Title: TUNNELS
1TUNNELS
2TERMINOLOGY for UNDERGROUND STRUCTURES
- Adit.....................................galeri
- Tunnel................................tünel
- Subway..............................metro
- Shaft...................................baca
- Chamber............................oda
- Portal.................................ana giris
veya çikis - Pilot adit.............................yan
galeri, pilot galerisi - Centre................................merkez,
eksen - Face...................................ayna
- Wall site..........................yan, kenar,
duvar - Floor...................................taban
- Roof...................................tavan
3- Overbreak.............................asiri
sökülme - Excavated profile..................kazi profili
- Natural archling....................dogal
kemerlenme - Load......................................yük
- Support.................................destek,
iksa - Failure...................................yenilme,
çökme - Gentle failure........................yavas
yenilme - Rock burst............................kaya
patlamasi - Squeezing ground................sikisan zemin
- Swelling ground....................sisen zemin
- Clay-filled joint.......................kil
dolgulu eklem - Long term stability.................uzun süreli
duraylilik - Ground treatment..................zemin
iyilestirmesi - Support before excavation....kazi öncesi
destekleme
4- Jet grouted roof cover..............jet grouting
ile iyilestirilmis tavan örtüsü - Shotcrete initial lining..............püskürtme
beton baslangiç çizgisi - Jet grouted floor cover............jet grouting
ile iyilestirilmis döseme - Top heading............................kalot
(Crown) - Invert.......................................stros
(Bottom excavation) - Bench......................................üzengi
çizgisi - Final concrete lining................sonuncu
beton kaplama (nihai beton kaplama çizgisi) - SHIELD tunnelling method..............KALKAN
Yöntemi - CUT COVER tunnelling method....AÇ-KAPA Yöntemi
- TBM (Full face Total Boring Machine).....TÜM
KESIT KAZI MAKINASI
5TERMINOLOGY for EXCAVATIONS of ROCKS SOILS
- DRILLING....................Sondalama
- Hardness.........................Sertlik
- Toughness.......................Dayanim direnç
- Abrasiveness...................Asindiricilik
- Structure..........................Jeolojik yapi
- Drilkling fluids..................Sondaj sivisi
- AUGERING..................Burgulama
- MACHINE BORING.....Mekanize tünel açma
- Total Boring Machine (TBM)
- Full face excavation
- BLASTING...................Patlatma
6- SCRAPING...................Kazima (makinayla)
- RIPPING.......................Kirarak kazima
- DIGGING......................Kazma
- GROUND WATER........yeraltisuyu
- Control of groundwater
- Groundwater flow
- Rate of flow
- Volume of flow
- Boundaries
7TUNNEL DESCRIPTION
- Made into natural material (rocks)
- Empty inside
- Carry the loads itself
- Both ends are open to atmosphere
- Generally horizontal
- Thick walled structure looks like cylinder
8(No Transcript)
91- Kilit (anahtar) tasi........................Key
stone 2- Kemer...................................
........Arch 3- Ayak (duvar)......................
..........Wall 4- Taban...........................
................Floor 5- Üzengi...................
.......................Bench 6- Üzengi çizgisi
(düzeyi)...............Bench line or plane 7-
Kalot............................................T
op heading 8- Stros...............................
.............Invert 9- Ano........................
......................Ano (unit)
10Tunnel Section for Swelling Ground
1- Digging section 2- Support 3- Swelling
section 4- Pressurized area 5- Flow direction of
water
11SURFACE EXCAVATIONS
12UNDERGROUND EXCAVATIONS
- In Rock
- In Sediment
- Stability Arching
- Water
- Dry tunnel...............above water table
- Wet tunnel..............below water table
- Gases
- Carbon dioxide (CO2)
- Carbon monoxide (CO)
- Methane (CH4)
- Hydrogen sulphide (H2S)
- Other gases
13- Gas bursts......................gaz patlamasi
- Rock falls........................kaya düsmesi
- Rock bursts....................kaya firlamasi
- Squeezing ground..........sisen kabaran zemin
- Temperature
- Subsidence
14EXPLORATION INVESTIGATIONS RELATED of SLOPE
STABILITY
- Geomorphologic maping and preparation of
longitudinal cross sections - Geological maping surveyings (aerial
photographs) - Geophysical surveyings
- Underground explorations, boreholes
- Ground water surveyings
- Laboratory tests
- Model studies
15SURFACE EXCAVATIONS
- Permanent
- Short term excavations
16SUBSURFACE EXCAVATIONS
- GEOLOGY
- Soil profile or hard rock geology
- Structure
- Ground water (hydrogeology)
- Stability
17- INVESTIGATIONS
- Mapping (Topographic, geologic, etc...)
- Geophysical surveying (especially seismic
velocity of rocks) - Trial pits boreholes
- General and local stability analysis
- Decide to excavation method
18(No Transcript)
19UNDERGROUND EXCAVATIONS
- Adit, shaft, incline, large chamber
- Tunnel
- Subway metro
- Underpass
- Shelter
- Power house
- Ware house, store, mining ...etc
20GASES (can be lethal or burst)
- Carbon monoxide (CO) 0.97 of air
- Carbon dioxide (CO2) 1.53 of air
- Methane (CH4) 0.55 of air
- (Highly explosive with air) marsh gas
- Hydrogene sulphide (H2S) 1.19 of air
- (Highly toxic and explosive)
- Sulphur dioxide (SO2)
21- ROCK FALL
- SQUEEZING GROUND (sand, silt, shale, clay)
- ROCK BURST
- BULKING (Increase in volume, 10-40)
22FACTORS EFFECTING EXCAVATION of ROCKS
- Mineralogical composition of rocks
- Texture fabric
- Petrographic features
- Structure
- Rock mass
- Strike dip of beds in relation to face of
excavation - Intensity of tectonic disturbances
- Degreee of weathering
23RESISTANCE of ROCKS to EXCAVATION
- Loose soils
- Soil easy to spade (bel ile kazmak)
- Soil easy to dig
- Crumbling weak rocks (ufalamak)
- Rocks easy to blast
- Rocks difficult to blast
- Rocks very difficult to blast
24TUNNELLING METHODS
25SHIELD TUNNELLING METHOD
- This method involves the use of shield machine to
drive the tunnels below the ground. - After completion of a work shaft, the shield
machine is lowered into the shaft and assembled
there before excavation and construction of the
tunnels using precast concrete lining segments of
about 1.2 meter width. - This construction method causes minimal
disruption to traffic and the environment because
all the work takes place below ground and the
ground level environment is unaffected.
26(No Transcript)
27CUT and COVER TUNNELLING METHOD
- This construction method, whereby the site is
fully excavated, the structure built and then
covered over, uses diaphragm walls as temporary
retaining walls within the site area. - Step one Construction of diaphragm walls, pin
piles, and decking. - Step two Excavation within the diaphragm walls,
installing struts as work progresses. - Step three Construction of permanent floor slabs
and walls. - Step four Fitting out the internal structures,
backfilling, and reinstating the surface
structures.
28(No Transcript)
29TBM (Tunnel Boring Machine)
- Mechanical-support TBM
- Compressed-air TBM
- Slurry shield TBM
- Earth pressure balance machine
- Mixed-face shield TBM
301- Mechanical Support TBM
- A mechanical-support TBM has a full-face
cutterhead which provides face support by
constantly pushing the excavated material ahead
of the cutterhead against the surrounding ground.
312- Compressed-Air TBM
- A compressed-air TBM can have either a full-face
cutterhead or excavating arms. Confinement is
achieved by pressurizing the air in the cutter
chamber.
323- Slurry Shield TBM
- A slurry shield TBM has a full-face cutterhead.
Confinement is achieved by pressurizing boring
fluid inside the cutterhead chamber.
334- Earth Pressure Balance Machine
- An earth pressure balance machine has a full-face
cutterhead. Confinement is achieved by
pressurizing the excavated material in the
cutterhead chamber.
345- Mix-Face Shield TBM
- Mix-face shield TBMs have full-face cutterheads
and can work inclosed or open mode and with
different confinement techniques.
35EFFECT of GEOLOGICAL STRUCTURES to TUNNEL
EXCAVATION
- Effect of soil layers horizontal, vertical and
inclined layers have different kinds of loading
conditions for tunnels.
36- Effect of faults the relation between the fault
slope direction and the tunnel direction, width
of the fault zone, type and thickness of the fill
material and the hydrostatic pressures in both
sides of the fault are some problems in the
tunnelling.
Relation between the fault zone and the tunnel
37- Tunnel excavations in the slopes the
discontinuities (layers, fissures) inclined
inside or outside of the slope are very important
regarding the stress and strength of the tunnel.
38- Effect of the folds While tunnel is excavated in
an area that contains folded rocks, different
stresses and conditions may occur depending on
the fold type.
Fold axis and the tunnel direction is parallel
Fold axis and the tunnel direction is vertical
39CLASSIFICATION of ROCKS for TUNNELING PURPOSES
40- Classification of rocks for engineering purposes
is needed in analyzing the project costs and to
obtain an economic and reliable solution. - The classification of the rocks, that the tunnel
will be constructed in, is first done by
Terzaghi. But, it is too general and gives
qualitative results.
41TUNNEL ROCK CLASSIFICATION by TERZAGHI
42Laufer classified tunnel rocks to 7 groups
according to stand-up time
43Rock classification and determination of
unsupported span
44URFA IRRIGATION TUNNEL
45(No Transcript)
46ONE of the LONGEST IRRIGATION TUNNELS in the WORLD
47- Consist of two concrete lined tunnels each of
which is 7.62 m in diameter and 26.4 km in length
discharging water from the reservoir of Atatürk
Dam.