Title: Raccoon Lake Development
1Raccoon Lake Restoration Project
Task Force Meeting May 9, 2007
2Raccoon Lake Task Force Vision Statement and Goals
- The Vision of the Raccoon Lake Restoration Task
Force is to preserve our main water source as
well as develop and fully utilize a beautiful
natural asset that will create recreational
opportunities improving the quality of life of
the Greater Centralia Area as well as create
opportunities for quality housing development to
attract residents to the area.
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
3Raccoon Lake Task Force Vision Statement and Goals
- Goals of the Restoration Process
- Stabilize and Preserve our Primary Water Source
Reservoir - Create Opportunities for Greater Recreational
Usage including Skiing, Sailing, Boating and
Fishing - Improve and Protect the Environment for Aquatic
Life - Establish Quality Housing Opportunities
- Create New Opportunities for Private Investment
including Potential Marina, Enhanced Golf Course,
Restaurant and Convention/Conference Center
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
4Permits
- Applications to include 3 settling basins and a
sediment trap - Within approximately 6 weeks (July 1) we should
be submitting the permit applications to - US Army Corps of Engineers
- Illinois Environmental Protection Agency
- Within approximately 8 weeks (July 15) we should
be submitting the permit applications to - Illinois Department of Natural Resources- Office
of Water Resources
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
5Scope of Dredging
- The Lake needs 2.9 million cubic yards of volume
to restore to its original configuration - An additional 0.50 million cubic yards of volume
will be removed for the sediment trap - Shoreline restoration of 3,000 feet by
constructing seawalls
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
6Scope of Dredging Budget
- Dredging of Lake (Removal of 2.9 Million Cubic
Yards of Silt), Land Acquisition and Construction
of Settling Basins - 16,000,000 - Construction of Sediment Trap inside Lake -
2,000,000 - Shoreline Protection - 1,000,000
- Contingency - 1,000,000
- Total Project Cost of 20,000,000
- Based on 2003 study and subsequent comparisons
to Lake Decatur, Springfield Lake and Lake
Schaeffer (Indiana)
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
7Wetland Delineation
- Has been completed for the entire Lake and Lake
boundary - Has been completed for all 3 Settling Basins
- Using US Army Corps of Engineers ratios, we have
identified the areas of removal around the
perimeter of the Lake and the resultant
replacement areas - Staff, in conjunction with the Engineer, has
proposed a system of canals
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
8Wetland Delineation
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
9What Are We Looking At?
A. No-Till Field
B. Raccoon Lake in 50 Years if we Dont Dredge
C. 418 Camouflaged Snipers
D. Settling Basin
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
10(No Transcript)
11(No Transcript)
12Typical Settling Basin
- The basin was mowed in 3 years
- Began farming in about 8 years
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
13Settling Basin Locations
66 acres City-owned
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
40 acres Leased
80 acres Leased
14Settling Basin Locations
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
66 acres City-owned
15Settling Basin Locations
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
40 acres Lease
16Settling Basin Locations
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
80 acres Lease
17Settling Basin Locations
Phillips Property Zion Hill Road
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
18Settling Basin Locations
Williams Property Green Street
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
19I.E.P.A. 319 Grant
- Grant Amount was 2.5 million
- The submittal focused on 3,000 feet of shoreline
protection (800,000 and construction of the 3
sediment traps (1,750,000) - It was submitted in July 2006
- We were notified that we did not receive the
grant in January 2007 - Re-submittal is due this summer. Comments
received include special emphasis on upland Best
Management Practices (BMPs)
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
20Direct Appropriation
- Task Force has been working with Bill Houlihan of
Sen. Durbins office since 2005 - Funding Letter was submitted in December 2005
- All Direct Appropriations were postponed in 2006
- Where do we go from here? Suggestions?
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
21Recent Actions
- Developers Meeting
- August 1, 2006
- Available Properties for Development
- Time Line
- Incentives
- Bankers Meeting
- September 12, 2006
- New Lease Agreement
- Sale of Property
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
22Recent Actions
- Phase III Property Appraisals
- August 23, 2006 Zieba Appraisal Begins
Inspections - November 1, 2006 Zieba Appraisal Finishes
Inspections - January 8, 2007 Five properties Declared Surplus
for Bidding - February 12, 2007 Bids Opened
- March 12, 2007 DJ Howard Associates Begins
Inspections
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
23Water Quality/Supply
- 4 million gallons/day
- 2006 Gallons Produced 1,341,191,000
- Raw Water Line will add an additional 7 million
gallons/day - So, why do we need to dredge Raccoon Lake?
- Its simple Economics
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
24Water Quality/Supply
- We live in a world with unlimited wants and
limited natural/ economic resources - You can never have too much water
- Raccoon Lake has lost 30 of its storage capacity
in the last 60 years
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
25Recreational Use
- Hiking/Biking Trail
- Marinas
- Motorized Watercraft
- Campgrounds
- Public Beach
- Fishing
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
26Campground/ Nature Park
Marina
Public Beach
City-wide Recreational Trail
Our Vision
27Development
- Projection for Next 10 Years
- 40-50 New Homes
- Vineyard, Bait/Boat Shop, Restaurant, Marina,
Nursing Home, Retail Strip
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
190 Developable Acres
28(No Transcript)
29Leases
- 195 total Leases
- 38 New Versions of the Lease have been Signed
Since 2006 - Current Lease Revenue
- 103,155 Annually
- 75,000 to General Fund for Maintenance (Mowing,
Point Park, Patrol) - 28,000 to Road Improvements
- Adjust Maximum 50 in 2010
- 154,732 Annually
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
30Tax Analysis
- Revenue Sources
- Property Tax (Residential and Commercial
Properties) - Sale of Undeveloped Land
- State Shared Revenue Based on Population
- Income Tax (71 per person)
- Use Tax (11 per person)
- Motor Fuel Tax (28 per person)
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
31Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
Assumes 50 new homes by year 10 Vineyard in year
2 Restaurant in year 4 Marina in year 5 Nursing
Home (small) in year 7 Bait/Boat shop in year
9 Retail Strip (3 unit) in year 10
32Continue Leasing or Sell Leases?
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision
33Questions?
Vision Statement Permitting Process Design
Phase Settling Basin Locations Typical Settling
Basin Funding Update Recent Actions Vision