Title: Buckley MILCON Program


1
Buckley MILCON Program
Lt Col James P. Zemotel 460 CES/CC 18 Sep 2008
2
Overview
  • Awarded and Pending MILCON Status
  • MILCON in Design
  • Projects submitted for FY10-15 FYDP

3
Awarded MILCON Status
  • Add/Alter Communications
  • Leadership Development Center
  • Construct VQ/TLF
  • Consolidated Fuels
  • Youth Center
  • BRAC 310 SFS Facility

4
Add/Alter Communication
  • Cost 10.6 M
  • Scope 45,988 SF
  • What this MILCON did Constructed a facility to
    provide communications support for new facilities
    being added to Buckley AFB. The facility will
    provide space for administration, information
    management, expanded telephone operations,
    additional telephone maintenance,
    telecommunications equipment, the network control
    center, technical control center, and an
    information assurance center.
  • Complete Apr 2008, Comm. awaiting furnishings
    to fully occupy

5
Leadership Development Center
  • Cost 5.95 M
  • Scope 16,900 SF
  • What this MILCON did Constructed a facility for
    large gatherings up to 450 personnel. Provides
    video teleconferencing capabilities for up to 40
    people and a catering kitchen to support meal
    service in conjunction with meetings and official
    functions is included.
  • Complete Aug 2008 Ribbon Cutting on 4 Sep

6
Construct VQ/TLF
  • Cost 30 M
  • Scope 109,000 SF
  • What this MILCON does This project will provide
    a combined 120 unit Visitor Quarters and 30 unit
    Temporary Lodging Facility. The facility will
    eliminate costs incurred by billeting TDY
    personnel and recent PCS movers in local lodging
    facilities.
  • Completion Date Mar 2009
  • Currently 35 Complete

7
Consolidated Fuels Facility
  • Scope 420,000 gallon JP-8 storage tanks, 2000
    SF Operations Building, Mobile Gas Storage tanks.
  • What this MILCON does Replace the inadequate
    and out of Compliance JP-8 and Mobile Gas fuels
    areas that are currently located next to the CDC
    and Family Housing. Relocates the Fuels into one
    complex next to the Flight line.
  • Estimated Completion Date Aug 2009 (16 Constr
    Complete)

8
Youth Center
  • Cost 7.8M
  • Scope 32,193 SF
  • What this MILCON does Current Youth Center
    Program has been asked to vacate their present
    location. Basic bid provides space for Youth
    Programs, conveniently located near Buckley
    Family Housing.
  • Completion Date TBD Awaiting final redesign
    and award

9
FY07 BRAC 310th SFS
  • Cost 2.3M
  • Scope 9,375 SF
  • What this BRAC MILCON does Relocates portion of
    310th mission from NAS New Orleans. There
  • are no other facilities on BAFB to house
  • their SFS mission.
  • Awarded Aug 08

10
MILCON Projects Under Design
  • FY08
  • Freight Transfer Facility Scope 10,000 SF/4
    M 85 Designed
  • BRAC Base Infrastructure - Scope 10 M 100
    Designed
  • FY09
  • Fam Camp (NAF) - Scope 38 Camp sites, 2.5 M
    100 Designed
  • BRAC ARPC Scope 98,400 SF / 25 M
  • BRAC AFR Training Facility Scope 28,500 SF /
    7.2 M
  • Medical MILCON Buckley Satellite Pharmacy -
    Scope 5,700 SF / 3M

11
FY 09 Projects Under Design
  • NAF Family Campground - 100 Designed
  • Scope 38 RV Camping Spaces, 2.5M
  • Est. Award Oct 09

12
FY 09 Projects Under Design
  • 310 ARPC BRAC - 15 Designed
  • Scope 98,400 SF/ 25 M
  • Award TBD

Most recent design change to ARPC
  • AFR Training Fac - 65 Designed
  • Scope 98,400 SF/ 25 M
  • Award TBD

ARPC CPSF
13
Medical MILCON
  • FY09 Buckley Satellite Pharmacy - 95 Designed
  • Scope 5,712 SF / 3M
  • Final Design Sep 2008
  • Award Est. Dec 2008

14
MILCON for FY10-15 FYDP
  • Security Forces Operations Facility, 35,800 SF /
    12.36M
  • Logistics Readiness Center, 35,000 SF / 12.72M
  • Education Center/Library, 26,600 SF / 11.7M
  • Joint Vehicle Maintenance Facility, 37,800 SF /
    17.12M

15
Security Forces Operations Facility
  • Project Cost 12.36 M
  • Scope 35,768 SF (3,323 SM)
  • Project Status
  • Submitted for FY10 FYDP
  • What the Project Does
  • Construct a new Security Forces Operations
    Facility to include central security control, law
    enforcement, resource protection, personnel
    security, information security, and training.
    The new facility is to be moved further away from
    the Priority Level 1 resource.

Disjointed operation in 3 separate facilities
with temporary use of building 950 in clear
zone and scheduled for demolition.
16
Logistics Readiness Complex
  • Project Cost 12.72 M
  • Scope 34,650 SF
  • Project Status
  • Currently in future FYDP
  • What the Project Does
  • Constructs a Logistics Readiness Center to
    house the Traffic Management Office (TMO), cargo
    movements, supply warehouse, a Sensitive
    Compartmented Information Facility (SCIF),
    deployment operations, and mobility bag and
    weapons storage. This facility supports
    logistics, readiness, and deployment operations
    and the deployment of over 500 personnel as part
    of the Wings' Air Expeditionary Force.

Disjointed operation in 3 separate facilities
with temporary use of building 950 in clear
zone and scheduled for demolition.
17
Education Center/Library
  • Project Cost 11.7 M
  • Scope 26,605 SF (2,193 SM)
  • Project Status
  • Currently in FY13 FYDP
  • What the Project Does
  • Houses education functions for academic and
    professional military education for active duty,
    national guard and reserve military and DoD
    civilians. Includes PME, FTAC, ALS, Lecture/
    Training Classrooms, and Off-Duty/Continuing
    Education/College-Degree Programs. It will also
    include space for administrative requirements of
    these programs and the base library. The mutual
    requirements of all of these programs are lecture
    classrooms and an auditorium each with Video
    Tele-conferencing and Video Tele-training
    capability.

18
Vehicle Maintenance Facility
  • Project Cost 17.12 M
  • Scope 37,716 SF (3,504 SM)
  • Project Status
  • Submitted for future FYDP
  • What the Project Does
  • Constructs a Vehicle Maintenance Facility (VMF)
    for assigned vehicles to receive routine,
    periodic and emergency maintenance and repairs.
    The existing VMF is undersized to meet the
    demands of active duty and tenant needs. The VMF
    will also house the administration and management
    functions for vehicle operations to include
    customer reception, private offices and storage.

Disjointed operation in 3 separate facilities
with temporary use of building 950 in clear
zone and scheduled for demolition.
19
Summary
Questions?