Title: Master Scheduling and RoughCut Capacity Planning
1Master Scheduling and Rough-Cut Capacity Planning
2Learning Objectives
- Explain the role objectives of a master
production schedule - Explain the organizational links to master
production scheduling - Develop a master production schedule
- Explain rough-cut capacity planning
- Calculate available-to-promise quantities
- Describe time fence policies
3Role of the MPS
- Aggregate plan
- Specifies the resources available (e.g. regular
workforce, overtime, subcontracting, allowable
inventory levels shortages) - Master production schedule
- Specifies the number when to produce each end
item (the anticipated build schedule) - Disaggregates the aggregate plan
4Business Planning Hierarchy
5Planning Links to MPS
6Objectives of MPS
- Maintain the desired customer service level
- Utilize resources efficiently
- Maintain desired inventory levels
7Developing an MPS
- Assume
- Make-to-stock environment
- Production is in fixed quantities of 125 (MPS)
- 110 units in beginning inventory (BI)
8Sample Problem
- We start with 110 units in Beginning Inventory
- Projected Available How many units are available
at the end of each time period? - MPS Replenishment Shipments that need to arrive
at the beginning of the time period - Projected Available BI MPS - Forecast
9Step 1
- Find first negative projected available
We start with 110 units in Beginning
Inventory Projected Available How many units
are available at the end of each time period?
(safety stock criteria could be in place gt
5) MPS Replenishment Shipments that need to
arrive at the beginning of the time period
10Schedule Production
11Repeat
12Continue, Until Complete
13Evaluating the MPS
- Customer service issues
- Does available-to-promise inventory satisfy
customer orders? - What new orders can we take from customers and
when?
14Available to Promise
- When a customer places an order, they do not
expect immediate delivery (negotiable). - The product will delivered by some later date.
- ATP how many uncommitted units the company has
available at a given time
15New Calculation for Projected Available
- Projected Available
- BI MPS Max (Customer Orders Forecast)
16Available-to-PromiseAction Bucket
- Action Bucket the current period
- Only calculate ATP during in Action Bucket and
when MPS occurs - ATP action bucket BI MPS-customer orders
before next replenishment - 110 0 (3525) 50
17Available-to-PromiseReplenishment periods
- ATP for replenishment periods
- ATP MPS - customer orders between current MPS
and next scheduled replenishment - ATP period 3 125 (25 20) 80
- ATP period 5 125 (0 15) 110
18New Order
- Suppose we get an order for 200, can we accept
this for delivery in period 5?
19Worksheet for New Order for 200
- Fit in the order for 200 (cant change MPS)
20New Order for 200
- Negative number in Projected Available might be
a problem in the future - Negative number in Available to Promise always a
problem - Solution?
21Split up New Order for 200
- Check to see if this is OK
22Can you now take 2 more orders?
- 50 units to be delivered in Period 8
- 30 units to be delivered in Period 12
23Time Fences
24- Frozen no changes are possible with a certain
period of time (i.e. 8 weeks) - Time Fence (length of period schedule is frozen,
liquid, etc.) - Demand Fence MPS numbers do not change and focus
is on orders not forecast - Planning Fence Master Production Scheduler is
planning more MPS.
25Rough-cut capacity planning
- An estimate of the plans feasibility
- Given the demonstrated capacity of critical
resources (e.g. direct labor machine time),
have we overloaded the system?
26Rough-Cut Capacity Planning
- Determine required resources proposed workload
Hours/unit
27Calculate RequiredLabor Hours
- Compare with hours available
28Calculate RequiredMachine Hours
- Compare with hours available