Eagle Hydrokinetic Turbine Project - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

Eagle Hydrokinetic Turbine Project

Description:

AP&T began studying the feasibility of low-head' hydro generation in the late '90's ... Navigable waters marking buoy and signals ... – PowerPoint PPT presentation

Number of Views:303
Avg rating:3.0/5.0
Slides: 47
Provided by: benjami79
Category:

less

Transcript and Presenter's Notes

Title: Eagle Hydrokinetic Turbine Project


1
Eagle Hydrokinetic Turbine Project
  • Alaska Tidal Energy Conference
  • January 2007
  • Presentation by
  • Alaska Power Telephone

2
(No Transcript)
3
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Hydrokinetic Turbine Project Timeline
  • APT began studying the feasibility of low-head
    hydro generation in the late 90s
  • Collaborating with UEK Corp. APT decided to
    proceed with developing plans for installing a
    small hydrokinetic station in Eagle
  • Today we are ready to proceed with formal
    engineering and design activities and move
    forward with the project
  • The four year project will determine the
    viability of the turbine and associated
    technologies for operation in rural arctic Alaska
  • Short Term engineering construction - first
    year
  • Mid Term - operation and monitoring - 3 yrs
    following commissioning
  • Long Term - after completion of the project and
    into the future

4
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Short Term Goals for the Hydrokinetic Turbine
    Project
  • Perform surveys of the project site
  • River - profiling, velocity, ice
  • Soils - boring,
  • Determine turbine location
  • Determine construction methods
  • Purchase or lease land for onshore facilities
  • Complete engineering design
  • Proceed with manufacturing
  • Proceed with construction and installation
  • Commission

5
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Three Year Goals for the Hydrokinetic Turbine
    Project
  • Operate
  • Test and monitor
  • Determine the reliability in arctic conditions
  • Determine best practices for deployment,
    operation and maintenance
  • Determine environmental impact
  • Determine performance
  • Determine OM costs

6
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Long Term Goals for the Hydrokinetic Turbine
    Generator
  • Installation of second turbine generator unit in
    Eagle
  • Output from two units would replace diesel
    generation
  • Diesels would be maintained for standby and
    emergency use
  • Reduction in rates to the consumers
  • Reduction in emissions and associated
    environmental impacts
  • Increase the sustainability for the rural Alaska
    communities
  • Possible installation of similar units in other
    locations

7
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • City of Eagle
  • Located on the north terminus of the Taylor
    Highway
  • About 6 miles west of the Alaska-Canada border
  • Due east of Fairbanks about 190 miles
  • At about 64.79 north latitude and -141.20 west
    longitude
  • At about 850 feet above sea level
  • Eagle Village is located about 3 miles upriver
    from the City of Eagle
  • Transportation into Eagle
  • State owned airstrip with commercial flights from
    Fairbanks
  • Float plane, during the summer months only
  • River boat, operating in the summer months only
  • Taylor Highway, open in the summer months only

8
Eagle Hydrokinetic Turbine Project
  • .

9
Eagle Hydrokinetic Turbine Project
  • .

Eagle at the End of Summer (Viewed from Belle
Island)
10
Eagle Hydrokinetic Turbine Project
  • .

Eagle in the Winter (Viewed from River)
11
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Brief History of the City of Eagle
  • The area is the historical home of the Han
    Kutchin Indians
  • The original settlement was established in 1874
    as a trading station supplying miners working the
    upper Yukon
  • The City of Eagle was founded in 1897
  • Population of over 1700 by 1898
  • US Army Fort Egbert established in 1900
  • First incorporated city in the interior 1901
  • Telegraph service from Eagle to Valdez in 1903
  • Population declined to lt200 by 1910
  • Fort Egbert abandoned in 1911

12
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Eagle Today
  • Population in Eagle is about 140 and in Eagle
    Village about 80
  • Subsistence activities are part of the lifestyle
  • Local economy includes
  • Retail businesses, seasonal
  • School
  • Utilities
  • Mining
  • Tourism, seasonal
  • River boat trip from Eagle to Dawson
  • Lodging and restaurants

13
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Electricity Generation in Eagle Today
  • APT serves about 190 customers in the two
    communities providing electricity and
    communication services
  • The electrical system is isolated
  • Powerhouse located in Eagle
  • Load varies daily according to the season from a
    summer low of 70kW to a winter high of 150kW
  • The prime movers for the existing generators are
    diesel engines
  • Annual fuel consumption is about 57,000 gallons
  • Engine life is 3 - 4 years (25,000 hours)
  • Annual generation maintenance costs about 40,000
    (w/o labor)

14
Eagle Hydrokinetic Turbine Project
  • APT Generation Goals
  • Renewable Energy
  • APT has for the for last two decades sought
    technologies to augment their diesel generation
    with renewable energy resources
  • Today APT supplies its customers with about 70
    of the generation from renewable energy resources
  • In the southeast APT has designed, built and put
    into service several hydroelectric power stations
  • For the companies interior utilities conventional
    hydroelectric facilities are not practical as
    such the application of other renewable energy
    resources is being studied including
  • Hydrokinetic turbine generation
  • Wind turbine generation

15
Eagle Hydrokinetic Turbine Project
  • Hydrokinetic Opportunity
  • Yukon River at Eagle
  • Eagle is located on the west bank of the Yukon
    River
  • The river divides at Eagle around Belle Island
  • The hydrokinetic turbine will be located just
    beyond the entrance to the west channel
  • Turbine location will be optimized for depth and
    water velocity

16
Eagle Hydrokinetic Turbine Project
  • .

17
Eagle Hydrokinetic Turbine Project
  • Hydrokinetic Opportunity
  • Yukon River at Eagle
  • The channel width in this area varies seasonally
    between 900 and 1,000 feet
  • Channel maximum depth in the winter is about 18
    feet including 4 feet of ice
  • The river water level changes 10 to 12 feet
    between winter and summer
  • Water temperature varies from just above freezing
    to about 60F
  • Water visibility varies from several feet in the
    winter to near zero in the summer
  • Water velocity in the winter is about 7.3 ft/sec

18
Eagle Hydrokinetic Turbine Project
  • Hydrokinetic Opportunity
  • Yukon River at Eagle Ice
  • River normally begins to freeze in October
  • River surface is frozen solid with ice normally
    about 4 feet thick
  • Ice thickness can reach up to 8 feet
  • Thinner ice in the area of the moving water
  • Frazil ice under the solid ice, thickness of
    frazil layer unknown
  • Ice break-up normally occurs in April and the
    river is clear by May
  • Ice break-up can be destructive with ice flow
    scouring the river bottom and edges removing
    several feet of earth

19
Eagle Hydrokinetic Turbine Project
  • .

Yukon River Winter Time (Belle Island in the
Distance)
20
Eagle Hydrokinetic Turbine Project
  • .

Ice Jamb Viewing Upstream from Eagle
21
Eagle Hydrokinetic Turbine Project
  • .

Ice Jamb Viewing Downstream from Eagle
22
Eagle Hydrokinetic Turbine Project
  • Project Overview
  • Major Project Features
  • Turbine
  • Converter Station
  • Directional Bore
  • Cable
  • Anchorage
  • Turbine Deployment Recovery

23
Eagle Hydrokinetic Turbine Project
  • Turbine
  • UEK System

24
Eagle Hydrokinetic Turbine Project
  • Turbine
  • UEK Corporation
  • Design and manufacturing performed since 1981 in
    Annapolis, Maryland USA
  • Builders of river and tidal current turbines
    featuring ducted design enhanced with a flared
    discharge (Augmentor Ring)
  • Current Activities
  • Turbine model testing at LEcole Polytechnic
    Federal de Lausanne (EPFL) laboratory in
    Switzerland
  • Turbine demonstration project in the Winnipeg
    River in collaboration with the University of
    Manitoba and Hydro Manitoba
  • Turbine supply for the Chitokoloki Mission
    Hospital in Zambia, Africa to replace diesel
    generation unit similar to Eagle turbine -
    installed in the Zambezi River delivery end of
    2007

25
Eagle Hydrokinetic Turbine Project
  • Turbine
  • Eagle Specifications
  • 8 foot diameter UEK System twin-rotor design
  • 100kW with a 5 knot flow
  • Counter-rotating turbine runners
  • Turbine assembly integrated into reinforced skid
    with flotation tanks to raise and lower the unit
    in the river
  • Turbine protected with heavy duty ice deflecting
    cage
  • 3Ø, AC generator with DC output from integrated
    rectifier
  • DC connection to shore station
  • DC-AC conversion at shore station

26
Eagle Hydrokinetic Turbine Project
UEK System View of Intake
27
Eagle Hydrokinetic Turbine Project
UEK System View of Discharge
28
Eagle Hydrokinetic Turbine Project
UEK System Section View
29
Eagle Hydrokinetic Turbine Project
  • Turbine Platform

30
Eagle Hydrokinetic Turbine Project
  • Turbine Installation Views

31
Eagle Hydrokinetic Turbine Project
  • Turbine Anchoring Details

32
Eagle Hydrokinetic Turbine Project
  • Turbine Directional Boring Details

33
Eagle Hydrokinetic Turbine Project
  • Converter Station
  • Utility Interconnection
  • Shore based facility located on land leased from
    the city
  • Station will be housed in a modified container
    equipped with
  • AC-DC variable speed converters similar to
    Magnetek Type PCS
  • 50 kW stackable modules
  • 600 750 VDC input x 480 VAC, 3Ø, 60 Hz output
  • Main switchgear with generator and feeder circuit
    breakers
  • Monitoring and control equipment
  • Communication equipment
  • Station service equipment
  • Air compressor for pumping air to turbine floats
  • Nitrogen gas system for pressurizing the
    generator housing
  • Step-up transformer and isolating switches for
    connection to utility power grid at 7,200 VAC
    (outdoor pole mounted)

34
Eagle Hydrokinetic Turbine Project
  • Directional Bore
  • Cable Connection to Generator
  • One bore sized for future additional turbine set
    or two bores
  • Option I
  • Bore from converter station to turbine anchorage
  • Approximately 800 feet long
  • Deep penetration from station elevation to below
    river almost 110 feet
  • Most expensive
  • Option II
  • Bore from intermediate location at elevation
    nearer the river surface
  • Shorter and shallower
  • Longer overall cable distance
  • Requires additional cable junction facility and
    trenching or overheading to converter station
  • Modifiers
  • Location of turbine in river, distance from shore

35
Eagle Hydrokinetic Turbine Project
  • .

36
Eagle Hydrokinetic Turbine Project
  • Cable
  • Cable Assembly
  • Cable length from 1,000 to 1,500 feet long
  • For the project the cable will be a loomed
    assembly of
  • DC power cable
  • Monitoring cable, multi-conductor and/or fiber
    optic
  • Nitrogen gas hose
  • Air hose
  • Insulated and armored electrical/ fiber optic
    conductors
  • Factory integrated cable possible for future
    projects
  • Watertight submersion rated connectors at turbine
  • Clamped to anchor cable for support

37
Eagle Hydrokinetic Turbine Project
  • Anchorage
  • Turbine Anchors
  • Single or multiple anchors for each turbine
  • Located 180 to 200 feet upstream of turbine
  • Anchor types being considered
  • Deadweight type, concrete/steel
  • Micropiles, bored and grouted
  • Multiple galvanized steel anchor cables

38
Eagle Hydrokinetic Turbine Project
  • Deployment and Recovery
  • Turbine Installation Removal
  • Turbine launched from public boat ramp 2,500
    feet upstream
  • Winch cable released under brake until turbine
    reaches anchor float
  • Turbine guided into position by small powered
    boat
  • Turbine attached to anchor cable and released
    from winch cable
  • Cable and hoses connected
  • Air released from float tanks to allow turbine to
    sink to bottom
  • Removal performed with the opposite process
  • Normal maintenance will include visual inspection
    and debris removal requiring only that the
    turbine be raised to the surface
  • Annual maintenance will require that the turbine
    be removed

39
Eagle Hydrokinetic Turbine Project
  • .

40
Eagle Hydrokinetic Turbine Project
  • Permitting and Regulatory Requirements
  • Permitting Agencies
  • US Army Corps of Engineers
  • Moorage Permit
  • State of Alaska Department of Natural Resources
  • Office of Habitat Management and Permitting
  • Fish Habitat Permit
  • Division of Mining, Land and Water
  • Private Non-Exclusive Right-of-Way Permit

41
Eagle Hydrokinetic Turbine Project
  • Permitting and Regulatory Requirements
  • Reviewing Agencies
  • US Department of Fish Wildlife Service
  • Alaska Department of Fish and Game
  • National Marine Fisheries Service
  • Other jurisdictional local, state, and federal
    agencies

42
Eagle Hydrokinetic Turbine Project
  • Permitting and Regulatory Requirements
  • Moorage Permit Requirements
  • Moored facility submerged approximately 20 below
    the surface of the river.
  • Historic and archeological remains -
    archeological monitor onsite.
  • Navigable waters marking buoy and signals
  • Approval of US Fish and Wildlife Service and
    Alaska Department of Fish And Game
  • Monitoring Plan
  • Possible fish injury from turbine operation
  • Pressure changes caused by blade action
  • Heat generation of unit and possible changes in
    surrounding water temperatures
  • Physical, biological, and behavioral impacts to
    different sizes of fish

43
Eagle Hydrokinetic Turbine Project
  • Permitting and Regulatory Requirements
  • Moorage Permit Requirements, cont.
  • Initial testing timed to avoid upstream migration
    of adult fish and downstream smolt migration.
  • Inclusion of mitigation measures such as screens
    or flutterboards, restrictions on operating
    times, and blade speed limits if required.
  • Onshore facilities shall have minimal impact to
    riparian vegetation.

44
Eagle Hydrokinetic Turbine Project
  • Permitting and Regulatory Requirements
  • Fish Habitat Permit Requirements
  • Construction and installation plan submittal and
    approval
  • Turbine pressure drop test results and possible
    field testing to confirm that pressure drop
    across turbine is lt2.7 psi.
  • Underwater monitoring plan to videographically
    document
  • Avoidance behavior of upstream migrant salmon
  • Presence or absence of main stem Chinook salmon
    spawning redds

45
Eagle Hydrokinetic Turbine Project
  • Permitting and Regulatory Requirements
  • Right-of-Way Permit Requirements
  • General construction requirements
  • Conduct studies to determine effect of the
    turbine on salmon as requested by the National
    Marine Fisheries Service.

46
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com