Title: ROUGHCUT CAPACITY PLANNING
1ROUGH-CUTCAPACITY PLANNING
- Validating The MPS (Sort Of)
- Bills Of Materials Routings
- Capacity Planning Using Overall Factors
- Capacity Bills
- Picking A RCCP Technique
2CORE MRP II
MANUFACTURING RESOURCE PLANNING
3VALIDATING THE MPS (SORT OF)
- Need to ensure that MPS is feasible
- MPS must not require more capacity then is
available - Use rough-cut capacity planning techniques to
estimate capacity needs in each workcenter - Labor requirements
- Machine requirements
- Compare capacity needed to planned available
capacity - Adjust MPS if workcenters are overloaded
4VALIDATING THE MPS (SORT OF)
- RCCP eliminates MPS's which drastically overload
some workcenters - Low computational expense
- Rapid calculation for what-if analysis
- Not 100 accurate
- Does not use material plans
- All RCCP ignores actual lot-sizing, beginning
inventory, work-in-process
5VALIDATING THE MPS (SORT OF)
- Information requirements for all RCCP techniques
- Bills of Materials (BOMs)
- Show how products are put together
- Routings
- Show where products and component parts are made
6BILLS OF MATERIALS
- BOM's show how parts combine to create a product
- Representation may be graphical
7BILLS OF MATERIALS
- Indented BOMs are common as computer printouts
- X
- A
- B
- A
- Y
- B(2)
- A
8ROUTINGS
- A routing lists the
- Operations necessary to make a part
- Workcenters where the operations are performed
- The routing also lists the expected capacity
needed at each operation - Per setup
- Per unit
9STANDARD TIMES
- A standard time per unit includes the runtime and
an allocated portion of the setup time - Standard times assume an average lot size
- Used in RCCP since actual lot sizes for parts
ignored
10CAPACITY PLANNING USING OVERALL FACTORS
- Simplest and least accurate RCCP method
- For N products, W workcenters, and a planning
horizon of T periods, requires only N W 1 rows
and T columns in a spreadsheet -
- Ignores current product mix, lead times
- Therefore appropriate if lead time is short and
product mix is steady over time
11CAPACITY PLANNING USING OVERALL FACTORS
- Determine cumulative standard times for each
product - Apply cumulative standard times from (1) to MPS
to determine total required capacity per period
for facility - Determine planning factors expressing of
facilty capacity historically used in each
workcenter - Apply planning factors from (3) to facility
capacity from (2) to determine capacity
requirements per period for each workcenter
12CUMULATIVE STANDARD TIMES
- The Cumulative Standard Time is the time required
to make a unit of a part from scratch - STi,j Incremental standard time to make part i
in workcenter j - CSTi,j Cumulative standard time to make part i
and all component parts in workcenter j - CSTi Cumulative standard time to make part i
and all component parts in all workcenters
13CUMULATIVE STANDARD TIMES
14CUMULATIVE STANDARD TIMES
15CUMULATIVE STANDARD TIMES
16CAPACITY PLANNING USING OVERALL FACTORS
- Determine cumulative standard times for each
product CSTX 2.05 CSTY 4.60
17CAPACITY PLANNING USING OVERALL FACTORS
- 2. Apply cumulative standard times from (1) to
MPS to determine total required capacity per
period for facility CSTX 2.05 CSTY 4.60
18CAPACITY PLANNING USING OVERALL FACTORS
- 2. Apply cumulative standard times from (1) to
MPS to determine total required capacity per
period for facility CSTX 2.05 CSTY 4.60
19CAPACITY PLANNING USING OVERALL FACTORS
- Determine planning factors expressing of
facilty capacity historically used in each
workcenter - Workcenter W101 70
- Workcenter W102 30
20CAPACITY PLANNING USING OVERALL FACTORS
- 4. Apply planning factors from (3) to facility
capacity from (2) to determine capacity
requirements per period for each workcenter - Workcenter W101 70
- Workcenter W102 30
21CAPACITY PLANNING USING OVERALL FACTORS
- 4. Apply planning factors from (3) to facility
capacity from (2) to determine capacity
requirements per period for each workcenter - Workcenter W101 70
- Workcenter W102 30
22CAPACITY PLANNING USING OVERALL FACTORS
- 4. Apply planning factors from (3) to facility
capacity from (2) to determine capacity
requirements per period for each workcenter - Workcenter W101 70
- Workcenter W102 30
23CAPACITY BILLS
- Slightly more computationally complex and more
accurate than CPOF - For N products, W workcenters, and a planning
horizon of T periods, requires N(W 1) 1 rows
and T columns in a spreadsheet -
- Ignores lead times
- Therefore appropriate if lead time is short
24CAPACITY BILLS
- Determine cumulative standard times per
workcenter for each product - Apply cumulative standard times per workcenter
from (1) to MPS to determine capacity
requirements per period for each workcenter
25CUMULATIVE STANDARD TIMES
26CAPACITY BILLS
- Determine cumulative standard times per
workcenter for each product - CSTX,W101 1.25
- CSTX,W102 0.80
- CSTY,W101 3.00
- CSTY,W102 1.60
27CAPACITY BILLS
- 2. Apply cumulative standard times per workcenter
from (1) to MPS to determine capacity
requirements per period for each workcenter - CSTX,W101 1.25 CSTX,W102 0.80 CSTY,W101
3.00 CSTY,W102 1.60
28CAPACITY BILLS
- 2. Apply cumulative standard times per workcenter
from (1) to MPS to determine capacity
requirements per period for each workcenter - CSTX,W101 1.25 CSTX,W102 0.80 CSTY,W101
3.00 CSTY,W102 1.60
29CAPACITY BILLS
- 2. Apply cumulative standard times per workcenter
from (1) to MPS to determine capacity
requirements per period for each workcenter - CSTX,W101 1.25 CSTX,W102 0.80 CSTY,W101
3.00 CSTY,W102 1.60
30CAPACITY BILLS
- 2. Apply cumulative standard times per workcenter
from (1) to MPS to determine capacity
requirements per period for each workcenter - CSTX,W101 1.25 CSTX,W102 0.80 CSTY,W101
3.00 CSTY,W102 1.60
31CAPACITY BILLS
- 2. Apply cumulative standard times per workcenter
from (1) to MPS to determine capacity
requirements per period for each workcenter - CSTX,W101 1.25 CSTX,W102 0.80 CSTY,W101
3.00 CSTY,W102 1.60
32PICKING A RCCP TECHNIQUE
- Stable demand and product mix?
- Use CPOF
- Changing mix but short lead times?
- Use capacity bills
- Changing mix and long lead times?
- Use resource profiles
-