Immersed Tunnels - PowerPoint PPT Presentation

1 / 44
About This Presentation
Title:

Immersed Tunnels

Description:

Immersed Tunnels Typically, an immersed tunnel is made by sinking precast concrete boxes into a dredged channel and joining them up under water. – PowerPoint PPT presentation

Number of Views:899
Avg rating:3.0/5.0
Slides: 45
Provided by: www2CeMe
Category:
Tags: immersed | tunnels

less

Transcript and Presenter's Notes

Title: Immersed Tunnels


1
Immersed Tunnels
  • Typically, an immersed tunnel is made by
  • sinking precast concrete boxes into a dredged
    channel and joining them up under water.
  • Tunnel sections in convenient lengths, usually 90
    to 150 meters, are placed into a pre-dredged
    trench,
  • joined, connected and protected by backfilling
    the excavation.
  • The sections may be fabricated in shipyards, in
    dry docks, or in temporary construction basin
    serving as dry docks.

2
(No Transcript)
3
  • Immersed tunnels are,
  • more advantegous as a subaquous solution in soft
    soils
  • increasingly used alternative to traditionally
    used shield tunnelling, without having the risks
    associated with pressure chambers and inrush of
    water.
  • also suitable in water deeper than it is possible
    with the shield method, which essentially is
    restricted to less than 30 m of water (concerning
    the maximum air pressure at which workers can
    safely work).
  • Advantegous as there is less loss in height than
    with tunnelling deeply under the riverbed, and
    the tunnel may therefore be shorter overall.

4
  • The world's longest and deepest application to
    date is the twin-tube subway crossing of San
    Francisco Bay, constructed between 1966 and 1971
    with a length of 3.6 miles (5,8 km) in a maximum
    water depth of 41 m. The 100 m long, 15 m wide
    sections were constructed of steel plate and
    launched by shipbuilding procedures.
  • The first tunnel of the concrete type was
    constructed in 1940 in Rotterdam under the Maas
    estuary.

5
  • The most profound effect of an immersed tunnel on
    the environment concerns the element it is meant
    to bypasswater.
  • The influence of the tunnel on the groundwater
    and the surface water in the area plays a
    predominant role in the tunnel design and
    construction methods.
  • An aspect of more recent concern affecting
    construction is the possible presence of
    contaminated soils that must be removed for the
    tunnel trench. Ways of removing these soils and
    transporting them to depositories that are
    especially equipped to receive them are
    environmental problems requiring novel techniques
    and quality control procedures.
  • The more traditional environmental aspects are
    those encountered on any construction job noise,
    dirt, and traffic hindrance.

6
  • The top of the tunnel should be protected by
    adequate protective backfill, extending about 30
    m on each side of the structure and confined
    within dykes or bunds. The fill must be protected
    against erosion by currents with a rock blanket,
    protective rock dykes or other means.
  • Tides and current effects of the waterway must be
    evaluated to determine conditions during dredging
    and tube sinking operations.
  • Importantly, dredging and backfilling operations
    should be executed in such a manner as to limit
    disturbance in the natural ecological balance at
    the construction site.
  • Governmental agencies having jurisdiction over
    environmental protection, natural resources or
    local conditions must be consulted and approval
    of authorities should be obtained in the
    preliminary design stage.

7
  • Foundation
  • The foundation method to be used must be chosen
    with due consideration, first of all, for the
    subsoil conditions and the degree to which the
    tunnel will be subject to dynamic loadings, and
    earthquake loadings in particular. Pile
    foundations are an option but this solution has
    been used for a few tunnels only.
  • For both steel and concrete types of tunnels, the
    main tasks are
  • Excavation of a tunnel trench to specifications
    and to keep it free of siltation that may be
    detrimental to the permanent foundation until
    this foundation has been constructed and the
    tunnel has been brought to rest on it.
  • Construction of watertight and durable tunnel
    elements.
  • Installation of the tunnel elements in the tunnel
    trench.
  • Construction of watertight and durable joints
    between the tunnel elements.
  • Construction of a durable foundation for the
    tunnel.

8
  • Once completed, an immersed tunnel is no
    different operationally from any other tunnel.
    However, it is built in a completely different
    way.
  • The Construction technique
  • A trench is dredged in the bed of the water
    channel.

9
  • Tunnel Trench Dredging
  • The dredging works required for the construction
    of an immersed tunnel will normally comprise
    some, or all, of the following items
  • Dredging of a casting or launching basin.
  • Dredging of test pits in the waterway for
    evaluation of siltation of tunnel trench.
  • Widening of the existing navigation channel in
    order to provide temporary navigation channels
    outside the marine working area.
  • Compensation grouting to make up for the
    reduction of the waterway cross section caused by
    the permanent tunnel works, and thereby avoiding
    changes in hydrographical and biological
    conditions in the waterway.
  • Dredging of the tunnel trench for the immersed
    tunnel section.
  • Dredging of an access channel between the
    casting/launching basin and the tunnel trench.
  • Maintenance dredging.

10
  • The dredging volume is generally in the order of
    l million m3 per km for a typical four-lane
    motorway tunnel.
  • The excavation must provide space for the
    prefabricated tunnel body the sand or gravel
    foundation under the body as wells as the
    protective backfill on the sides and on the top
    of the tunnel.
  • Because the top of the backfill has to be kept
    below the existing or future navigation channel
    profile, a trench bottom level at between 25 and
    30 m below Low Water level is quite common.
    Immersed tunnels in deep or open sea may require
    specially built dredgers.

11
  • Except for cases where very soft subsoil, deemed
    unsuitable for support of the tunnel, has to be
    removed and replaced by suitable materials, the
    general requirements for the dredging of the
    trench bottom are
  • A clean, even surface, as close as possible to
    the upper acceptable limit in order to avoid the
    economic consequences of having to fill
    overdredged areas
  • A minimum disturbance of the remaining exposed
    upper soil layers in the trench bottom, in order
    to limit the changes in the geotechnical
    characteristics of the subsoil.
  • The possible physical disturbance and softening
    of the exposed soil layers in the trench bottom,
    particularly in cohesive subsoils, can have a
    considerable influence on the geotechnical
    behaviour of these soil layers later-and, hence,
    on the quality of the tunnel support as a whole.
    This in turn influences the design of the
    structural tunnel body and, thus, eventually the
    overall economy. These technical requirements
    are met by
  • Using the proper type of dredger(s).
  • Careful controlling the position of the cutting
    tool, bearing in mind that the dredging normally
    has to be done in tidal waters and sometimes in
    waters subject to swell and waves.
  • Careful planning the dredging operation in order
    to avoid undesirable failures of the slopes.
  • Timing of the dredging operation, in order to
    limit the time that the trench bottom is exposed
    and, at the same time, to limit the sedimentation
    caused by subsequent dredging nearby.

12
(No Transcript)
13
  • Construction of Tunnel Elements
  • The tunnel elements are made fully or partially
    buoyant by means of temporary bulkheads installed
    at the element ends.
  • In addition to providing proper structural
    strength and controlling the weight of the
    element, the main design and construction task of
    the reinforced concrete tunnel is to provide a
    watertight structure. For many years, the answer
    was to wrap the tunnel element in a watertight
    membrane composed of steel on the bottom, outer
    walls and even on the roof. Alternatively,
    bituminous membrane has been used on the outer
    walls and roof.
  • In recent years, reinforced concrete tunnels
    without a membrane at all are being used. Above
    all, this will require sophisticated control of
    concrete temperature during hardening to avoid
    cracking. In order to reduce the development of
    cracks during hardening, primarily in the walls
    when they are cast after the bottom slab, cooling
    of the lower part of the walls has been the
    practice for many years. Insulation of the
    formwork and careful sequencing of stripping of
    the forms are also used to control the concrete
    temperature.
  • Improved field concrete technology aimed at
    minimising the development of cracks during
    hardening, combined with moderate prestressing,
    seems to be the course to follow.

14
  • Tunnel elements are constructed in the dry, for
    example in a casting basin, a fabrication yard,
    on a ship-lift platform or in a factory unit.

15
  • Casting Basins
  • The tunnel elements can be prefabricated in a
    casting basin or in a dry dock. For shorter
    roadway and railroad tunnels, the elements are
    normally cast in one batch in a casting basin. A
    programme for control of concrete density and
    concrete dimensions is required in order to
    control the weight and displacement of the tunnel
    elements.
  • The typical casting sequence is
    bottom/walls/roof, but sometimes all at once, in
    15-20 m segments.
  • The tunnel elements can be monolithic, or they
    can be provided with flexible joints between
    tunnel segments within the elements. The latter
    arrangement minimises longitudinal bending
    moments caused by compression of the subsoil in
    the permanent stage, but is unsuitable for
    railway tunnels in soft ground and in seismic
    regions.
  • Normally the tunnel elements will be buoyant and
    need to be ballasted prior to flooding of the
    casting basin in order to make sure that they
    remain parked until they are to be brought to
    the immersion location. This ballasting is
    normally done with water contained in
    purpose-built ballast tanks inside the tunnel
    element. Pumps and associated pipelines allow
    charging and removal of the ballast. A number of
    lifting eyes and bollards must be provided on the
    element roof.
  • Watertight, temporary bulkheads are installed at
    the ends of the element, and rubber gaskets are
    mounted around the periphery of the one end of
    the tunnel element, while a plane steel plate is
    provided at the opposite end. Later, when the
    tunnel element is joined to the previously placed
    tunnel element, this gasket provides a watertight
    seal between the two tunnel elements.
  • As the casting basin is flooded or as the tunnel
    is launched from the dock, the tunnel element is
    checked for watertightness, the attention being
    directed principally towards the temporary
    bulkheads and pipe let-ins.
  • Recently a system of constructing concrete tubes
    on floating pontoons is developed. By removing
    the need for casting basins on the river or canal
    costs are reduced, and the process is more
    environmentally friendly.

16
Cooling of concrete in outer tunnel walls
17
  • The ends of the element are then temporarily
    sealed with bulkheads.
  • Each tunnel element is transported to the tunnel
    site - usually floating, occasionally on a barge,
    or assisted by cranes.

18
  • Installation of tunnel elements in the trench
  • For transportation of the element from the
    flooded casting basin or dock to the tunnel
    trench, conventional towage is normally used.
  • The warping, which ends with the tunnel element
    being moored for immersion, is normally carried
    out by the contractor's organisation responsible
    for the subsequent sinking and joining, whereas
    towing normally is done by experienced towage
    companies.
  • The immersion of the tunnel element is carried
    out after the tunnel element bas been moored and
    the element has been ballasted as necessary to
    provide adequate loads in the immersion tackles.

19
  • The tunnel element is lowered to its final place
    on the bottom of the dredged trench.

20
  • The new element is placed against the previous
    element under water. Water is then pumped out of
    the space between the bulkheads.
  • Water pressure on the free end of the new element
    compresses the rubber seal between the two
    elements, closing the joint.

21
  • Once placed, the elements are joined first by
    bringing rubber gasket at the joint into contact
    with the steel face of the previously placed
    tunnel element, and then draining the joint
    chamber, thereby mobilising the full hydrostatic
    water pressure on the tunnel cross section remote
    end.

22
  • Backfill
  • material is placed beside and over the tunnel to
    fill the trench and permanently bury the tunnel,
    as illustrated in the figures.

23
  • Approach structures can be built on the banks
    before, after or concurrently with the immersed
    tunnel, to suit local circumstances.

24
  • Immersed tunnels have been in widespread use for
    about 100 years. Over 150 have been constructed
    all over the world, about 100 of them for road or
    rail schemes. Others include water supply and
    electricity cable tunnels. The examples given
    indicate the diversity of projects that have been
    realized.

25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
  • Immersed tunnels do not suit every situation.
    However, if there is water to cross, they usually
    present a feasible alternative to bored tunnels
    at a comparable price, and they offer a number of
    advantages, such as
  • Immersed tunnels do not have to be circular in
    cross section. Almost any cross section can be
    accommodated,
  • making immersed tunnels particularly attractive
    for wide highways and combined road/rail tunnels.
    Some examples of realised cross sections are
    shown below.

29
  • Immersed tunnels can be placed immediately
    beneath a waterway. In contrast, a bored tunnel
    is usually only stable if its roof is at least
    its own diameter beneath the water. This allows
    immersed tunnel approaches to be shorter and/or
    approach gradients to be flatter - an advantage
    for all tunnels, but especially so for railways.

30
  • expensive, such as the soft alluvial deposits
    characteristic of large river estuaries. They can
    also be designed to deal with the forces and
    movements in earthquake conditions, as in the
    example illustrated above, to be placed in very
    soft ground in an area prone to significant
    earthquake activity.

31
  • Bored tunnelling is a continuous process in which
    any problem in the boring operation threatens
    delay to the whole project.
  • Immersed tunnelling creates three operations -
    dredging, tunnel element construction and tunnel
    installation, which can take place concurrently,
    thus moderating programme risk considerably.
  • Partly for this reason, an immersed tunnel is
    generally faster to build than a corresponding
    bored tunnel.

32
ARE THERE ANY SPECIAL PROBLEMS ?
  • Immersed tunnels are sometimes perceived by
    newcomers to the technology as "difficult" due to
    the presence of marine operations. In reality
    though, the technique is often less risky than
    bored tunnelling and construction can be better
    controlled. The marine operations, though
    unfamiliar to many, pose no particular
    difficulties.

33
The perceived problems include
  • DREDGING
  • Dredging technology has improved considerably in
    recent years, and it is now possible to remove a
    wide variety of material underwater without
    adverse effects on the environment of the
    waterway.

34
  • INTERFERENCE WITH NAVIGATION
  • Interference with navigation On busy waterways,
    it is sometimes assumed that construction of an
    immersed tunnel would be impractical as it would
    interfere with shipping. In fact, such tunnels
    have been successfully built in some
    exceptionally busy waterways without undue
    problems.

35
  • WATERTIGHTNESS
  • It is often assumed that the process of building
    a tunnel in water, rather than boring through the
    ground beneath it will increase the likelihood of
    leakage. In fact, immersed tunnels are nearly
    always much drier than bored tunnels, due to the
    above-ground construction of the elements.
    Underwater joints depend on robust rubber seals
    which have proved effective in dozens of tunnels
    to date.

36
A NEW DEVELOPMENT THE SUBMERGED FLOATING TUNNEL
  • Traditional immersed tunnelling results in a
    tunnel buried beneath the waterway which it
    traverses. A new development- the submerged
    floating tunnel - consists of suspending a tunnel
    within the waterway, either by tethering a
    buoyant tunnel section to the bed of the
    waterway, or by suspending a heavier-than-water
    tunnel section from pontoons.
  • This technique has not yet been realised, but one
    project, in Norway, is currently in the design
    phase. The submerged floating tunnel allows
    construction of a tunnel with a shallow alignment
    in extremely deep water, where alternatives are
    technically difficult or prohibitively expensive.
    Likely applications include fjords, deep, narrow
    sea channels, and deep lakes.

37
Design Aspects of Immersed Tunnels
  • The starting point of an immersed tunnel design
    is required cross-sectional area i.e. the hollow
    space. The tunnel must have the same number of
    traffic lanes as the road.
  • Dimensional requirements vary from country to
    country generally speaking the lanes should be
    3,5 m wide with headroom above, depending on
    local regulations (e.g. 4.5 m for Holland).
  • There should also be a clearance from the
    carriageway to the walls of 0.8 to 1.0 m, for
    broken down cars. The clearance will also reduce
    the wall effect drivers shying away from the
    wall thereby reducing the capacity of the road.
    Above the headroom there should be adequate room
    for ventilation booster fans, luminaries and
    signal equipment. In the dual-carriageway tunnels
    there is often a service gallery for cables
    located between the traffic tubes.

38
  • Design for floating
  • After construction, the elements are floated to
    their final position. The element is then made
    heavier than its displacement by means of
    temporary ballast (often water), after being
    temporarily supported by the immersion rigs. At a
    later stage this ballast is replaced by
    definitive ballast in the shape of non-reinforced
    concrete below the future carriageway or
    externally, or other secondary interior
    structural concrete. By this time the immersion
    equipment and bulkheads will have to be removed.
    The element must now weigh sufficiently more than
    its buoyancy to remain in place.
  • The pressure head of the groundwater below the
    tunnel base may lag behind the water level in the
    river. At low tide this may result in an
    additional upward force. To compensate for
    effects of this kind, the design criterion often
    adopted at this stage is that the weight of the
    tunnel must exceed the water displacement by an
    absolute minimum margin against flotation when
    all removable items and backfill are removed.
    This floation margin may be in the range of
    1.075, but is determined on a project basis. The
    safety margin is later increased because the
    sides and top of the dredged trench into which
    the tunnel was placed is then backfilled.
  • This results in the first place in a load on the
    roof whereas friction on the walls is ignored.
    Erosion protection is placed to continuously
    maintain a 1.15 or 1.2 factor of safety against
    flotation, depending upon the clients
    requirements, and safety against sinking ships
    and dropping anchors.

39
  • At the transport stage ,
  • Weight 0.99 maximum water displacement or
  • 2.46 S 3.0 0.99 (B H S) (1)
  • A value of 2.46 will be taken as the specific
    weight of reinforced concrete in the flotation
    stage, and a density of 2.42 in the final stage.
  • In the final phase a counter-flotation margin
    should apply,
  • assume this margin to be 7,5 per cent, hence
  • Weight 1.075 water displacement, or
  • 2.42 S 2.25 B 1.075 (B H S) (2)

40
Case study Øresund Link Strait crossing
  • The Øresund link connects Copenhagen on Zealand,
    Denmark to Malmö in Sweden thus establishing a
    land traffic corridor from Scandinavia to the
    continent. The link comprises a 3.5 km immersed
    tunnel, 4 km artificial island, and 8 km bridge,
    including a 490 m span cable-stayed bridge. The
    link incorporates approximately one million m³ of
    concrete, of which more than two thirds
    constitute the immersed tunnel.
  • The Øresund Tunnel was motivated by the fact that
    one of the main shipping lane is very close to
    the Copenhagen international airport, making a
    high bridge over the nearest navigational channel
    unfeasible.

41
  • The tunnel cross-section accommodates two tubes
    for the two-track railway and two tubes for the
    four-lane motorway. A central installation
    gallery between the motorway tubes doubles as a
    safe and smoke-free escape route in case of
    emergency.
  • The immersed part of the tunnel consists of 20
    elements, each approximately 175 m long,
    resulting in a total immersed tunnel length of
    3,510 m. Each element is made from 8 segments,
    joined together by temporary prestressing, and
    weighing approximately 56,000 t. The outer
    cross-sectional dimensions are 8.6 m by 38.8 m,
    the height being governed by the railway
    clearance profile. The track is fastened directly
    to the bottom slab, the omission of the ballast
    reducing the required tunnel height. The elements
    were placed in a pre-dredged trench, and founded
    on a gravel bed. Backfilling along the sides and
    on the roof was designed to offer a permanent
    cover and protection of the tunnel in all
    situations.
  • The final tunnel profile is in general below
    seabed level, and at the Drogden navigation
    channel the top of the cover is 10 m below water
    level. The rock cover was designed to withstand a
    falling or dragging anchor, or a sunken ship.
    Furthermore the protective layer is stable
    against scour and erosion caused by currents or
    ship propellers.

42
  • All 20 Tunnel elements were fabricated in a
    purpose-built casting yard. The precast facility
    applied production techniques developed and
    tested in the construction of bridges over the
    last 20 years, but it was the first time these
    techniques were applied to immersed tunnel
    construction, involving casting and in
    incrementally launching segments weighing up to
    7,000 t and elements of 56,000 t.
  • Factory conditions were achieved by the erection
    of sheds where the reinforcement was assembled
    and prefabricated. A central shed covered two
    production lines, where two segments were made
    simultaneously per week, in order to meet the
    time schedule. Each 22 m segment was constructed
    on specially prepared formwork, being cast in one
    single pour of 2,800 m³ of concrete over a
    30-hour period. By casting an entire segment in a
    single operation production was sped up, and
    thermal cracking of the concrete was minimized. A
    crack-free concrete is essential, since the
    tunnel design does not include a watertight
    membrane.

43
(No Transcript)
44
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com