Title: A Perspective on the PACS Programme
1A Perspective on the PACS Programme
- David Whitfield
- 20th April 2005
2A Perspective on the PACS Programme
- Introduction and Context
- Scene Setting
- Bidding
- Contracting
- Early Delivery
- Growing Pains
- Conclusion
3Scene Setting (1)
- Features of Successful Programmes
- Have a clear vision and real sponsorship
(otherwise failure is not left to chance) - Concerned with outcomes rather than deliverables
- Embrace systems, processes and people aspects
- Involve the stakeholders and deploy clear
management - Embrace control change rather than resist
stifle it
- Some Danger Signs
- Over ambitious
- Over complicated
- Over long
- Few early benefits planned
4Scene Setting (2)
- Some things to remember
- By default, large programmes fail / under-deliver
- You cannot contract for the behaviour you require
- Partnership is essential its a long term
relationship - Shared objectives, recognising different measures
of success - The behaviour that you incentivise rather than
penalise - Contracts are baselines/agreements not management
handbooks - Contracts are the reference of last resort in
court - Nothing of real value is achieved without a
struggle
. its meant to be hard!
5Bidding to April 2004
- Small procurement team
- Bidder-to-user contact
- Limited by process
- Good reaction to supplier initiatives
- Information baseline
- Detailed requirement specification
- National solution from multiple vendors
- Consultation process
- National integration vision
- Sequence change without impact analysis
- Moving goalposts and short timescales
6Contracting (1)
- Supplier selection end April 2004
- Then, all of a sudden, nothing happened ..
... and after a while, nothing more happened
..
.. and then it was July .. .. when
things really did start to happen
- Discussions on contractual matters
- commenced
- faltered, and then
- resumed in earnest
- early engagement at 3 Trusts
7Contracting (2)
- Small procurement team handling multiple LSPs
- IT procurement model based on the core contract
model - Top-down deployment targets drove
- cookie cutter model with rapid responses
committed from the NHS - introduction of encouragements for the
contractors - significant obligations agreed on the Trusts (and
the wider NHS) - Governance and management model
- A number of cliff-edge moments
- After nearly 7 months had elapsed from supplier
selection - agreement reached on 11th November 2004
- with no change in deployment target dates
8A Business Change Programme
. with a contract which focuses on the
delivery and operation of the enabling IT
component
9. which is only about this .
Southern Cluster Primary Image Store
West Dorset Server Rack
10.. to facilitate the changes from this ..
11.. to support the vision of ..
12.. film-less and paper-less imaging
13The Going-In Environment
- Centrally established requirements
- Standardised buying method
- Output based service charging
- Limited user involvement
- Information centralised
- and then.
- Huge urgency
- Lean scaling
- Unclear financial arrangements
- Limited communications
- Lack of ready answers on important topics
.. hence some tricky starts were to be
expected ..
14Early Engagement
- A fast start was essential but had to be
sustainable and strategically aligned - Pre-contract work provided a framework for wider
engagement - Focus on delivering early results
- Temporary Order mechanism avoided many start-up
delays - Initial equipment configured and ordered for 3
Trusts and for the Cluster Image Store within 5
weeks - Working with the Trusts rather than doing PACS
to them - Finding ways round obstacles / challenges rather
than using them as explanations for delays - Striving to fill the information gaps for the
Trusts .. - .. and feeling a way through the governance
arrangements ..
15Stakeholder Relationships around PACS
National Programme for Information Technology
Southern Cluster
SHA
XYZ Hospitals NHS Trust
16Contractual Relationships for PACS
National Programme for Information Technology
Southern Cluster
SHA
XYZ Hospitals NHS Trust
17Deployment Sequence
Prelim Config
Final Config
Bus Case Approval
Place Order
Initial Meeting
Ongoing Service
Test Accept
Rec Stage Eqpt
Install Integrate
Go Live
18Deployment Status - Today
Royal Surrey, MTW
Plymouth
Gloucestershire
Poole
Dartford Gravesham
Worthing Southlands
Prelim Config
Final Config
Bus Case Approval
Place Order
Initial Meeting
North Bristol, NOC, East Kent
Brighton Sussex
Royal Cornwall
Temporary Order
Milton Keynes
Salisbury
Ongoing Service
Test Accept
Rec Stage Eqpt
Install Integrate
Go Live
Ashford St. Peters
19Growing Pains
- Life changes after any major service goes live
- Priorities restoration, continuity, enhancement
- Environment continually changes - PACS is not an
island - Technology presents new opportunities
- The service must evolve or risk becoming
irrelevant - The current early nursing is not scalable
- Broader engagement ahead
- Industrial strength processes to be
institutionalised - Governance and management gear change
- BUT each Trust sees their PACS deployment with
fresh eyes
20Conclusion
- The urgency was a significant factor in building
momentum - The end of the beginning has now arrived
- One Trust may not a Cluster be . . . . but it is
at least a tangible start! - There is no realistic way back
.. before it gets even harder
- .. but lessons can be learned to make it
easier - Change will be both an imperative and a potential
threat - The deployment will inevitably cause the vision
to evolve
.. and finally..
21PACS . . .
Enabling a step change in healthcare provision