Moma Project
AGM Presentation July 25, 2005
2
Progress Headlines
  • 28.5 complete against contractual 23.2
  • Present forecast is for completion in 25.5 months
    (contract 27 months)
  • Monthly progress rate increased by 50 in June
  • Majority of big-ticket items ordered

3
Health and Safety
  • Over 600,000 man-hours achieved without LTI
  • Permanent Safety Officer on site
  • Extensive HS policies in place

4
Main Areas of Project(Roaster)
  • A magnetising roast is required to enhance the
    separation of hi-chrome and low-chrome ilmenite
    and to enhance TiO2 content
  • Roaster design completed and order placed in May
    for delivery in late 2006

5
Main Areas of Project(Civils)
  • Aggregate crushing screening complete
  • Bulk earthworks 90 complete
  • Civils 10 complete, first concrete poured
    end-June

6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
Main Areas of Project(Camp)
  • JV has used Kenmares camp until the permanent
    village was erected.
  • Erection of village is underway.

16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
19
(No Transcript)
20
Main Areas of Project(Freight)
  • Main shipping contract with Rohlig. Beach
    landings sub-contracted to Comarco.
  • First barge left Bunbury 1st June, second barge
    left 13 days later.
  • Remainder of equipment to be transported in
    conventional ships brought to site on smaller
    barges.

21
(No Transcript)
22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
Main Areas of Project(Dredges)
  • Two 1800 kVA suction-cutter dredges ordered from
    IHC (Holland) in February.
  • Construction on schedule. Keels were laid in
    May.
  • Delivery in Q1 2006.

26
Main Areas of Project(Barge)
  • Design of Bronagh J complete and orders will be
    placed this month

27
(No Transcript)
28
(No Transcript)
29
Main Areas of Project(Jetty)
  • A 350m long jetty will be built to facilitate
    transfer of 1000 t/h product onto the barge and
    to receive fuel
  • Agreement signed for jetty construction

30
Main Areas of Project(Electrics and Transmission
Line)
  • Bush cleared along entire 170 km route
  • 20 pylon bases completed
  • Resettlement and crop compensation programme
    completed
  • Power will be available from February 06

31
Environment
  • No incidents or breaches have occurred.
  • All reporting requirements on schedule. The
    baseline monitoring programme has begun.
  • Local liaison working well.
  • HIV/AIDS programme on schedule.

32
(No Transcript)
33
(No Transcript)
34
Operational Aspects
  • Recruitment underway for mining manager and mine
    planner to boost operations team.
  • Organograms revised and recruitment schedule
    completed.
  • Fuel supply contract being negotiated.

35
Summary
  • Project ahead of schedule
  • Majority of large items on order
  • Logistical problems being overcome
  • 200 currently on site, set to peak at 400
  • First production anticipated final quarter 2006