Title: LA DEMARCHE DEVELOPPEMENT DURABLE DANS LE BATIMENT
1RETROFITTING Chevrollier School Angers -
France
REVIVAL
WORK PACKAGE NUMBER 1 CHEVROLLIER SCHOOL STATE
IN OCTOBER 2006
October 2006
2Overview before refurbishment
3Building with asbestos
N
BEFORE REFURBISHMENT
4Building M and a part of Building L (L2) not
concerned to REVIVAL
Building A (sport room) and N (cathering)
Conserved in original state
NEW BUILDINGS
C
N
X
REFURBISHMENT
K
L
L2
L1
M
J
O
D
H
I
E
F
G
C
B
A
Note Recent change of buildings names from
Direction of Chevrollier School
5 L2
L1
Building L is decomposed in 3 parts (L-L1-L2)
L-L1 will be achieved in July 2007 M (habitation
for teachers) and N2 (archives), not included in
Revival project Actual works in buildings D, O,
L, L1
6GENERAL ANALYSIS
- Strict respect of delay and planning
- Technology strict respect of planning
- Photovoltaic previously in atrium, placed in
building C - Difficulty and complexity concerning to BEMS
installation the first place of BEMS was in
building B - New installation of BEMS in Building J (in
function) - Maintenance buildings in function with
durability of material and easily maintenance
71st BALANCE
Objective reached
Summer Comfort (without HVAC)
- Students exams started out in June 2006, during
a hot week - Students have total satisfaction
- Note During this week, we have received
permission to apply questionnaires, but interdict
to take pictures and to realize measurements - In the most hot day of the year (beginning of
September) we have realized measurements with
suitable results - Remarks BEMS and ventilation system were not in
function in this day
8Natural Lighting
- Encouraging results
- Persons have satisfaction (comparison between
before and after refurbishment
Acoustic Comfort
- ITAC enterprise has realized measurements during
final works (good performance) - Note Teachers and technical persons are very
satisfied
9ARCHITECTURAL ASPECTS
Look
- All professionals (administrative, learning,
students, manager, visitors, etc) are delighted
with the new buildings of Chevrollier High School
Functional
- Considering the reinforcement of social links,
the main objective is affected. The number of
students increases.
10Global expertise including investment cost and
maintenance cost
- Determination of the best solution during all the
design phases to both optimize - The investment cost, the maintenance cost, the
energy consumption, the CO2 emission, the
comfort, the health
11 PICTURES
We will show some pictures of the buildings which
have been achieved in June-July 2006 and in
function since September 2006
12 Buildings achieved in June 2006. South façade of
Buildings E-F In function since 1st September 2006
13 C
E-F
Buildings achieved in June 2006. South façade of
Buildings E-F and North façade of Building C E-F
in function since 1st September 2006
14 A classroom in Building E In function since
September 2006
15 Inside Buildings E-F secondary daylight
In function since September 2006
Note Remember technical planning
16 Buildings achieved in July 2006. West façade of
Building H Actually in function
Note This building replaces the old workshop
with asbestos
17Buildings achieved in July 2006. East façade of
Building H Actually in function
18 Daylight
Buildings achieved in July 2006. Inside of
Building H Actually in function
Note This picture has been taken in the early
morning
19 Buildings actually in retrofit works Building D
20North daylight strategy
Beginning of retrofit works Building O
21Beginning of retrofit works Building O
Metallic sheet to improve the maintenance
Linoleum natural material / low VOC
22 Chevrollier Monitoring in Progress
-
- We have begun the monitoring of
- DAYLIGHT
- SUMMER COMFORT
- ACOUSTIC COMFORT
- MAINTENANCE
- VENTILATION AIR FLOW RATE (realized by the firm
AXIMA)
23Dissemination
- Concerning to REVIVAL theme, Gaudin Ingénierie
office has realized a presentation form
containing various slides with two following
parts - Reduced form (with 40 slides) per 40 minutes
- Global form (with 150 slides) per 3 hours
- Since 2003 presentations and interventions in
French Municipality, French Universities,
International and French Congress, Public and
Private Sectors, HVAC Association, French
Professional Associations and Enterprises
24Principal interventions in Universities and
Schools
- Architecture School of Nantes (France) 60
students - Engineering Institute of Rennes INSA (France)
190 students - Polytechnic School of Nantes (France) 60
students - Master of Faculty of Architecture in Federal
University of Rio de Janeiro (Brazil) 40
students
25Principal presentations in French Municipality
and RPDL Region
- RPDL Region presentation to elected people
- Municipality of Rézé
- Community of municipality Villaines La Juhel
- Nort sur Erdre municipality
26Principal presentations in professional
enterprises and associations
- Successful enterprise (CSC) in Rézé (France)
- Successful enterprise (Library of Nantes
University) - Lafarge regional meeting (Rencontre des décideurs
du bâtiment) 300 persons (Nantes, France) - French High Environmental Quality Association
(ICEB) Revival first Balance 50 persons
(Paris, France) - French Association of HVAC Engineer (AICVF,
member of REVHA) - Local Architecture Association (CAUE-AE)
specialized in environment - SIDEV, a big owner presentation before
realization of sustainable public equipment
(12.000m²) France - French Gas Technical Association (ATG)
- Some Architecture offices in France Archidee
Menard Lepinay - etc
27Meetings and papers in preparation
- Presentation and paper publish is programmable in
the 21st-22nd November 2006, in Lyon, France
(CLIMAMED HVAC International and Mediterranean
Congress of REHVA) - Paper in preparation CLIMA 2007 Well Being
Indoors (International Congress), in Finland, in
June 2007
28 Building C (South-East corner) and Building E-F
(South façade) Synthesised image
29 THANKS FOR YOUR ATTENTION