costing /
innovation - Service concessions (M6 toll, Thames Gateway)
- Maintains / enhances discipline on partner (risk
transfer) - May undermine whole life costing
- Asset sales (BAA)
- High level of discipline on owner / total risk
transfer / whole life costing - Lose public sector control subject to regulation
- Will remain off balance sheet
More like PFI
Less like PFI
19Infrastructure Procurement Delivering long-term
value
- Sets out the next steps the Government is taking
to secure value for money in its procurement of
assets, infrastructure and long term service
provision - Sets out a range of alternative procurement
approaches, many of which stem from experience
with the Private Finance Initiative (PFI). - Outlines the key drivers in assessing value for
money when making decisions and encourages the
use of alternative procurement approaches where
they provide best value for money. - Provides assistance on where alternative
procurement approaches might be value for money
and encourages dialogue around these alternative
approaches. - Reaffirms the governments commitment to use PFI
where this provides best value for money,
regardless of accounting treatment.
20M25 Possible New Approaches
- Long construction period 8 years
- Large capital value 2bn
- Innovative financing could create savings
- Debt Underpin
- Up-front capital
- Milestone capital payments
- Debt Funding Competition
- Equity Funding Competition
21Current Margins on UK PPP Lending
Source Ernst Young