RAILTRACK - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

RAILTRACK

Description:

... solvent on 5 October. No financial meltdown whatsoever we were trading profitably and cash ... Huge 1.4bn investment over 4x pre-tax profits enabled ... – PowerPoint PPT presentation

Number of Views:128
Avg rating:3.0/5.0
Slides: 21
Provided by: annemarie2
Category:

less

Transcript and Presenter's Notes

Title: RAILTRACK


1
RAILTRACK
  • Interim Results for the six months ended 30
    September 2001

2
Key Results Issues
  • Business WAS clearly solvent on 5 October
  • No financial meltdown whatsoever we were
    trading profitably and cash outflow was
    favourable to budget
  • Huge 1.4bn investment over 4x pre-tax profits
    enabled by access to financial markets which is
    no longer available
  • Network operational performance was moving in the
    right direction

Government must address the implications of
forcing Railtrack into insolvency
2
3
Key Financials
2001
2000
Operating profit m Profit before tax m Earnings
per share Interim dividend
197 175 36.8p 9.75p
333 292 48.8p -
69 67 33 -
6 months ended 30 Sept
3
4
Key Ratios
30 Sept 2001
30 Sept 2000
Net debt m Equity Shareholders funds m Gearing
Adjusted interest cover
2,186 3,213 68 4.9x
4,551 2,933 155 3.8x
Debt Equity Operating profit interest
before capitalisation
4
5
Operational Delivery
  • Railtrack attributable train delays down 52 on
    the previous 6 months (back to pre-Hatfield
    levels)
  • Broken rails down 12 compared to first half
    2000/01 (down 36 over two years)
  • TSRs down 39 to 696
  • Average track quality at highest level since 1994
  • TPWS commissioning doubled HMRI target succeeded

5
6
Infrastructure delays were trending to
pre-Hatfield levels but performance payments
under Schedule 8 totalled over 200m
6
7
Record 1.4bn Investment
  • Renewals up 29
  • Enhancements up 35
  • CTRL on time and budget

7
8
Average Track Quality 1994 - 2001
points difference from line standard
1994/5
1995/6
1996/7
1997/8
1998/9
1999/00
2000/01
2001/02
8
9
Investment Record 1995-2002
  • Net debt up 4bn to finance investment
  • 1996-2001 Invested 2bn over Regulators
    allowance
  • Rail infrastructure spend GDP 82-95 UK0.12,
    Europe0.25

m
Forecast
9
10
TPWS commissioning rates have doubled
Per Quarter
  • HMRI targets met for the last 3 quarters
  • Paddington completed, 3 weeks ahead of target.

10
11
Way Ahead for Railtrack Group
  • Separate Group and PLC
  • Work closely with shareholder groups
  • Prepare for robust legal challenge
  • Secure value of Group cash, CTRL franchise and
    property
  • Intense scrutiny of Administrators stewardship
    of value and proposed transfer process

Value maximisation of Group assets will be
vigorously pursued for as long as it takes
11
12
Railtrack Group PLC
  • Appendix

12
13
So why didnt you oppose the order?
  • Secretary of States action precipitated material
    adverse change
  • No additional government support (4bn funding
    gap)
  • Reneged on Renewco transaction (worth 1.3 bn by
    2003)
  • Disabled Regulators right to credibly intervene
  • Allowed Government intent to be leaked to media

13
14
Implications of Secretary of States Action
  • Ability to draw down on our 1bn plus of bank
    lines destroyed
  • Unequivocal QC advice - trading whilst insolvent,
    bankers would foreclose and railway could cease
    operating

FACT Railtrack (and its successor) can only
exist with underlying if not explicit, Government
support that was taken away
14
15
What would Plan B have looked like?
  • Announcement that discussions with Government had
    not delivered a solution
  • Update on timetable for addressing the funding
    gap
  • WCRM status and options provisionally agreed for
    review with Government
  • Plan to access bond markets in Spring
    Discussions with Banks were underway
  • Timetable for ORR interim review possibly
    accelerated, depending on Renewco status

15
16
What would Plan B have looked like?
  • Review of five year spending commitments
    especially 2004-6 in advance of ORR review
    decision (to increase covenant headroom)
  • Trigger cost reduction plans and zonal
    restructuring to build credibility and deliver
    efficiencies

16
17
Channel Tunnel Rail Link Phase 1
  • Railtrack Groups ownership confirmed in
    principle
  • Committed to buy rights to infrastructure assets
    of Section 1 at cost of construction - 1.7bn
  • Lease over Section 1 until July 2086

17
18
Channel Tunnel Rail Link Phase 1
  • Building of route 85 complete
  • Railwork 75 complete
  • 192m (135m) spent in first six months
  • 3.2km tunnel under North Downs completed
  • 1.2km bridge over River Medway completed

18
19
Five year business plan spend Renewals,
Maintenance Opex, excl West Coast
17.1
14.5
13.3
12.9
32 20 41
bn
Controlperiod 1
ORRDetermination
August costsubmission
Businessplan
changeon controlperiod 1
Control period 2
bn 00/01 prices
19
20
CP2 value gap vs ORR allowance
3.6bn
Recoverable
Hatfield Direct 0.6 Hatfield Indirect 0.9 Safety 0
.5 2.0 RAB Adjustments 0.6
2.6bn
Efficiency challenge
Average250m p.a 2002/6
1.0bn
Excluding - 0.2bn efficiencies announced
April 2 - 0.5bn performance gap -
un-remunerated West Coast spend
20
Write a Comment
User Comments (0)
About PowerShow.com