Title: ACARP
1ACARP
Australian Coal Association Research Program
- Australian Roadway Development
- Improvement Project
- OPERATORS WORKSHOPS
- September 2006
2OBJECTIVE AND FORMAT
- Provide a forum for roadway development operators
to - Learn of emerging best practice and roadway
development initiatives - Learn of developments in equipment and technology
- Network with peers, and share their experience
and learnings (and not just their successes) - Identify areas for targeted research
3FORMAT
- Four workshop subjects presented by best practice
operators - Each workshop comprises a 20-25 presentation and
a 20-25 minute open forum for discussion and
sharing of experiences and learnings - Poster board presentations by OEMs and
researchers - Plenary session to
- Capture key findings
- Identify opportunities to improve the workshop
process - Identify other issues for future workshops
- Identify areas for targeted research
- Workshop report with copies of presentations to
be provided to all participants
4INTRODUCTION
- Prerequisites for attendance
- A passion for roadway development, and
- A willingness to participate in discussions and
share experiences
5ACARP
Australian Coal Association Research Program
- ROADWAY DEVELOPMENT
- TASK GROUP
- Guy Mitchell, BMA
- Glen Lewis, Xstrata Coal
- Bob Miller, Centennial Coal
62005 DEVELOPMENT CHALLENGE Why?
- Marked increase in demand for export coal.
- Significant increase in capital and production
costs. - Substantial improvements in longwall production
and productivity are continuing to be achieved. - Improvements in roadway development are generally
failing to keep abreast of longwall improvements. - Higher capacity, new generation mines are being
planned. - Older mines are still struggling to survive as it
becomes more difficult to find solutions and
successfully apply them. - Unlikely that both will be realised if current
roadway development activities and trends are
remain unchanged.
72005 DEVELOPMENT CHALLENGE
- RDTG formed design a roadmap or strategy for
targeted RD to improve roadway development. - Previous attempts as one off Company
initiatives have failed - Poor problem scope, planning organisation
- Lack of Mine involvement and commitment
- Poor execution and patience
- Absence of information sharing (competitive
edge) - Industry wide problem where common sense suggest
joint problem solving approach where we share
successes and failures! - Initial members were Anglo, BHPB, BMA,
Centennial, Rio Tinto, Thiess, and Xstrata. - References to July 2005 ACARP report identifying
what incremental and step changes can and must be
made in roadway technology and systems - Development of new generation longwall mines
- Older mines to remain competitive
82005 DEVELOPMENT CHALLENGE
- Report Recommendations
- What operators/mine managers should do
- What mine owners should do to address key
constraints - What incremental/step change initiatives should
be pursued by ACARP - Focus on Key Elements
- Coal cutting and loading
- Roadway support
- Coal clearance
- Logistics (services supplies)
- Operators Workshop
- Industry practitioners with broad range of
conditions - Detailing sub elements of the development process
- Providing insight into where their gains have
been made - Process control/continuous improvement
- Roof/rib support practices and equipment
- Best practice maintenance
- Panel advances
- Opportunity for questions and discussions
9ACARP
Australian Coal Association Research Program
- REVIEW OF AUSTRALIAN ROADWAY DEVELOPMENT
CURRENT STATUS - Gary Gibson, ACARP
102005 REVIEW
- Identify where past wins have been achieved and
the lessons learnt. - Identify incremental and step changes in roadway
development technology and systems necessary to - Enable new generation, high capacity longwall
mines to be developed - Provide productivity gains to enable existing
mines to compete with the new generation mines. - Identify specific RD opportunities for new
technologies, equipment and associated systems. - Build support and commitment for a targeted 7
year RD program.
11INDUSTRY REVIEW PROCESS
- Reviews conducted with representatives from
- All longwall mines
- Bolting hardware suppliers Hilti, Jenmar, and
One Steel - Corporate offices - Anglo, BHP Billiton, BMA,
Centennial, and Xstrata - Geotechnical consultants - SCT, Seedsman, and
Strata Engineering - Mining contractors - HWE, Roche, Thiess, UGM, and
Walters - Mining equipment OEMs - DBT, Joy, and Sandvik
- Other OEMs Alminco, Continental, Hydramatic,
and PJ Berriman - RD organisations CET, Eikon CoalStream, GSS,
and QCAT - Regulators and service providers DNRM, DPINR,
and Coal Services - TBM OEM/developers IHI and Pacific Tunnelling
- In all, some 160 persons participated.
- Structured review process at mine sites, 1 on 1
interviews elsewhere.
12BEST PRACTICE MINES
- A wide range of performance levels were reported
across a wide variety of mining conditions and
equipment. - Factors other than mining conditions, and
equipment must be at play significant
differences with similar equipment and similar
mining conditions!
13BEST PRACTICE MINES
- Key factors differentiating best practice mines
and others - Driven culture, desire to succeed, focus on
getting things right, accountability. - Understanding of roadway development as a
process, and the application of short interval
process control. - Degree of involvement of employees.
- Focus on utilisation of personnel through
provision of adequate fit for purpose
equipment. - High levels of reliability and availability
engineered into equipment, with focus on
maintaining equipment fit for purpose. - Awareness of and aggressive application of new
technology, equipment and systems to improve
safety, productivity and costs .
14HIGH PERFORMANCE MINES
- High performers in poor conditions were typically
achieving similar or better development rates
than poor performers in good conditions. - Factors typically evident at high performing
mines - Major focus on and prioritisation of roadway
development. - Incentive schemes strongly linked to development
performance. - Likely utilisation of 12CM/12/30/32 continuous
miners in a balanced, sequential cutting and
bolting process. - Ability to complete panel advances in 12 15
hours. - Effective mine planning.
15MAIN FINDINGS
- Later generation mines with good conditions are
likely to establish 15Mtpa mines without major
developments in mining equipment and systems.
16MAIN FINDINGS
- Infrastructure limitations likely to constrain
older mines from making major improvements in
mine capacity. - Adverse conditions associated with depth (eg
stress and gas) will pose additional productivity
challenges to older mines, and to later
generation mines as they mature.
17MAIN FINDINGS
- Technology developments are currently underway
which will address some key process constraints
in the short to medium term, providing potential
to improve system capability across all mines.
18CURRENT DEVELOPMENTS IN TECHNOLOGY
- Five self drilling bolting (SDB) systems are
currently in various stages of development, with
a variety of civil sector SDB also available (but
expensive). - Sandvik releasing an upgraded ABM25(S) designed
for difficult mining conditions and 4.8m wide
roadways. Likely to incorporate Aro
semi-automated bolting system. - Joy mooted to be developing a new generation
continuous miner for global roadway development
market. - DBT established a global roadway development
group. - Both IHI and Pacific Tunnelling have developed
concepts and detailed engineering designs for
TBMs, and project that they could be on site in
18 24 months.
19CURRENT DEVELOPMENTS IN TECHNOLOGY
- Joy had 2 floor mounted 4FCT systems in operation
in US mines, with 2 other systems then under
manufacture for US mines. - Sandvik were due to shortly release a roof
mounted continuous haulage system. - Continental anticipated releasing a roof mounted
monorail based extensible and retractable
development/longwall conveyor. - Cutting Edge Technologies had reportedly
completed designs for an extensible conveyor
system. - Eikon had completed design for a 250m3/hour coal
slurry transportation system. - Finalisation of the ACBM was reportedly stalled
by a failure to complete contracted development
of an automated bolting system.
20ROADWAY DEVELOPMENT CONSTRAINTS
- Roof and rib bolting, and installation of roof
and rib mesh - Cyclic nature of coal haulers, particularly
beyond 70m from boot end - Advancement of conveyor and panel services,
particularly with dual CM units - Routine installation of ventilation ducting
- The logistics of supply, transport, distribution
and handling - particularly at older mines. - Installation of long tendons as primary support
becoming more widespread - installation equipment
still fairly rudimentary - The physical demands of the work environment, the
extent of manual handling, an ageing workforce - Coal cutting was not seen as a constraint at any
mine, however the ability of machines to cut
breakaways for cut throughs was considered to be
a major failure of all machine configurations.
21NEW MINING SYSTEM
- The key attributes of a new roadway development
mining system were identified as - Integrated, continuous cutting, bolting and coal
clearance system continuous mining. - Automated bolting, with self drilling bolts.
- Integrated materials supply and logistics with
components stored in magazines or cassettes
allowing minimal manual intervention. - Extensible (monorail mounted) face services (eg
ventilation, power, water, compressed air, pump
out). - Extensible, self advancing panel conveyor.
- High capacity, automated installation of long
tendon secondary supports.
22INDUSTRY CONSTRAINTS
- Real or perceived constraints to successful RDD
of new technology and mining systems - Industrys ability and willingness to fund and
sustain the RDD of new mining systems,
particularly through tight economic conditions. - Few mines have sufficient development float to
allow critical resources and mine real estate to
be deployed to developing new technology. - Scarcity of managers, engineers, supervisors,
operators and trades. - Limited size of Australian market, and OEMs
propensity to develop new technology as global
products, and for development to be done
in-house. - Lead time from concept to successful
demonstration is too long - loss of project champions (eg promotion or
turnover) and - diminution of corporate energy and critical mass.
- Overly restrictive legislation limiting the
development and application of new technologies
and the use of light weight materials. - Over zealous pursuit of absolute safety first by
Inspectorate, with prosecutions in the event of
less than absolute safety.
23RECOMMENDATIONS
- What mine operators and mine managers should do
to improve development performance. - What mine owners should do to address key
constraints. - What incremental change initiatives should be
pursued by ACARP. - What step change initiatives should be pursued by
ACARP.
24MINE OPERATORS AND MINE MANGERS
- Pursue industry best practice roadway
development. - Fully embrace concepts of process control,
continuous improvement, and involvement of all
personnel in those pursuits. - Commit to conduct of a routine roadway
development benchmarking process across the
industry. - Commit and contribute to a regular best
practice roadway development forum and enable
development practitioners to share successes and
failures, and learn of new practices,
developments in RD, and emerging issues. - Through publication of Proceedings from the
forums, support the development of a body of
knowledge of best practice roadway development. - Give due recognition to development in the mines
operation - Adequately resource development to enable it to
be properly accountable for its performance.
25MINE OWNERS
- Develop and commit to a long term investment
strategy to support and sustain the research,
development and demonstration of new mining
systems and technology. - Develop and commit to a long term strategy to
develop the industrys skills base and overcome
the scarcity of experienced mining professionals,
engineers, supervisors, operators and trades
personnel. - Challenge the restrictive legislative framework
being imposed on the industry, and the regulators
resort to prosecution in the event of less than
absolute safety. - Fund, support and sustain
- routine roadway development benchmarking studies
- conduct of regular best practice roadway
development forums, and - development of a best practice body of
knowledge. - Challenge mine operators and mine managers if
they fail to pursue industry best practice
roadway development practices.
26ACARP
Australian Coal Association Research Program
- ROADWAY DEVELOPMENT
- IMPROVEMENT STRATEGIES
- Guy Mitchell, BMA
- Glen Lewis, Xstrata Coal
- Bob Miller, Centennial Coal
27BRAINSTORM TIME
- A quick exercise
- Your thoughts ideas
- Your opinions
- Whats good?
- Whats bad?
28WORKSHOP RESPONSES - MACKAY
- GOOD
- Clean separation of development from longwall
equal focus individual business units - Involvement of operators and others in all facets
of the development process and activities - Companies using data to identify opportunities
- Ownership of process and involvement is high at
high-performing mines - Focus on workforce and community
- Parallel-pathing of activities
29WORKSHOP RESPONSES - MACKAY
- BAD
- Lack of commitment by all stakeholders
- Right people lack control
- Industry becoming closed to new inexperienced
people - Operators dont have enough input into
standardising processes - Non-standardisation of processes
- Coal haulage continued use of shuttle cars
- Old technology used too long
- Failure of develop continuous haulage systems
- Unrealistic budgets
- Lack of investment in process
- People not able to be accountable
- People lack of work ethic
- Unrealistic expectations of machinery and
peoples performance - Fear of failure development behind budgets -
reluctance to try new things - Fear of prosecution
- Rosters affect effective communication
- Lack of knowledge and management focus
- Shift duration - operators become unproductive
later in shift
30WORKSHOP RESPONSES - POKOLBIN
- SUCCESSES OF LAST 5 YEARS
- Hydraulic bolters in lieu of hand held bolters
- Focus on process, and integration of systems
- Set standards, with all shifts doing the same
thing - Achievements in primary and secondary support
systems and products (installation systems
require further RD) - Machine monitoring improvements, almost to
longwall standards - Use of fit for purpose materials and equipment
handling attachments - spent on ancillary
equipment to improve materials handling and
logistics systems - Attitude of personnel harnessing power of
people pride in their job maintenance of
standards - Senior management credibility doing what they
said they would do - Involvement of people in process
- Change in leadership model and supervisors role
leader rather than lamp holder - Age of workforce focus on ergonomics
- Increased focus on safety and development of
safety systems approach - Services handling systems monorails
- Increased KW installed in development equipment
- Radio control of machines success?
reliability? exposure of people to pinch points?
31WORKSHOP RESPONSES - PENRITH
- RD SUCCESSES OF LAST 5 YEARS
- Geological and geotechnical developments for roof
support determination - Application of monorail systems
- Development of roof and rib support hardware by
OEMs and suppliers - Technology developments from ACBM project
- How do we wrap emerging technologies together as
an integrated, cost effective system? - RD ISSUES FROM THE PAST 5 YEARS
- RD on the run (roof and rib support) lack of
industry support - Reactive application of geotechnical design to
support systems - Failure to adopt other industry supply systems
- Lack of predictability of geotechnical conditions
- Pioneering development of equipment
- Further improvements in monorail systems required
- ACBM getting OEMs and operators to take it
forward
32ACARP - INCREMENTAL CHANGE
- Demonstrate a high capacity, integrated mining
system that incorporates then available, best
practice technology. - Pursue and expedite commercialisation of
alternative self drilling bolt technologies and
automated bolting systems, including potential
retrofitting of automated bolting systems to
existing CMs. - Facilitate and expedite completion of the ACBM
and associated technologies. - Develop alternate skin reinforcement and
confinement measures to eliminate use and
handling of steel mesh. - Facilitate development of an extensible, self
advancing panel conveyor. - Develop a high capacity, automated long tendon
installation system for both primary and
secondary support applications.
33ACARP - INCREMENTAL CHANGE
- Develop a mine economics modelling system that
enables mines to properly evaluate the full cost
of alternate development systems. - Pursue other complementary technology
developments including - automation and robotics
- machine guidance systems
- light weight materials
- face pumping systems
- roadway construction and consolidation
- gas drainage
- Improve level of awareness and understanding of
technologies being applied in other industry
sectors - Metalliferous and tunnelling
- Coal industry assessment by a technologist
34ACARP - INCREMENTAL CHANGE
- Improve level of awareness and understanding of
roadway development technologies and systems
being utilised in mines overseas. - Desk top review
- Technology mission if warranted.
- Develop software that will facilitate and enhance
the adoption of the systems approach/ process
control.
35ACARP - STEP CHANGE
- (We recognise the problem but cant conceptualise
the solution) - Develop a vision to demonstrate a high capacity,
integrated mining system by end 2008. - Specification capable of sustained, continuous
production at a level of 10MPOH, gt20 hours day
(10/20). - Develop a strategy for development and
demonstration of the high capacity, integrated
mining system. - Develop a specification for the high capacity,
integrated mining system - Commission the design of a number of alternative
systems - TBM concept could provide an integrated,
continuous cutting, bolting and coal clearance
system at a number of mines. - TBM provide good immediate ground support in
difficult ground conditions. - Construction industry approach simultaneous and
parallel pathing of work activities
36ACARP - STEP CHANGE
- Evaluate and select a design that best meets the
industry specification and requirements, and - Commission an OEM (or OEMs) to develop the
technology and manufacture the integrated system. - Establish a collaborative agreement to conduct
demonstrations at appropriate mine site (eg
highwall), either - by a project team internally funded by the mine
owner, or - by an externally funded mining contractor
(ACARP). - Project manage the technology and equipment
development process through to the conclusion of
the field trials and demonstrations through to
end 2008.
37WHAT HAS BEEN DONE TO DATE
- Report accepted by ACARP and key recommendations
supported including - Benchmarking studies on 6 monthly basis
- Regional Operators Workshops on 6 monthly basis,
culminating in Operators Conference early 2008 - Review of civil and tunnelling sectors
- Alternate skin reinforcement and web-based
operators network/MIS invited to make second
round submissions - Support for field trials of SDB project
- High capacity mining systems workshop scheduled
November 2006 (coupled with L15 project?) - Commitment to pursue opportunities identified in
workshop processes
38ACARP
Australian Coal Association Research Program
- KEY FINDINGS JULY 2006 BENCHMARKING STUDY
- Gary Gibson, ACARP
39JULY 2006 BENCHMAKING STUDY
- Contributions received from
- Mandalong
- Metropolitan
- Broadmeadow (BMA)
- Tahmoor
- Angus Place
- Beltana
- Austar
- North Goonyella
- Broadmeadow (HWE)
- Springvale
- Appin
- Glennies Creek and Kestrel reportedly well
advanced - Findings now to be separately reported to
respondents and workshop participants, with
close-off of responses 8 September 2006.
40ACARP
Australian Coal Association Research Program
- PROCESS CONTROL AND CONTINUOUS IMPROVEMENT
- David Gibson and Matt Bonnard, Beltana
41PROCESS CONTROL WORKSHOP - MACKAY
- How do you involve people in the selection the
equipment? - Form task groups to involve people from
conception to completion. Benchmark other sites
and consider all OEMs. Beltana to supply
guidelines for equipment performance and
expectations. People that will be using the
equipment pick the best of what is available and
engineer in changes to suit our requirements - How much time per week you as Development
Coordinator spending doing work for your process
and not the rest of the mine? - Approx 70 attributable to the process
- How do you get people to own the process?
- Firstly, development operates as a business unit,
and recruits its own personnel, with personnel be
selected for what they are good at (majority of
personnel were recruited from South Bulga and
were each well known for their various strengths
and capabilities) - We feed them with information and shift briefings
are attended daily by each crew at the start of
shift - We listen to suggestions and act where
appropriate, and involve them in the selection of
their equipment - We adopt sustainable manning levels
- Can you outline the incentive scheme?
- Two major components, 50 each for development
metres and longwall tonnes - We conduct fortnightly audits of panel standards
including roadway alignment and horizon control,
safety equipment, etc - Safety performance is also factored into
incentive scheme - What are the top 5 delays, and do you have any
magic wands? - No magic wands top 5 delays section advance,
travelling to section, flitting, stone dusting,
supplying the miner
42PROCESS CONTROL WORKSHOP - MACKAY
- What material handling issues have been
identified with the new CM? - Bolts handled by QDS pod system. Biggest issues
are handling 1.7m mesh module and vent tubes.
Mesh is stowed in the rib behind the miner and
fetched as required, vent tubes are brought in
when bolting and handled/installed from the miner
platforms. - Are you going to transfer the learnings to the
new Blakefield mine? - Yes, the process will be picked up and taken to
Blakefield South although there will be a need
for a much larger work force - Face cycle?
- Approx 3.2 3.5 days including 8 hour
maintenance shift and 18-20 hours for section
advance - Impact of say 30 increase in support density?
- Reduce development rate by 0.5MPOH (from 5MPOH)
- Shift roster?
- Seven day, four panel roster, 8 week rotation
- Rotate shifts each 2 weeks, that is, 2 weeks on
night shift, 2 weeks on afternoon shift, 2 weeks
on dayshift, two weekends, 1 week off - Undermanagers work same roster but the
development process management team works normal
5 days - Do you intend to utilise dual CM unit at
Blakefield? - Yes. The model has us running two twin miner
panels at Blakefield - Back bye maintenance?
- We are responsible for everything inbye of our
portal. Done when we are cutting at the start of
our cut sequence when there are no parallel tasks
to do and also during our weekend maintenance
windows.
43PROCESS CONTROL WORKSHOP - POKOLBIN
- You mentioned panel auditing, what auditing do
you do? - Fortnightly audits of panel standards are
conducted as part of the mines incentive scheme - Typically audit alignment and width of roadways
and compliance with other panel standards - Have you sought or do you have an exemption for
stonedusting? - Yes, application currently being evaluated by
Department - What have you found to be the optimum break away
angle? - Have found 70 degrees to be optimum as it doesnt
add too much additional development over life of
panel - Used to drive belt road and cut out a wedge for
break away, now cut a 5.5m cut out in the cut
through as the belt road is advanced. That
enables CM to get a full head of coal when it
commences cut through - Who starts the panel advance?
- Whoever holes the cut through, no other fast
rules, rotating shifts are employed - Now considering cutting B heading again while
belt road is being cleaned up - What is the budget this year and how are you
going against it? - Budget 17.446km roadway development for single
unit - 11.18km completed YTD, and we are 186m ahead of
budget YTD - What are the major impediments to further
improvement? - Continued use of shuttle cars, need to utilise
continuous haulage systems (going overseas next
week to benchmark their performance) - Panel advances are biggest delay, typically 20
hours to complete and over life of panel that is
significant given that we are currently
completing two panel advances per week - Face services an issue, but not convinced
regarding monorail systems at this stage - What fundamental changes do you expect as you go
into deeper areas of mine?
44PROCESS CONTROL WORKSHOP - PENRITH
- To get good scores you need equipment
reliability. How do you achieve it? - Firstly, you need good equipment supported by a
good maintenance program, with 100 compliance
with that program - We use a 4-5 day window between panel change outs
to give equipment a major work over - Utilise two maintenance windows, 2 x 12 hour
shifts of a weekend and one 8 hour dayshift mid
week. Major maintenance jobs done on weekends - How do you develop crew ownership of the
development process? - Firstly, development operates as a business unit,
and recruits its own personnel, with personnel be
selected for what they are good at (majority of
personnel were recruited from South Bulga and
were each well known for their various strengths
and capabilities) - We feed them with information and shift briefings
are attended daily by all crews at start of their
shift - We listen to suggestions and act where
appropriate, and involve them in the selection of
their equipment - We adopt sustainable manning levels
- Who tracks the development cycle process time?
- Crew supervisors report on a prepared shift
report and are required to log performance in 15
minute rests - Development Maintenance Coordinator uses the
mines PULSE system to record data - Performance is tracked on a daily basis on a
whiteboard in the crew muster area, weekly
performance is tracked, reported and trended by
the planner. Graphs displayed in muster area
updated weekly. - Are crew supervisors deputies, and how do you
achieve sustainability if in fact they are
deputies? - Yes, crew supervisors are deputies and we
typically have at least two deputies in a crew,
sometimes 3. They step-up from operator to Crew
Supervisor as required - The step-up deputies/crew supervisors are paid at
a rate higher than operators but slightly less
than the nominated Crew Supervisor - You noted that at 170m depth rib support density
increases. Do you experience a change in
development rates with increased rib bolting? - Yes, we see a de-rating of development rates of
some 15 with the increase in rib support and
seam water make - The 170m depth of cover is nominal and the change
in rib support is driven by conditions. We
commenced increased rib support at 130m depth of
cover in the current gateroad
45PROCESS CONTROL WORKSHOP - PENRITH
- What do the 12 man development crews comprise?
- Each crew comprises a crew supervisor plus an 11
man crew, with the crew comprising a maintenance
supervisor, 2 fitters, 2 electricians and 6
operators one of which is a step up crew
supervisor (deputy) - You noted that development crews comprised 12
personnel including the crew maintenance
supervisor, how many people are used when cutting
and loading? - We typically cut out for 10-12m at a time and
then bolt the 10-12m increments in one campaign - We require that 5 people be on the CM when
bolting up, and this will include whoever is
available including SC drivers and trades
personnel - What does the weekend maintenance crew consist
of? - 1 crew supervisor, 1 operator, 2 fitters and 1
electrician, plus supplementary contractor if
required - What sort of incentive scheme do you have?
- Two major components, 50 each for development
metres and longwall tonnes - We conduct fortnightly audits of panel standards
including roadway alignment and horizon control,
safety equipment, etc - Safety performance is also factored into
incentive scheme - Do you have a system for controlling the
development process? - Dont do it down to the minute, but crew
supervisors report in 15 minute increments on
report forms which are customised for each shift
in accordance with work scheduled for shift - Debrief crew supervisors and crews at end of each
shift - Do you maintain during belt moves?
- No, not with the single CM unit. Maintenance is
completed during the three scheduled maintenance
windows - What rosters do you work?
- Seven day, four panel roster, 8 week rotation
- Rotate shifts each 2 weeks, that is, 2 weeks on
night shift, 2 weeks on afternoon shift, 2 weeks
on dayshift, two weekends, 1 week off
46ACARP
Australian Coal Association Research Program
- ROOF AND RIB SUPPORT PRACTICES AND EQUIPMENT
- John Vincze, Springvale
47ROOF RIB SUPPORT WORKSHOP - MACKAY
- With self drilling bolts is it important to
pre-tension the bolt? - Yes, we believe it is important to tension the
bolts as we go. At this stage we havent trialled
any SDB but we will as soon as they are ready. - How does galvanising the long tendons
(spin-bolts) affect the metallurgy of the
tendon/bolt? - Dont know, thats a question for a metallurgist.
Again we havent used them yet however we are
considering them for use in the Mains where we
have a high water content from adjacent old
workings. - What benefit do you get out of the galvanised
mesh as compared to the standard mesh? - Marked difference, they last a fair bit longer.
It is more expensive and we only use it for
reconstruction work in a light duty rib support
role, and it is very easy to handle. Must note
that we put a fair bit of support into it, with
bolt spacing at 1 metre in accordance with the
mines standard support rules. Also the large
pizza plates give it a fair bit of support and
provide good coverage over the mesh. - With all the primary and secondary roof support
materials, belt structure and other materials
being used has there been any increase in manual
handling injuries? - Yes, but we try to minimise it. The PET delivers
the pods to the panel and they are put onto the
miner with a pod handler, and the operator only
has to touch the 7 bolts when he goes to install
them, and he drags the 8m bolts off the monorail. - Trusses installed by contractors and they are
delivered underground and unrolled on the job. - Main injuries at the mine are strains, to the
back, shoulder and arms, and we do notice that as
the workforce ages they are more susceptible to
these injuries. - I noticed on one of the photographs that the
miner appeared to have a slide arrangement to put
the mesh onto the CM. Can you give us some more
details of that? - Yes, we have a slide arrangement for when we put
the mesh onto the CM, it minimises the incidence
of the mesh catching on the CM.
48ROOF RIB SUPPORT WORKSHOP - MACKAY
- You mentioned light weight tensioners, can you
give us more detail? - They are lighter than previous ones used, but I
am not certain how heavy they actually are. It
certainly is an issue working at 3m height when
lifting the tensioner overhead. We do get
injuries, and we dont have a solution yet. We
would certainly like to hear of one if there are
any solutions. - Do you post grout the 8m spin bolts?
- Yes, they are post-grouted with a thixotropic
mixture which is the consistency of toothpaste.
Also post grout the tendons and trusses but we
use a strata binder grout for that, with the
strata binder penetrating the strata as well. - What else is suspended off the monorail system?
- 8m bolts, plastic (grout) tubing, maximum fifteen
20 litre drums of oil, maximum 20 bags of
stonedust (20kg each), fitters and electricians
tool boxes, first aid equipment - What is the make up of the production crews and
what are they responsible for? - Similar to what was at Beltana with dual
continuous miners in gateroads and 6 miners on
each CM, with 1 fitter, 1 electrician and 1
deputy in the panel. - Deputy manages the crews annual leave roster,
with one tradesmen and 3 miners allowed off at
any one time. Sick leave does impact upon numbers
although we have good support from outbye crew. - The three production crews cut coal, do belt
extension and pipe extensions, with the dayshift
outbye crew doing roadworks right up to the crib
room, and doing the transformer moves, and
transporting belt structure and supplies. - 110m belt move is budgeted for 3 shifts,
averages 17 hours with a best result of 11 hours.
The belt move includes the belt and 6 air and
water pipes, with a 4 fire main between the
travel road and belt road every second pillar
49ROOF RIB SUPPORT WORKSHOP - POKOLBIN
- What is the standard panel manning and what are
the crews responsible for? - A deputy, 12 operators, 1 fitter and 1
electrician - Dual CM unit in gateroads
- Headings at 48m centres, cut throughs at 140m
centres - Crew responsible for supplying panel, roadworks,
pipework, belt structure - Best panel advance 11 hours, budget 3 shifts but
typically achieve 18 hours - 1200mm longwall conveyor installed in development
- Transformer move every fourth pillar
- You mentioned you hade problems with Megabolts
and they were no longer used, can you expand upon
that? - Had problems tensioning Megabolts off the CM,
very heavy tensioning equipment - We found that Megabolts were not flexible enough
in our operating environment - Also found them to be difficult to install and
post-grout
50ROOF RIB SUPPORT WORKSHOP - PENRITH
- Water was reported to be a major issue at
Springvale, can you outline what you use to
manage the mines water make? - Have a number of Air 2000 pumps, 3.7KW and 37KW
mono pumps - Typically have fish tanks every 3-4 pillars along
the longwall gateroads - Water is pumped out to surface via a series of
boreholes and in some instances we utilise a FBT
(frigging big tanks) to transport water from the
mine - We have also drilled a 1.2km long borehole in
advance of the longwall bleeder roadways to
pre-drain the installation face area of future
longwalls - It was noted that you are awaiting the
development of SDB. Hilti now have a self
drilling bolt available now, why not utilise it ? - The Hilti SDB system does allow the bolt to be
pre-tensioned - While Hilti have a SDB roof bolt, we have a
greater need for a SDB rib bolt - What type of rib mesh do you use along the
longwall block side of gateroads? - Steel rib mesh is now used although we were
previously using Tensar mesh
51ACARP
Australian Coal Association Research Program
- DEVELOPMENT AND OPTIMISATION OF CONTINUOUS MINERS
- (Best Practice Maintenance and Engineering)
- Alan Bruce, Crinum
52CONTINUOUS MINER WORKSHOP - MACKAY
- How much roof and rib support is installed at
Crinum? - In good roof conditions there are 6 x 2100mm roof
bolts installed per metre, with 2 x 1200mm steel
rib bolts on the chain pillar side and 3 x
cutables on the block side. When roof conditions
deteriorate there are 8 x 2100mm bolts installed
per metre. - Platforms on the ABM25(S), why do they raise and
lower? - Our ergonomist recommended that operators only
move their head through a 15 degree arc in order
to minimise pinching of discs in the neck, and
also required operators to be at a suitable
height relative to the drills rigs - The preferred operating height was above the
preferred maintenance height, and to lift the
machine components up 200mm to be above the work
platform would have increased the overall machine
height - Then decided to install a moveable platform which
was raised for operation and lowered for
maintenance, thereby putting the operators at the
correct height and avoiding increasing the
machine height - Where are the control for raising and lowering
the platforms? - There is another valve bank situated beside the
rib bolter controls to operate the platforms and
the mesh handler. - How far back from the face are the roof bolts
installed? - The roof bolts will be installed at 2.6m from the
face. - The Joy Sumps Shearer addressed many of the
ergonomic issues raised in your presentation, is
there any benefit in revisiting that machine as a
work platform? - The Sumps Shearer is no longer being considered
for development by Joy, but I definitely believe
it had potential. - What sort of improvement do you expect from the
new ABM25(S)? - The ABM25(S) is expected to give a 12 increase
in development productivity - What other improvement initiatives are being
considered with introduction of the ABM25(S)? - There are three different projects currently
being undertaken. One is the ventilation-monorail
system and its interface with the miner, the
second is the supply cassette system, and the
handling, carting and loading of supplies onto
the miner, the third is the electrical
requirements to run the machine, ie cable sizing
and handling.
53CONTINUOUS MINER WORKSHOP - POKOLBIN
- You stated that the work platform raised and
lowered some 200mm for maintenance, can you
explain that some more? - Our ergonomist recommended that operators only
move their head through a 15 degree arc in order
to minimise pinching of discs in the neck, and
also required operators to be at a suitable
height relative to the drills rigs - The preferred operating height was above the
preferred maintenance height, and to lift the
machine components up 200mm to be above the work
platform would have increased the overall machine
height - Then decided to install a moveable platform which
was raised for operation and lowered for
maintenance, thereby putting the operators at the
correct height and avoiding increasing the
machine height - What level of productivity improvement is
expected with the ABM25(s) at Crinum? - The ABM25(S) is expected to give a 12 increase
in development productivity - What was the increase in cost for the ABM25(S)
relative to a new CM? - I understand that VA spent some 6-7M to complete
the development - It cost BMA 0.5M more than an off the shelf
machine - Did it surprise you that you had to be so
proactive with OEMs? - I know what OEMs are like, they dont like making
changes - You have highlighted a number of changes to the
on-board ventilation system. Do you consider that
the on-board systems are worthwhile as compared
to a conventional ducting system? - Dont know, we have always had the on-board
system - Are any other changes to the roadway development
system at Crinum being considered? - Yes, always working to improve the system
- Looking at how to make the supply system work
better, including QDS attachments, etc - A participant noted that Crinum had developed and
fitted a simple device to the MBE that allowed
belt structure stands to be inserted with minimal
manual effort
54CONTINUOUS MINER WORKSHOP - PENRITH
- How well does the ABM25(S) break away and
complete cut throughs? - Same as the 12CM32, hasnt been identified as an
issue at this stage - With the electronic roof bolting controls is
there any ability to monitor bolt torque and
tension? - Yes, there is an ability to monitor all CM
functions and to record data on the surface - In regard to the specific drilling energy
function we monitor and record data for the two
outside roof bolts - Why have you fitted hydraulic traction drives on
the CM? - To create room on the machine, that is two motors
that are not required - Development and fitment of self drilling bolting
systems are likely to require on board chemical
injection storage and pumps and the space created
by fitting the hydraulic traction units will
allow retrofitting of SDB systems - What factors were identified by OEMs when they
did not submit tenders for development of the new
Crinum CM? - No analysis of why OEMs didnt submit tenders was
completed - Is Crinum a wet or dry pit?
- Dry now, although it was very wet initially
- Have you done any comparison of the availability
of the electronically controlled roof bolting
rigs? - Still working on the comparison although it
should be noted that we didnt have to send a
fitter into the panel for the first 6 weeks that
the bolters were being used (Note Crinum
standard panel manning does not include trades
personnel) - You seem to have had a fair budget available to
undertake all the necessary modifications? - Small changes were taken at a time, with
continual improvements being made over time
55CONTINUOUS MINER WORKSHOP - PENRITH
- You reported that you have just had your best
year of development at Crinum, what performance
rates were achieved, MPOH and metres overall? - Typically achieving 3.5 3.75MPOH
- Dont have an exact overall figure but it was the
most metres achieved in any one year and we only
operated the 3 CMs on a part time basis, rather
than on a full time basis as in previous years - Now that you have both upgraded 12CM32s and an
ABM25(s) available, do you have any preference on
how they will be deployed to mains and gateroad
drivage? - No preference however should note that we are
moving to a highwall operation at Crinum East and
there will be no mains development - You noted that you changed from gear pumps to
Rexroth pumps, were there any other changes
necessary to accommodate that change? - No, nothing different
- What did it cost for development of the ABM25(S)?
- BMA committed 300,000 up front to commence the
development process and I understand that VA
spent some 6-7M to complete the development - The machine as delivered will cost 4.8M
- What level of productivity improvement is
expected with the ABM25(s) and what other
improvements are contemplated in roadway
development at Crinum? - The ABM25(S) is expected to give a 12 increase
in development productivity - Other improvements include introduction of
monorail mounted ventilation systems and
improvements to handling and installation of roof
mesh and support materials
56ACARP
Australian Coal Association Research Program
- PANEL ADVANCES
- Jim Richardson, United
57PANEL ADVANCES WORKSHOP - MACKAY
- What improvements to the development services
time? - Panel advance could be sped up by utilisation of
Development monorail system. - Potential to get time down to 4.5 hours.
- Is there a specific development maintenance
window, and does maintenance get done during
development time? - Maintenance for the belt road equipment is linked
to a full shift (usually Thursday ) each week
when Stop Belt maintenance is carried out. - The travel road equipment is carried out when
services are being advanced after the travel road
miner has mined to 130m chainage. - Why does the mine work a five day roster, why not
seven day roster? - 5 days are enough to maintain longwall
continuity. - Rosters are simple.
- Management are not burnt out.
- We are not paying penalty rates.
- Do you utilise detailed procedures to ensure that
the belt extension process is consistently
repeated? - We have procedures detailed within the panel
folder however we tend to achieve repeatability
by utilising the same people to do the same job
each time, so there is not a need to constantly
refer to these procedures. - With the introduction of the contractor based
weekend production crews we have progressively
involved them in the process to the point that
this weekend they will complete their first solo
panel advance.
58PANEL ADVANCES WORKSHOP - POKOLBIN
- Can you go through the road clean up and cut
through holing process? - The travel road CM is advanced to 132m to
complete overdrive before being pulled back to
clean up travel road from outbye cut through to
face - Following clean up of travel road vent ducting is
recovered and the extension of services is
commenced - Belt road CM completes 20m overdrive in belt road
before commencing cut through - When belt road CM holes it takes about 2 hours to
complete bolt up, during which time a loader is
used to doze up belt road into overdrive - Belt road CM then trammed into belt road and an
LHD cleans up the cut through into belt road
overdrive, before CM trammed to face and loads
out stowage at face into shuttle car - Does the conduct of the panel advance on day
shift and out of cycle require specialisation
of day shift crew? - Yes, that is one of the keys to our success, with
the day shift crew developing their
specialisation and repeating it each 4 days, with
the same people doing the same thing each time - What type of LTU drives are installed?
- Eddy current winches which tension the belt to
7KN - What is the name of the day shift supervisor?
59PANEL ADVANCES WORKSHOP - PENRITH
- When do surveyors install the grade line and do
the belt bolt mark-up? - On the stop belt shift (typically Thursdays)
although may have to do it during the panel
advance if there is no belt stop shift between
panel advances - When are belt hanging bolts installed?
- On the stop belt shift (typically Thursdays)
although may have to do it during the panel
advance if there is no belt stop shift between
panel advances - Why not pre-hang the belt hanging chains rather
than hang them at the start of the belt move? - One fell down hit operator, and there have also
been reports of then falling down and catching
equipment - Doesnt add too much time
- We use fully encapsulated 2100mm belt hanging
bolts which are part of our roadway support
system - Participant reported that they pre-hung the
chains and marked the grade line on the chains to
expedite levelling of the conveyor structure - How long are the longwall blocks, and do you have
any problems pulling the belt out of the LTU over
that distance? - 3.2km long
- Problems are experienced at times due to soft
floor conditions in inbye section of panel,
however the utilise a second LHD to assist - Do you have any issues involving contractors in
panel advances given the strong union culture at
the mine? - Union role at mine not an issue, they have a
position of Board and employees are kept fully
informed on costs and profitability - Employees recognise that contractors are there to
assist them and to make the mine viable - Contractors used on panel advances are drawn from
other contract works being undertaken at the mine
at the time (eg secondary support, ventilation)
and are not specifically employed for panel
advances
60PANEL ADVANCES WORKSHOP - PENRITH
- When do you put the belt into the LTU?
- On the stop belt shift, approximately 2 hours
to install - How do you doze up the belt road?
- Use an LHD bucket to push up the floor material
rather than use it as a conventional loader
bucket. Then load it out with CM and shuttle cars - How do you install the belt structure when
pulling the boot end back with the LHD? - We crowd the boot end back into the bucket and
that separates the top and bottom belt and allows
the idlers to be inserted between the belt - Do you use the weekends when there is no
production scheduled to complete preparation
works for panel advance? - Previously we used weekends to catch up on the
belt hanging bolts, stone dusting and major
component changes on the equipment, and
maintenance of the travel road unit - Now are working a 7 day week with mine employees
on a 4X9.5 hour roster 4 days per week, with
Walters working other 3 days to catch up on a
development shortfall created by extended
equipment overhauls, geology and EA negotiations - Contractors trained to do belt advances and they
are completed as they fall - being utilised on 3X12
- What is the pillar cycle time?
- Typically 4 days in middle 20 pillars of gateroad
development, extending out to 5 days at start and
finish of panel due to mining conditions - Do you use a second DCB?
- Yes, use a second DCB to leapfrog belt road DCB
each pillar, with travel road CM powered directly
off transformer which is moved every 2 pillars as
part of panel advance
61PANEL ADVANCES WORKSHOP - PENRITH
- Do you have any views regarding roof and floor
mounted structure? - 1200mm belt operates at 5.2m/s and needs to be
high standard, and we utilise roof mounted
structure to provide a high standard longwall
ready conveyor - Minimal works are undertaken on completion of
gateroad development to get conveyor longwall
ready - What improvements could be made to panel advances
at United? - Considering use of monorail services management
system in both headings to take the extension and
relocation of panel services off the critical
path - Expect panel advances could then be completed in
4.5 hours - Do you use a breaker feeder?
- No, we load directly onto a grizzly style boot
end - The overall system is currently in balance and do
not require a breaker feeder for surge capacity - Do you mine any rock at all?
- Yes, seam thins at inbye end of longwall blocks
and we take up to 400mm of roof stone - Not a problem for conveyor system
- Which miner completes the cut through?
- Belt road CM completes the cut through
- The travel road CM pulls up at 132m after
completing overdrive and is then pulled back to
clean up travel road from outbye cut through to
face (while belt road CM completes hole through),
before recovering vent ducting and commencing
extension of services