Title: LOKTAK ESTIMATE COMMITTEE
1PRESENTATION
On
Comments on Discussion paper on Terms and
conditions of tariff (Tariff period
commencing from 01.04.2004)
by
National Hydroelectric Power Corporation Ltd.
( A Govt. of India Enterprise)Sector
33, Faridabad (Haryana),
INDIA
2Presentation of NHPC
on Discussion paper on Terms
Conditions of Tariff effective from 01.04.2004
- As per the Electricity Act 2003 under Section 61,
CERC shall be guided by the National Electricity
Policy and Tariff Policy for the purpose of
specifying the terms and conditions for
determination of tariff. - Government of India has still not finalised the
National Electricity Policy and Tariff Policy. - It is perhaps in this context too early to
deliberate on the concept paper. - In view of the above it is felt that
existing terms and conditions should continue for
a further period of 3 years.
2
3Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Issues relevant to transmission and wheeling of
electricity (Para 2.3.3)
- The transmission and wheeling services should not
be provided free. - The methodology proposed in para 2.3.3.4 for
sharing of transmission / wheeling charges seems
to be reasonable. - NHPC is of the opinion that the transmission /
wheeling charges should be payable only by the
importing utility and should not be shared /
borne by the exporting utility / generator
because of the prevailing gap between demand and
supply.
3
4Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Interest on Loan (Para 3.1.2.(i))
- Interest on loan should be continued to be
provided separately on actual basis as per
existing system. - Besides, if short terms loans are raised to pay
earlier term loans (if Depreciation Advance
Against Depreciation is not enough to provide
funds for repayment of loans), then interest
should be paid on these short term loans also.
4
5Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Rate of return (Para 3.2)
The rate of return should be return on equity
rather than the return on capital employed (ROCE)
for the following reasons-
- Debt equity ratio is varying and has not yet
stabilized to the proposed preferable level of
8020. - Clear basis for the determining the interest on
debt portion is not available. - Miscellaneous provision (0.5 proposed by the
CERC) to cover the cost of FERV, income tax, fuel
charges etc. is on adhoc basis and not based on
any study.
5
6Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd.
Rate of return (Para 3.2)
- Foreign exchange rate variation (FERV) depends on
many national / international issues and any
miscellaneous provision in ROCE to take care of
FERV will be on adhoc basis and not based on any
study. - PLR is changing and has not yet stabilised and
therefore ROCE approach will need revision on
year to year basis and keeping it fixed for
tariff period will be incorrect. - Abnormal variation of PLR carries the risk and
adhoc figure of 5 variation in PLR for
re-setting the tariff in that particular year, is
also not reasonable / based on any study.
6
7Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd.
Rate of return (Para 3.2)
- The return on equity is more dependant on
mobilizing extra resources for Hydropower
development and therefore the present concept of
return on equity should continue. - The rate of return in Hydro Sector should be more
as compared to others for attracting more
investments in this sector. - The present system of 16 return on equity i.e.
post tax return of 16 p.a. should at least
continue.
7
8Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Rate Base (Para 3.3)
- Determination of rate base in case of return on
equity (ROE) is simple and easy and is the equity
base whereas in case of ROCE determination of
rate base is more complicated and cumbersome. - Depending upon the balance sheet for the rate
base is not appropriate due to the following
reasons
- Capital cost is provisional and may be inclusive
of certain provisions for payment to the
contractors. - Certain payments are required to be made to the
contractor on the basis of the arbitration award
etc. which are known only at the later date and
are not included in the capital cost.
8
9Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd.
Rate Base (Para 3.3)
- In many cases, only essential systems and
services, immediately required for operation of
the stations are completed upto COD. Certain
works remain pending and hence are not reflected
in the capital cost.
- Tariff should have provision for revision due to
above expenditures. At present the revision of
tariff is not allowed if expenditure upto 20 of
capital cost is incurred during the tariff
period. - This ceiling limit on capital expenditure should
be removed.
9
10Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
FERV Payment (Para 3.3.6.5)
- In case of NHPC, FERV was initially being paid as
per option - (i) Given in Discussed paper which
was subsequently changed to option No. (ii) /
(iii) as per CERC orders. - The financial implications on tariff arising on
account of change in the methodology for working
out FERV should be computed for any project from
the commercial operation date (COD) and any under
or over payment should be adjusted in that
particular year in which the change in
methodology is proposed. - The existing rate base is on Gross Fixed Assets
(GFA) concept and same should be continued.
10
11Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd.
FERV Payment (Para 3.3.6.5)
- The existing system should continue.
- However, consequent upon introduction of revised
AS-11 effective from 01.04.2004, the ERV on
repayment of principle amount are to be charged
to PL account instead of adjustment in carrying
cost of relevant fixed assets as per existing
AS-11. - The revised AS11 needs to be taken into
consideration in order to avoid any confusion on
the issue of ERV.
11
12Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Interest on working capital (Para 3.4)
- The miscellaneous provision of 0.5 to take care
of income tax proposed in the discussion paper is
not based on any study and the amount of income
tax varies from year to year and is not constant
and therefore could not be considered as 0.5 for
this purpose. - The existing system to continue with maintenance
spares taken as 1 of capital cost in case of new
projects. - Maintenance spares should be taken on the basis
of five years average consumption in case of old
projects.
12
13Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd.
Operation and Maintenance cost (Para 3.5)
- The present method of working out the OM cost
i.e. normative for new projects and average
expenses duly escalated, for the old projects, is
reasonable. - The normative OM expenses for old projects based
on historical cost of project would not be
correct and would be insufficient keeping in view
the high material, employees cost etc. - The normative OM expenses on the basis of option
B given in paper (Para 3.5.9) is not reasonable
because the Hydro projects are tailor made and
any two projects of same capacity (MW) are not
identical as far as OM expenses are concerned. - The OM expenses depend on the location of dam,
weir, powerhouse, employees colony, topography
and other related matters.
13
14Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd
Operation and Maintenance cost (Para 3.5)
- The discussion paper proposes that in case of
Hydro stations, the benchmark values may have to
be specified for the following categories of
stations (Para 3.5.14).
- Purely run of the river stations.
- Run of the river with pondage type of stations.
- Storage type of stations.
14
15Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd
Operation and Maintenance cost (Para 3.5)
NHPC feels that the bench mark value is not
dependant on the type of stations as far as the
OM expenses are concerned but is dependant upon
the following factors-
- Lay out of the project.
- Location of the dam, plant, powerhouse etc.
- Location of the employees colonies.
- Topography of the area.
- Remoteness of the project.
- Law and order situation.
- Silt content in the water.
- Restriction imposed on the project design on
account of international water treaty, if any.
15
16Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd
Operation and Maintenance cost (Para 3.5)
- However, it is proposed that in case of new
projects the OM expenses should be taken as 2.5
of the capital cost. The escalation factor of
10 should be adopted for older projects because
escalation in employees cost has always been much
higher than the increase in escalation factor.
16
17Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Depreciation (Para 3.6)
- The amount of depreciation should cover the
amount of repayment of loan during the year.
17
18Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Operational Norms (Para 3.7.2)
Pricing of secondary energy
- The rate of secondary energy should not be less
than the rate of primary energy because then only
the generator will be incentivised to generate
additional secondary energy. - At the same time the beneficiary has not to pay
the capacity charges on this secondary energy,
therefore, this is always cheaper than primary
energy for him.
18
19Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Incentives for Hydro Stations (Para 3.8.2)
- Incentive Actual Peak Time Generation x
Incentive Rate (Rs. / Kwh) x (CIA CIN) / 100 - The above formula proposed in the discussion
paper takes into account the actual peak time
generation which is related to the actual
capacity index and therefore having the factor of
actual capacity index along with the actual peak
time generation does not seem to be justified. - It is necessary that the peak hours are properly
defined. - The proposed formula should be made applicable to
the storage type and peaking type stations only - For the run of river stations, the existing
formula for incentive should continue.
19
20Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Development Surcharge (Para 3.9)
- The funds required for capacity addition are not
to be mixed with the amount of depreciation and
hence it should be separately dealt. - The total amount of depreciation recovered
through tariff is limited to 90 of the cost of
the project and by increasing the rate of
depreciation the total amount of depreciation
does not increase. Therefore, the additional
fund should be made available over and above the
depreciation amount by way of development
surcharge for capacity addition.
20
21Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd
Development Surcharge (Para 3.9)
- Development surcharge collected from the sale of
power by the generators should be utilised only
for development of hydro sector, for improving
hydro - thermal mix required for security and
stability of the grid. - The existing system to continue and there should
be freedom with utility for deployment of
development surcharge fund in rated securities
available in market. No rebate should be given
on development surcharge amount. However late
payment surcharge is to be levied.
21
22Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Tariff Period (Para 4.1)
- NHPC feels that tariff period should be 5
years.
22
23Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Regional Tariff (Para 4.2)
- Since the quality of end product i.e. power does
not depend upon the project, from where it is
generated, therefore NHPC feels that tariff
should be only on regional basis for a generator.
23
24Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Peak and off peak tariff in Bulk Generation (Para
4.3)
- Peak and off-peak tariff should be introduced .
- Peak tariff should not be more than double the
off peak tariff.
24
25Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Declared Capacity (Para 4.4)
- The amount for extra generation due to over -
loading of machines should be over and above the
Annual Fixed Charges (AFC) paid to the generator.
- Declared capability of the generator should be
exclusive of over-loading capacity of the machine
because declared capability is on continuous
basis whereas over-loading of machine will depend
upon various technical parameters / limits
prescribed by the manufacturer.
25
26Presentation of NHPC on Discussion paper on
Terms Conditions of Tariff effective from
01.04.2004
Contd.
Additional Issues
The following additional issues may be considered
- The monthly capacity charges to be recovered
should be proportionate to the design energy of
that particular month and not in 12 monthly equal
installments. - The unscheduled interchange (UI) rate needs to be
reviewed as this rate was fixed somewhere in
1997-98.
26
27THANKS
27