Title: WHICTS County ICT Programme Board
1Worcestershire Health ICT Services County ICT
Programme Board Presentation - Key Points
Notes (15th Jan 08) John Thornbury Director,
Worcestershire Health ICT Services John.thornbury_at_
nhs.net 078 667 213 71 (wictp_a_080115_00
_presentation.ppt)
2Ag 2 - Previous Actions List (PCT)
3Ag 2 - Previous Actions List (PCT)(Contd)
4Ag 2 - Previous Actions List (Acute)
5Ag 2 - Previous Actions List (Acute) (Contd.)
6Ag 2 - Previous Actions List (MHP)
7Ag 2 - Previous Actions List (ICT)
8Ag 2 - Previous Actions List (ICT) (Contd.)
9Ag. 3 - Countywide ICT Strategy / Plan
- DoH full guidance for IMT Plans (21st Dec 07)
Attachments 1. - Completion of 1st draft (Attachment 2) by close
of Jan 08 full plan by close of Mar 08. - PCTs to act as leads in delivery (based on
governance set up 2007/8). - LHC based plan, PLUS
- Provider Trusts (incl. PCT as provider) to have
individual IMT plans. We recommend Trust
sections within a single LHC based IMT plan. - Full plans must contain
- Operational level detail for 2008/9
- Local service transformation plans requiring IMT
input. - Service benefits planning from IMT perspective.
- Clear outline of governance arrangements.
- Investment against baseline as well as local,
regional Nat devt. - Capacity and capability planning.
- Longer Term Plans to 2010/11
- Anticipated service priorities.
- Progress towards Maturity Model.
- Indicative roadmap for regional and national
solutions.
10Ag. 3 - Countywide ICT Strategy / Plan (Contd.)
- We also have the following as guidance
- SHA guidance to PCTs (Attachment 3) on Assurance
Frameworks (Peter Spilsbury letter 17th Oct
07) - Our NHS Our Future focus on 8 clinical
pathways - Investing in Health 7 Big Challenges
- 2008-9 Operating Framework
- Setting out concept of vital signs for action,
including - Cleanliness and infection control
- Improving access (18WW GP)
- Reducing health inequalities and promoting health
and well being particularly addressing - Cancer
- Stroke
- Childrens services
- Maternity
- A range of existing and new ICT specific
deliverables, incl. - Confirming migration to national systems.
- Heavy emphasis on primary care based systems.
- Migration to a mature infrastructure.
11Ag. 3 - Countywide ICT Strategy / Plan (Contd.)
- Initial summary provided last month.
- Current Jan 08 version
- Addresses new areas in final version of DoH
guidance. - Biggest dependencies on completion of initial
version - Trusts confirmation on initial service priorities
MHP known. - Budget to be agreed by CEOs.
- Clarification on DIP agreements awaited from SHA.
- Send this initial plan to SHA by close of Jan 08,
then.. - Trusts finer detail on service priorities.
- Finer detail on deployment schedule against Jan
08 plan. - Update DIP should Cluster / National system
functionality change. - Finer detail of resources allocation against Jan
08 plan. - Full plan end Feb 08 for sign off at Board (17th
Mar 08.) - Full plan to SHA for close of Mar 08.
12Ag. - ICT Services Report (Operational)
- Full report available (Attachment 4)
- Service Availability
- Networks Server consistently excellent
- Applications
- Quarterly un/scheduled downtime consistently
below 1 - Covers NCRS, Oasis, Oasis theatres, AE Patient
First, CaB - NCRS rose to 2 (aborted upgrade) and Oasis to
2.8 (planned CaB upgrade) in Dec 07. Aug 07
last period when gt1.
13Ag. 4 - ICT Services Report (Operational Contd.)
- Service / Helpdesk Calls
- Application Call
- Calls closed continue to match calls opened.
- Calls opened closed in same month consistently
gt 90 - Call Cost to CfH have now been suspended.
- Call makeup (Dec 07)
- 43 Account set up
- 25 NCRS
- 26 Oasis
- 1 CaB
- 4 EDS
- 1 AE Patient First
- Service Desk
- Dec 07 Calls closed (2155) exceed calls opened
(2124) - Averaging gt70 calls logged online.
- GP extensive use of web call logging (average 90
of calls)
14Ag. 4 - ICT Services Report (Operational Contd.)
15Ag. 4 - ICT Services Report (Projects)
- (W2b) Choose Book (PRIORITY 1)
- System continues to function well.
- Update awaited on
- management issues discussed at last meeting
(Acute action 13) - progress on utilisation plan to increase usage to
50 by Mar 08. - (W2c) Electronic Prescription Service (R1
Technical) (PRIORITY 1). - GP Pharmaceutical suppliers slow to get systems
accredited - 48 (72) of General Practices are technically
live. - 43 (64) are operational (4 on last month).
- 53 (61) of pharmacies are claiming payments
(10 on last month) BUT 94 systems functional
discussion with SHA as to how to encourage more
use. - PCT prescription rate is 5th highest in SHA. Q2
up 113 on Q1
16Ag. 4 - ICT Services Report (Projects Contd.)
- (W22) NSTS Closure (PRIORITY 1)
- Very good progress currently the 3 Trusts are
within top 19 nationwide, having completed
technical go live. - Ph1 work essentially technically closed
training will continue over Jan / Feb 08. - Acute RA Management (Acute action 11a, 11b) has
not functioned continuing issue. Needs
addressing by Trust as a matter of urgency. - (W29) GP2GP (PRIORITY 1)
- Good progress for 22 practices involved
- 17 live (6 on last report).
- Discussions with remaining 5 taking place.
- (W3d) Maternity (PRIORITY 2)
- Data sets for normal pregnancies now complete
testing planned . - Data sets for abnormal pregnancies continue to
be developed. - Go live likely end of Mar 08 / Apr 08.
17Ag. 4 - ICT Services Report (Projects Contd.)
- PACS (PRIORITY 2)
- (W3i) WRH closure processes commencing (legacy
data transfer contd.) - (W20) Comm POWCH Evesham installed. Malvern
Tenbury started. - Cluster Solution agreement to take RIS. Detail
awaited. - Acute Medical Records (PRIORITY 2)
- Selection criteria nearing completion.
- (W36) GP OOH Tender (PRIORITY 2)
- ICT Services both service and ICT project
management components. - Spec, OJEU advert, PQQ competitive dialogue
complete. - Invitation to Submit Final Offers sent out.
- (W28) Infection Control (PRIORITY 2)
- Technical deployment 95 complete.
- Training planned for Jan 08.
- Go live anticipated close Jan 08.
18Ag. 4 - ICT Services Report (Vacancies)
- ICT Services Directorate (Total)
- 2 posts awaiting consideration
- 5 to advert
- 5 interviews scheduled
- 1st Line Support
- 2 posts awaiting consideration
- 1LS012 (IT Desktop Technician)
- 1LS013 (IT Junior Desktop Technician (Andrew
Coburn)) - 1 to advert
- 1LS011 (IT Equipment Transportation Officer )
- 3 interviews scheduled
- 1LS008 (IT Junior Desktop Technician)
- 1LS009 (IT Desktop Technician)
- 1LS010 (IT Desktop Technician)
19Ag. 4 - ICT Services Report (Vacancies Contd.)
- Knowledge Management
- 2 interview scheduled
- KMT001 (Library Informatics Assistant,
Worcester/Evesham) - KMT005 (Library Informatics Assistant,
Kidderminster) - Clinical Informatics
- 1 to advert
- CIF005 (Clinical Informatics Specialist)
- Project Management
- 3 to advert
- PPM001 Project Manager (Senior)
- PPM002 Project Manager (Standard)
- PPM003 Project Manager (Junior)
20Ag. 5 Information Governance
- Key Points From Last County IG Forum Meeting
- The Acute Trust IG Officer had been unable to
commit fully to their IG role as they have been
providing cover for Information Services. Now
resolved. - Date now set for interviews for WHICTS
Information Security Officer 11 Jan 2008 - Worcs PCT IG Officer has left post to take up a
new role in the organisation. This vacancy is set
to be advertised soon. - David Nicholson has written (4th Dec 07) to all
NHS CEOs regarding IG and esp. patient data
transfers. A checklist of immediate actions to
be taken for securing data in transit has been
published by CfH in the form of the Good Practice
Guidelines, which cover the transfer of person
identifiable data by means of portable electronic
media - Ian McGregor in his role as Information Security
Officer has begun this work by emailing out to
all senior managers and heads of services to
urgently review arrangements that are currently
in place where person identifiable data is sent
in digital format. A subsequent report and action
plan are to follow. - Issues Requiring Organisational Senior Management
Attention - IG01 - Out of Hours RA Support - RA support will
need to be provided for out of hours staff who
require access to NHS Connecting for Health
compliant applications - IG02 - WHICTS IG related policies - need
renewing. - IG03 - Statement of Compliance - 17 key standards
that all Trusts need to agree to before receiving
access to the N3 network. At present, each Trust
falls short on compliance in one area or another. - IG04 transfer of patient data David
Nicholson, the Chief Executive of the NHS in
England has written to all NHS Chief Executives
about IG and transfers of patient data.
Subsequent reports and action plans are to be
produced urgently.
21Ag. 6 - Monthly Budget Report
- Attachment 5 (text).
- Attachment 6 (figures).
22Ag. 7- Any Other Business
- Information Security Policy (Attachment 7).
- Mobile Devices Policy (Attachment 8).
23Ag. 8 Date Time Next Meeting
Schedule