Title: Project in Eagle Alaska
1Project in Eagle Alaska
- 2008 Alaska Federation of Natives
- Convention
- October 2008
- Anchorage, Alaska
- Presentation by
- Alaska Power Telephone
2Yukon River Hydrokinetic Turbine Project
- Project Overview
- Hydrokinetic Turbine Project Timeline
- APT began studying the feasibility of low-head
hydro generation in the late 90s - Collaborating with UEK Corp. APT decided to
proceed with developing plans for installing a
small hydrokinetic station in Eagle - Today with a grant from the State of Alaska
Denali Commission we are involved in engineering
and design activities. - The four year project will determine the
viability of the turbine and associated
technologies for operation in rural arctic Alaska
- Short Term engineering construction - first
two years - Mid Term - operation and monitoring 2-3 yrs
following commissioning - Long Term - after completion of the project and
into the future
3- The City of Eagle Alaska, located on the Yukon
River. The city is east of Fairbanks near the
Canadian border. APT provides electricity and
telephone services to the residents of the city
and to Eagle Village a tribal community located
upriver. The maximum electrical load in Eagle
varies seasonally with the maximum load occurring
in the winter at about 150 kW.
4Aerial photo of the City of Eagle and the
location of major project features. Note the boat
launch which will be used to deploy the turbine
equipment. The turbine location is approximately
2500 feet downstream of the boat launch. You can
also see in the photo the tour boat Yukon Queen
docked just upriver of the boat launch.
5The turbine will be deployed from the boat launch
using a truck mounted winch. It will be guided
into position with workboats and fastened to its
mooring lines. The power cable will be connected
to the turbine and laid across the river bottom
to shore where it will be buried and routed to
the converter station. This converter station
location was chosen primarily for its proximity
to the utilities 3 phase power transmission lines
that run overhead along the adjacent road.
6This is a view of the boat launch area to the
left you see the city and to the right you see
Belle Island. The turbine equipment will be
assembled adjacent to the boat launch and
deployed into the river using a truck mounted
winch stationed at the boat launch and workboats
on the river to guide the equipment into
position.
7TerraSond workboat with crew performing river
survey activities. Site specific surveys were
performed to more accurately determine the best
project approach and provide a means to correlate
USGS survey data of the Yukon river at Eagle to
the project
8(No Transcript)
9(No Transcript)
10In addition to the bathymetry and velocity
surveys TerraSond also performed a acoustic sub
bottom surveys and took material samples from the
bottom to provide data for the mooring anchor
engineering.
11Yukon River Hydrokinetic Turbine Project
- Evolution of the turbine design
- Original Ideas
- Bottom mounted and or kited turbine.
- Flight technology promised to allow turbine to
operate at the best point in the water column but
technology was in early stage of development - Could operate all year long located in the river
below the ice but maintenance and evaluation
would be very difficult and would require removal
prior to ice break-up to prevent potential loss - Low velocities near the bottom were used to
calculate energy production which turned out to
be very low - Todays Plans
- Barge mounted turbine.
- Highest velocities found near the surface of the
river - Turbine easily accessible for maintenance and
evaluation.
12The Yukon River at the time of break-up in
spring. The scrapping of the ice can be very
destructive and there will be no permanent
project structures located in the river. The
turbine and power cable will be removed prior to
ice forming in late fall.
13Sketch of current plan to deploy the turbine. The
turbine will be supported from a pontoon barge on
the surface of the river. A buoy will be deployed
in front of the barge to help deflect larger
debris and to train the mooring cable at the
proper depth to the turbine barge.
14Sketch of barge with the turbine deployed. Note
trash screen to protect the turbine from river
borne debris. The turbine can be raised with
hoists to allow service and inspection from the
deck of the barge.
15(No Transcript)
16(No Transcript)