University of Colorado at Boulder D S U A V E Interim Review 1 Spring 2007 2 Meet the Team Burhan Muzaffar..Project Manager Miranda MeslohAssistant Project Manager Nathan Sheiko...Systems Engineer David Goluskin.Fabrication Engineer Jastesh Sud..CFO Yoshi Hasegawa........Safety Engineer Brandon Bobian.Electronics/Webmaster Michael Lapp..Vehicle Design Lead 3 Overview
Changes in Design RFA
Design Summary
Test Plan
Current Issues
Schedule Progress
Budget Progress
4 RFAWing Deployment Spring Length 5 RFAWing Deployment Spring Length Deflection 6 RFAWing Deployment Spring Length Force applied to Piece 3 when Piece 2 hits Piece3 7 RFAWing Deployment Spring Length
Shear stress analysis
Shear stress (MPa) Epoxy (Shear stress is13.8MPa) - connects backbone and pieces. Assume that epoxy can connects backbone and pieces perfectly. 8 Design Changes
Wing deployment mechanism
Spring in compression when maximally extended
Triggered by onboard servo
Vehicle deployment mechanism
Triggered by onboard servo
Two vehicle connection points
Protective tube eliminated
9 Design Changes
Vehicle and wing deployment
10 ElectronicsChanges Since CDR
FM instead of PCM RC receiver
Futaba R168DF 8-Channel FM DC 75MHz
Release servo
One servo to release vehicle and deploy wings
Changes to Onboard Software
Deploy vehicle with an RC command
11 Subsystem TestsW-01 Wing Structural Test
Requirements
Wingtip deflection less than 5 wingspan under worst case (2.5g)
Verification Tests
Measure tip deflection of loaded spar-only and complete wing
Needed for Test
Half-Wing
Measurement Grid and Camera
Clamp Capable of 25N Force
50-gram Masses (10)
12 Subsystem TestsWD-01 Wing Deployment Timing and Locking
Requirements
Wing deployment time lt0.4s
Correct operation of locking mechanism
Verification Test
Wing deployment under flight conditions (12m/s)
Wing remains fully locked after deployment
Video recording of test to verify timing
Needed for Test
Complete swing mechanism mounted on backbone
Truck with an open bed
Video camera
Test location (N. 55th St.)
13 Subsystem TestsWD-02 Release Servo Timing
Requirements
Time between vehicle release and wing deployment lt0.3s
Verification Test
Initiate release sequence to time the servo
Video recording of test to verify timing
Needed for Test
Complete release mechanism and the swing mechanism mounted on backbone
Video camera
14 Subsystem TestsE-01 Electronics Range Test
Requirements
Communications range must be gt1km
Correct control surface and throttle operation at max range
Ground station reception of velocity at max range
Verification Test
Determine maximum range at which communication work correctly
PowerShow.com is a leading presentation sharing website. It has millions of presentations already uploaded and available with 1,000s more being uploaded by its users every day. Whatever your area of interest, here you’ll be able to find and view presentations you’ll love and possibly download. And, best of all, it is completely free and easy to use.
You might even have a presentation you’d like to share with others. If so, just upload it to PowerShow.com. We’ll convert it to an HTML5 slideshow that includes all the media types you’ve already added: audio, video, music, pictures, animations and transition effects. Then you can share it with your target audience as well as PowerShow.com’s millions of monthly visitors. And, again, it’s all free.
About the Developers
PowerShow.com is brought to you by CrystalGraphics, the award-winning developer and market-leading publisher of rich-media enhancement products for presentations. Our product offerings include millions of PowerPoint templates, diagrams, animated 3D characters and more.