Title: Quality AssuranceQuality Control Plan Evaluation
1Quality Assurance/Quality Control Plan Evaluation
February 16, 2005
2A time of change
- A/E Oversight Guidelines.
- This defining of roles and responsibilities
paints a clearer picture of the responsibilities
and relationships within CFL and consultants. - With these guidelines in place it is now time to
review the other components of the processes that
contribute to the delivery of projects.
3Why Do You Plan for Quality?
- If you dont know where youre going, any road
will take you there - Louis Carroll
4Responsibility for Quality
- Recognition of A/E industry capabilities
- Acceptance that quality is the A/Es
responsibility - Both parties
- CFLHDs roles is QA
5Follow Through on Quality
- The best written quality plan is no better than
the worst, if it is not followed through. - Take the time to provide the appropriate level of
quality control. - Reduced levels of QC may be justified, but they
must be communicated and agreed to.
6Reasons for Evaluation
- CFLHD accepted the existing QA/QC plans on the
merits of each firm. - Now that the existing QA/QC plans have been in
practice for a while, CFLHD will be evaluating
them to develop a basis for providing QA/QC
program improvement recommendations modification
of scopes of work to address deficiencies and to
identify weakness areas for monitoring.
7How Evaluation was Developed
- Key elements of a comprehensive highway QA/QC
plan were identified - The evaluation criteria was selected by
researching quality practices of State DOTs and
consultants.
8Goals of Evaluation
- Provide CFLHD with a clear understanding of the
QA/QC processes and procedures that are in place
to control the quality of the work. - Identify improvement opportunities.
- And
9Goals of Evaluation
- Verify that the mechanisms that control quality
are in place so the product meets the
expectations of the team. - Client Agencies
- CFLHD and
- A/E
10Evaluation Criteria
- The current organizational QA/QC plans will be
evaluated, using 25 evaluation criteria, for the
inclusion of the elements necessary to promote
the thorough review and checking of all
documents. - Implementation of QA/QC is not intended to lead
to unnecessarily complex and expensive systems
but only to formalize and record the good
management practices that have usually been
practiced in the past.
11(No Transcript)
12(No Transcript)
13(No Transcript)
14Involvement of Project Management in QA/QC
- Project managers have to be active participants
in the quality of deliverables. - Verification that scope and design are in
agreement.
15Development of a Project Quality Plan
- Scope of each review.
- Allocation of resources and areas of
responsibility. - Analysis of risks and design decisions.
- First step in assuring that best practices and
sound engineering judgment is used. - Quality assurance of subconsultants.
- Reference quality procedures to be used.
- Modification of PQP.
16Subconsultant Quality Assurance and Quality
Control
- Subconsultants have acceptable QA/QC plans.
- QA activity to ensure that work is balanced
between project constraints, good engineering
judgment, and it reflects the appropriate level
of risk. - Subconsultant are tasked to provide activities
for back checking the technical recommendations
against the project deliverables to assure that
the technical recommendations reflect the
evolution of the project.
17Quality Assurance Certificate of Compliance
- A certificate of compliance is to be submitted
for ALL deliverables.
18Use of Checklists and QA/QC Control Documents
- Use documents at the appropriate stages of
development. - Submit the completed checklists with each of the
deliverables.
19Sealing and Signing of Documents
- Engineering drawing
- Cross-Sections
- Specifications
- Engineering reports and formal technical
memorandums - Construction staking reports
- All other technical recommendations or
deliverables
20Final Closeout and Evaluation
- Document problems encountered
- Areas for improvement
- Mistakes and lessons learned
- Outstanding features
- Corrective action plan
21Next Step in the Process
- An audit report for each of the current QA/QC
plans will be developed. - The reports will be distributed.
- Meeting to discuss the results will be scheduled,
as necessary, to address findings.
22Questions