Title: Chapter 6 Chip Seals
1Chapter 6Chip Seals
- From Maintenance Technical
- Advisory Guide (MTAG)
2Managers Overview
- From Maintenance Technical
- Advisory Guide (MTAG)
3Introduction to Chip Seal
- What is Chip Seal?
- Why use Chip Seal?
- When to use Chip Seal?
- Where to use Chip Seal?
- Chip Seal Variations
4What Is Chip Seal
Application of asphalt binder on existing
pavement followed by a layer of aggregate chips.
The treatment is then rolled to embed the
aggregate into the binder.
5Performance and Cost-Why to Use
- Performance
- Proper application of binder and aggregate
- Proper embedment
- Typical treatment life 4 to 7 years
- Average cost
- 0.96/m2 to 1.32/m2 (0.80 to 1.10/yd2)
6Where and When to Use
- Surface for light to medium traffic
- Waterproof layer
- Skid resistant surface
- Restore weathered surface
- Address bleeding
- Temporary base course cover
- Define shoulders
7When NOT to Use!
- Structurally deficient pavements
- Cracks gt6 mm (0.25 in) wide
- Medium- to high-severity alligator cracking
- Large number of potholes
- Rutting gt25 mm (1 in)
- Very rough surface
8Keys for Success
CHIP SEALS
- Proper surface preparation
- Use the right emulsion and clean aggregates
- Determine the appropriate spread rates for the
emulsion and the aggregate - Follow the construction specs, including the need
for traffic control - Chip seal in good weather conditions
9 Binder Application
Sweeping (before and after)
Aggregate Application
Rolling
10Proper Application
11Loose Chips
Bleeding
Streaking
12Chip Seal Variations
- Single chip seals
- Double or triple chip seals
- Cape Seals
- Sand seals
- Fabric and chip seals
13Chip Seal VariationsSingle Chip Seals
Existing Pavement
14Chip Seal VariationsDouble Chip Seals
Existing Pavement
15Chip Seal VariationsCape Seals
Brooming
Existing Pavement
16Chip Seal VariationsSand Seals
Existing Pavement
17Chip Seal VariationsFabric and Chip Seals
Existing Pavement
18Chip Seal VariationsFabric and Chip Seals
19Chip Seal CourseTraining Modules Available
- Design, Materials Specifications
- Construction, QC Trouble Shootings
20End OverviewBegin Project Design, Materials
Specifications
21Design, Materials Specifications
Module 6-1
- From Maintenance Technical
- Advisory Guide (MTAG)
22Topics to be covered
- Chip Seal Design Process
- Design Considerations -Quantity Selection
- Chip Seal Design Methods
- Material Selection Binder and Aggregate
23Chip Seal Design Process
- Assess existing pavement
- Select chip seal variation
- Select compatible binder and aggregate
- Quantity selection
24Design ConsiderationsQuantity Selection
- Residual asphalt content
- Asphalt cement factor 1.0
- Emulsion factors range 0.55 to 0.65
- Aggregate application rate
- Single chip layer
- No more than 10 excess chips
- 70 embedment recommended
25Chip Seal Design Methods
- McLeod procedure
- Asphalt Institute method
26Asphalt Institute Method
- Determine aggregate size and specific gravity
- Aggregate and asphalt emulsion quantities from
table - Adjust aggregate (if necessary)
- Adjust asphalt content based on condition of road
(if necessary)
27WorkshopChip Seal Design Problem
- Break into groups
- Work design problem in Participants Workbook
- Present findings to class
28Material SelectionBinder
2-4.28
29Material SelectionBinder
- Rapid setting emulsions
- Polymer-modified emulsions
- Asphalt cement
- Rubberized asphalt
30Material SelectionEmulsion Ingredients
- Asphalt
- Water
- Emulsifying agent (surfactant)
31Material SelectionEmulsion Classification
- Electrical charge ( or )
- Speed of break slow (SS), medium (MS), and rapid
set (RS) - Asphalt relative viscosity hard (h) or soft
(s) - Polymer-modified asphalt (P or L)
- High float (HF)
32Material SelectionEmulsion Classification
33Material SelectionRubberized Asphalt Chip Seal
2-4.33
34Hot Rubber Chip Seals
- Binder Material
- Field Blended using hot asphalt, extender oil and
crumb rubber. - Oil application is usually .60 gal / square yard
through an agitated distributor truck attached
with a vapor recovery system. - Aggregate Chip
- Chips are always hot pre-coated, and applied at
35-40 lbs. per square yard
35(No Transcript)
36Asphalt Rubber Chip Seal
37Polymer Modified Chip Seals
- Binder
- Terminal Blended using hot asphalt, polymer and
can use crumb rubber. - Application rate is 0.35 - 0.50 gals/sy
depending on size of chip - Chips
- Chips can be 3/8 up to 1/2 (25-35 lbs. / sy)
- Chips can also be pre-coated but not required
38(No Transcript)
39Polymer Modified Emulsion Chip Seals
Crack Seal before PM Emulsion Seal
40PM Emulsion Rejuvenating Chip Seals
- Binder
- Polymer modified emulsion with a solvent free
rejuvenating agent additive - Application rate is 0.25 - 0.40 gals/sy
depending on size of chip and degree of cracking. - Chips
- Chips can be 1/4 up to 1/2 (18-35 lbs. / sy)
- Can be applied at temperatures down to 40o F
- Crack filling is not required
41Material SelectionAggregates
- Clean and durable
- One size 6 to 16 mm (0.25 to 0.6 in)
- Cubical shape
- Flat and elongated particles limited to 25 to 30
percent - Fines limited to 1 to 2 percent
42Material SelectionProblem With Flat Aggregates
Existing Pavement
43End Project Design, Materials
SpecificationsBegin Construction, QC, and
Trouble Shooting
44Construction and Inspection
Module 6-2
- From Maintenance Technical
- Advisory Guide (MTAG)
45Topics to be covered
- Construction Procedures
- Quality Control
- Inspection
- Troubleshooting
46Construction
2-4.46
47ConstructionConventional Chip Seal Procedure
- Clean existing pavement
- Apply binder
- Spread aggregate
- Roll
- Allow binder to cure
- Broom loose aggregate
48ConstructionCleaning Existing Pavement
49ConstructionStart and Stop Application on Mat
50ConstructionBinder Application
51ConstructionBinder Overlap
Spray Bar and Nozzles
Single Overlap
Roadway Surface
52ConstructionBinder Application Overlap
53ConstructionBinder Application
54ConstructionAggregate Application
55ConstructionAggregate Application
56ConstructionRolling
- Immediate rolling of aggregate
- Pneumatic-tired rollers
- No fewer than three passes
- Full coverage necessary before asphalt hardening
57ConstructionRolling
58ConstructionRolling
59ConstructionCuring of Binder
- Time depends on temperature and relative humidity
- Emulsion break should begin just after first
roller pass - Open to traffic in about 2 hours
60ConstructionBrooming Loose Aggregate
61Quality ControlPreliminary Responsibilities
- Project review
- Document review
- Material checks
62Quality ControlPre-Application Inspection
- Surface preparation
- Equipment inspection
- Asphalt distributor
- Chip spreader
- Haul trucks
- Rollers
- Brooms
63Quality ControlPre-Application Inspection
(continued)
- Weather requirements
- Determining application rates
- Checking application rates
- Traffic control plan and setup
64Quality ControlProject Inspection
- Asphalt application
- Aggregate application
- Truck operation
- Rolling
- Longitudinal joints
- Transverse joints
- Brooming
65Quality ControlPost-Application Inspection
- Cleanup
- Opening to traffic
66Quality ControlPreliminary Responsibilities
- Project review
- Document review
- Material checks
67Quality ControlPre-Application Inspection
- Surface preparation
- Equipment inspection
- Asphalt distributor
- Chip spreader
- Haul trucks
- Rollers
- Brooms
68Quality ControlPre-Application Inspection
(continued)
- Weather requirements
- Determining application rates
- Checking application rates
- Traffic control plan and setup
69Quality ControlProject Inspection
- Asphalt application
- Aggregate application
- Truck operation
- Rolling
- Longitudinal joints
- Transverse joints
- Brooming
70Quality ControlPost-Application Inspection
- Cleanup
- Opening to traffic
71Quality ControlPreliminary Responsibilities
- Project review
- Document review
- Material checks
72Quality ControlPre-Application Inspection
- Surface preparation
- Equipment inspection
- Asphalt distributor
- Chip spreader
- Haul trucks
- Rollers
- Brooms
73Quality ControlPre-Application Inspection
(continued)
- Weather requirements
- Determining application rates
- Checking application rates
- Traffic control plan and setup
74Quality ControlProject Inspection
- Asphalt application
- Aggregate application
- Truck operation
- Rolling
- Longitudinal joints
- Transverse joints
- Brooming
75Quality ControlPost-Application Inspection
- Cleanup
- Opening to traffic
76Troubleshooting
2-4.76
77TroubleshootingWhat is wrong here?
Streaking
78TroubleshootingWhat is wrong here?
Poor Longitudinal Joint
79TroubleshootingWhat is wrong here?
Bleeding
80TroubleshootingWhat is wrong here?
Loss of Cover Aggregate
81TroubleshootingWhat is wrong here?
Inadequate Aggregate Coverage
82TroubleshootingPossible Construction Problems
Aggregate embedment gt 80 percent
83TroubleshootingPossible Construction Problems
Aggregate embedment lt 50 percent
84TroubleshootingWhat is wrong here?
Loss of aggregate due to inadequate curing
85TroubleshootingWhat is wrong here?
Single Overlap
86TroubleshootingWhat happened here?
87Questions?